HCFCD Asking to Tap Flood Resilience Trust for Bond Projects

Item #123 on the Harris County Commissioners Court Agenda for 6/28/22 is a request to tap the County’s Flood Resilience Trust Fund to help finance 16 flood-bond projects in the coming year. The request also seeks approval for a method of allocating future funds that weighs projects using a social vulnerability index.

A Backstop for Partner Funds

The introduction to the request states, “Although the Harris County Flood Control District (HCFCD) continues to aggressively pursue partnership dollars … substantial amounts of anticipated partner funding remain unrealized.”

Of the roughly $5 billion in 2018 Flood-Bond Projects, officials hoped that Federal, State and local partners would supply roughly half the money. But it hasn’t all materialized yet. So last year, Commissioners created a flood-resilience trust fund to create backstop funding. Until now, the county has not needed it. But now the county does…for the sixteen projects listed below.

Projects recommended for first round of backstop funding. Some of these projects started before the flood bond, were later included in it, and ran over budget.

To date, Harris County has secured $1.275 billion in partnership funding for 2018 Bond Program projects from Federal, State, and local partners. Of the $2.5 billion in partner funds originally anticipated, “the county has not yet identified $754.2 million. This gap includes projects for which grant applications were submitted to various Federal and State programs such as CDBG-MIT, FEMA-BRIC, and others but not awarded,” says HCFCD.

Ironically, the backup documentation provided to commissioners by HCFCD makes no mention of the $750 million allocated by the U.S. Department of Housing and Urban Development (HUD) and the Texas General Land Office (GLO) to Harris County. More on that below.

Ranking Methodology

The document provided to commissioners by HCFCD contains information about the Trust, its history and intent, projects that need funding help now, and a methodology for ranking projects.

After ranking all flood-bond projects that are short of funding using the proposed matrix below (Appendix B), the county began whittling away from Trust funds. HCFCD started with the top-ranked project and proceeded to the lowest until the money ran out, i.e., the balance in the trust fund went negative. Only two projects from the entire San Jacinto Watershed made the “eligible” list: one near the ship channel and another below Highway 90. But neither of those is part of the group of 16 above.

Weighting Factors in Proposed Matrix

The scoring matrix used by the County includes evaluations of:

  • Cost per person (15%)
  • Cost per structure (30%)
  • Non-structural benefits (45%)
  • Existing conditions (20%)
  • Social Vulnerability Index (20%)
  • Long-term maintenance (5%)
  • Minimizing environmental impacts (5%)
  • Ability to deliver multiple benefits, i.e., flood mitigation, social and environmental (5%)

As additional partnership funding sources are identified, money remaining in the Trust may cover additional projects…assuming inflation doesn’t eat it all up.

For this exercise, HCFCD analyzed all projects with partnership funding gaps. However, that doesn’t mean that those projects will necessarily receive Flood Resilience Trust funds. When and if HCFCD identifies funding partners, some projects could drop off the list of those needing help. That could make funds available for lower ranking projects. See Appendix B, last page.

Future Plans

If approved, HCFCD will return to Commissioners Court twice each year with additional requests from the Flood Resilience Trust. Each of those requests will include an updated analysis of partnership and contingency funding needs, Trust funds remaining, and eligible projects.

HCFCD will request money from the Trust only when projects cannot move forward without it.

$750 Million HUD Allocation Not Discussed

The County’s Community Services Department is currently developing a Method of Distribution (MOD) for the $750 million designated earlier this year for Harris County by HUD. A MOD is a plan for distributing the $750 million. Where and how will the county use the money? Who will benefit?

HUD and the GLO require that at least 50% of the money benefits Low-to-Moderate Income neighborhoods.

At the time the GLO and HUD dedicated $750 million to Harris County, they also dedicated $488 million to the Houston Galveston Area Council (HGAC).

HGAC has already submitted its MOD to the GLO and received preliminary, conditional approval. Conditional approval requires:

  • Validation of all calculations
  • Meeting HUD requirements
  • Verification that all recipients are still interested in participating.

According to a GLO spokesperson, HGAC began developing its MOD when the GLO submitted its action plan to HUD. However, Harris County reportedly delayed planning until AFTER HUD approved the GLO’s recommendations.

That delay could mean spending more local money. And that could penalize Harris County watersheds farther down on the Trust Fund priority list that don’t currently meet SVI and other requirements. Will there be money left for the Lake Houston Area by the time we work our way further down this list? Only time will tell.

Posted by Bob Rehak on 6/28/2022

1764 Days since Hurricane Harvey

May Flood-Bond Update Shows Spending Drought in Lake Houston Area Continues

The Harris County Flood Control District (HCFCD) posted the June 2022 status of 2018 flood-bond expenditures for Commissioners Court last Friday. Among the report’s highlights: the spending drought continues in the Lake Houston Area where only two capital improvement construction projects are active. Their total reported value: $2 thousand. That’s out of more than $235 million in active construction projects during the month of June.

Said another way, the Lake Houston Area is getting less than one-thousandth of 1% of the construction budget (0.000851%). March and April updates show that no new capital improvement construction projects have started in the Lake Houston Area in months.

See last page of full report for high resolution version. Note spending drought in NE portion of county.

Project Highlights

In the good news category, HCFCD:

  • Completed the $480 million Project Brays
  • Finished detention Basins near Little York and Hopper in the Halls Bayou Watershed, with combined 200 acre-feet of storage.
  • Wrapped up Halls Bayou conveyance improvements
  • Began demolition of the old Raveneaux Country Club on Cypress Creek
  • Started drainage repairs in the Carpenters Bayou watershed
  • Issued a purchase order for the Atascocita Area Drainage Study, which had been approved on February 8.
  • Released the Phase II, 1800-page report on flood tunnel feasibility

Spending Breakdowns by Watershed

Harris County contains 23 major watersheds shown below.

The 23 watersheds in Harris County and the amount spent to date from all sources under the 2018 flood bond.

The table and bar graph below make the rank-order and relative magnitude of spending in various watersheds more apparent.

Spending by watershed ranked from high to low. San Jacinto is middle of pack despite being largest watershed in county,
Bar graph of table above.

Factors Affecting Watershed Spending

Several factors affect the magnitude of spending in each watershed. They include:

  • Equity Prioritization Framework – This scoring matrix gives higher priority to projects in low-to-moderate income watersheds that have a high social vulnerability index. Projects with high scores started sooner.
  • Project Lifecycle Stage – Generally speaking, the earlier a project kicked off, the further along it is in its lifecycle. Studies have completed and construction has started or even completed. Some areas that flood repetitively had engineering studies completed and were already shovel-ready after Harvey.
  • Repetitive damage to population centers – More damage in highly populated areas gets more attention.
  • Prior Investment – Sims had massive investment by the Army Corps before Harvey and, comparatively speaking, had less flooding than other watersheds.
  • Partner Funding Availability – Projects with committed local, state or federal matches get higher priority.
  • Buyouts/Right of Way Acquisition – Sometimes entire subdivisions must be bought out to make room for flood mitigation projects. This can delay construction for years.
  • Lobbying – Squeaky wheels play a role on multiple levels.

Usually, no one factor accounts for a project’s or an area’s ranking. But multiple factors – working together – can push an area up or down the list.

Certainly, some areas have suffered spending-wise because of political priorities.

Other Highlights

HCFCD spent a total of $1.05 billion through the end of May. That compares to $1.025 billion through the end of April. So HCFCD spent $25 million in May.

Of the $1.05 billion spent to date, bond funds comprised $545 million. Grants comprised $367 million. And $140 came from other local funds.

HCFCD reported a schedule performance index of .97. That means projects are running slightly behind schedule. On-schedule performance would have earned a 1.0.

Overall, HCFCD has completed 21.8% of the bond projects when we’re 37.5% of the way through the 10-year program (45 months out of 120).

For the complete June update on bond spending, click here. Remember to review the last page. It shows capital improvement construction projects throughout the county and the spending drought in the Lake Houston Area.

Posted by Bob Rehak on June 26, 2022

1762 Days since Hurricane Harvey

Editorial: Contrived Ignorance in Flood Mitigation

Last week, one of the biggest issues in Harris County flood mitigation came into sharp focus for me: contrived ignorance regarding flood-bond spending. Three things brought it into focus:

  • The completion of the $480 million Project Brays, the largest in Harris County Flood Control District’s (HCFCD) history. The Brays watershed has 58% low-to-moderate income (LMI) residents.
  • Commissioner Rodney Ellis’ repeated assertions that FEMA discriminates against projects in LMI neighborhoods, and that “all the funding” is going to affluent neighborhoods.
  • HCFCD’s release of the May update on flood-bond spending. It showed that less than one one-thousandth of one percent of active flood-bond construction dollars are going to the entire northeastern part of the county (Kingwood, Huffman, Humble, Atascocita, and Crosby).

Ellis keeps rubbing me the wrong way. Why inflame racial distrust, Rodney, with statements so far from the truth?

Ignorantia Affectata

I’ve always had trouble understanding politicians who deny reality. But it turns out Thomas Aquinas, the great Catholic theologian and philosopher from the Middle Ages, described the phenomenon 800 years ago. He called it ignorantia affectata, a Latin phrase meaning “affected or cultivated ignorance.”

I found a great description of it on this blog. “The deniers first deceive themselves that they are sincere in their adherence to falsehoods. Thus they cannot be faulted for acting on genuinely held views. But in truth, they have cultivated an ignorance of the facts, an ignorance so useful that one protects it at all costs … in order to continue using it in one’s own self interest.”

David Luban, a professor at Georgetown Law, wrote a brilliant essay on the ethics of “Contrived Ignorance” (a related concept) and the law. It begins with a poignant description of how criminal defense attorneys discourage defendants from telling them everything they know. Admitting guilt could limit their defense of the client, because the law forbids lawyers from lying or knowingly putting on perjured testimony. Luban also touches on another related concept, plausible deniability, so common in politics and business.

Plausible Deniability No Longer Plausible

After Ellis spoke at the ribbon cutting ceremony – for the largest project in flood control history – he can no longer plausibly deny that poor neighborhoods can’t get flood-mitigation funding. They do!

But he tried. He trotted out his tired distortion about higher value homes in affluent neighborhoods skewing benefit/cost ratios. The problem: it ignores density. Higher density more than compensates for higher value homes. And in fact, from the ribbon cutting ceremony one could see apartments several stories high, stretching blocks in all directions.

While Ellis leads people to believe that projects in LMI areas struggle to achieve Benefit/Cost Ratios above 1.0, Project Brays had a 7.0 ratio. That’s extremely high. See this 2019 Federal Briefing. It will return $7 for every $1 invested!

Rodney Ellis at ribbon cutting ceremony for the $480 million Project Brays. The project helps reduce flood risk in neighborhoods where Ellis grew up and also where he now lives.
Brays Bayou, looking west toward medical center from Almeda Drive.

Contrived Ignorance Vs. Informed Debate

The problem with contrived ignorance is that it prevents informed debate. Why would you look for evidence that undermined your world view? That prevented you from reducing flood risk in your neighborhood even further?

Why use the commonly accepted dictionary definition of “equitable” when you can redefine the word to serve your self interest?

I find it incredible that in 18 months, a majority of the Community Flood Resilience Task Force:

  • Has failed to define “worst first.”
  • Refuses to discuss what percentage of flood-mitigation funding affluent neighborhoods should get.
  • Won’t admit that flood-mitigation projects have already been built in their neighborhoods.
  • Is arguing about how to float another flood bond for $60 billion when we’re only 20% complete with the first $5 billion.
  • Won’t discuss whether 2-year flooding in affluent neighborhoods should be fixed before 500-year flooding in LMI neighborhoods.
  • Attributes past flooding to racially motivated neglect without examining the role of development practices
  • Recommended that HUD pay people only from poor neighborhoods to protest the unfair distribution of flood-mitigation funds.

When you try to discuss actual facts in Task Force meetings, shocked silence often greets you. Members keep talking about how they want facts. But a full year after requesting flood-risk data, no one seems concerned about the fact that they haven’t gotten it yet. Could this be what Thomas Aquinas meant?

Posted by Bob Rehak on 5/30/22

1735 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Of Active HCFCD Bond Construction Spending Totaling $226 Million, Lake Houston Area Has $2 Thousand

Harris County Flood Control District (HCFCD) delivered its March 2022 Flood Bond Spending Update yesterday to Commissioners Court. It shows $226,476,745 dollars worth of active capital construction projects underway throughout the county. But only two of those valued at a grand total of $2,000 are in the Lake Houston Area.

That’s less than one-tenth of one percent, despite the fact that the Lake Houston Area was one of the most heavily damaged in the county during Harvey.

Maintenance Costs Harder to Determine

The update also includes active maintenance projects. However, those are grouped in ways that make it difficult to determine the exact cost of each. The Lake Houston Area had 3 out of 36 of those. At least one of the three is now complete. It consisted of cleaning a block-long stretch of the drainage ditch that parallels Stonehollow Drive in Kingwood. Judging by the group costs, none of the three qualifies as major.

The update does not disclose the value of past projects. Nor does it break out the value of studies, right-of-way acquisition, or future improvements.

For the full update, click here. I compiled the numbers above from the last two pages in the PDF. To see the location of projects, check the HCFCD’s Flood Education Mapping Tool. It shows the number of every ditch and stream in Harris County.

Other Insights

The report yields many insights.

  • 19.7% of the bond work has been completed as of the end of March. That’s up from 19.4% at the end of February. That percentage should increase faster as HCFCD completes more preliminary studies and moves into the expensive phases of projects, such as right-of-way acquisition and construction.
  • Of 1175 buyouts identified, 457 have completed – 39%.
  • Biggest winners to date in the flood-bond, mitigation-funding sweepstakes have been:
    • Brays Bayou – $173.1 million
    • Cypress Creek – $87.4 million
    • Greens Bayou – $82.7 million
    • Addicks Reservoir – $75.4 million
    • Little Cypress Creek – $53.7 million
    • White Oak Bayou – $53.2 million
    • Clear Creek – $38 million
    • Halls Bayou – $35.4 million
    • Hunting Bayou – $34.1 million
    • Willow Creek – $33.5 million
  • The San Jacinto River watershed has received $20.7 million despite being the largest in the county.
  • HCFCD completed two projects during the month and began construction on one other.
  • Eight other projects changed stages, i.e., from feasibility study to preliminary engineering.

“Partner Funds” To Date Virtually Equal “Bond Funds”

Virtually half of flood bond spending through the end of March 2022 came from partner funds. Local funds plus grants totaled $483 million. Money spent out of the bond itself has totaled $492 million. So, 49.5% of spending to date came from partner funds. It has gone largely to watersheds supposedly disadvantaged by partnership requirements. A popular political narrative claims low-to-moderate income watersheds get no partner funding and more affluent watersheds get it all. But that simply isn’t true.

The narrative is being used to accelerate the start of projects in LMI neighborhoods by decoupling grant approval and project initiation. However, as these numbers show, turning our backs on partnership funds could potentially double the cost of flood mitigation.

49.5% of mitigation dollars to date have come from partners. 50.5% came from the bond itself.

Glaring $750 Million Omission

Although the March update contained a discussion of several partnership grants, it failed to mention $750 million allocated to Harris County by HUD and the GLO for flood mitigation on March 18. The March update did, however, discuss several smaller grants, earmarks and partner funds. Those took up two and a half pages.

The $750 million, together with the flood resilience trust approved last year, would fully fund the flood bond. That means that no watershed should have to wait on partner funding for construction projects to begin once engineering is completed.

Only one step remains before Harris County can start using the money – approval of a “method of distribution.” That’s a final plan for how and where the money will be used.

Posted by Bob Rehak on May 11, 2022

1716 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Editorial: “Chaos” in Harris County Government

Two weeks ago, I wrote a post about the brain drain at the highest levels in Harris County government, and its impact on productivity and service delivery. Sixteen departments have had a total of 34 leaders under Lina Hidalgo.

Since then, dozens of people have contacted me describing the impact of turnover on programs and service.

One manager used the word “chaos” to describe the environment since Lina Hidalgo took office. All of the sources for this post have requested anonymity because they fear reprisals – a chilling comment in itself.

No doubt, many good, talented, hard-working people remain in Harris County government, but the problems described below make it harder for them to do their jobs.

Unexplained Changes in Direction

One person told me about a new Harris County juvenile center that was being planned, due to overcrowding and substandard living conditions at the old center. Then one day, “…like out of nowhere, we got a sense that the whole project was canceled. We tried to explain how far along the project was and why it was necessary. And they didn’t care. It was just like, ‘Well, we [the judge’s office] are not going in that direction.’” The source added, “We had a lot of things in motion that just came to a halt.”

The new center never did get built. It had reportedly gone all the way through the design phase, so the unexplained cancellation was costly.

Not So Resilient Resiliency Plan

Another person mentioned a county-wide resiliency plan. The heads of multiple Harris County departments had worked on it for months. At the eleventh hour, people in Hidalgo’s office with no experience rewrote everything that people with experience had developed. “It just changed completely,” said one person involved.

Transportation Plan Stalled

Yet another person told me, “In Hidalgo’s mind, if you’re building a road, you’re doing taxpayers a disservice. Philosophically, she’s into multi-modal transportation. But a lot of times, she misses the point that the county is only allowed to do what the state of Texas allows it to do. That’s where they’ve had more problems. Their thought process a lot of times was, ‘Well, if they want to sue us for that, then they can.’ We’ve seen that play out several times.” 

Other sources told me about progress on various components of Harris County’s Transportation Plan. 

  • There has also been little to no movement on the county’s Multimodal, Major Thoroughfare plan to improve connectivity.
  • The Equity Study has stalled. So has a framework to implement it. There has been no movement on equity in transportation.
  • Likewise, there has been little to no movement on Vision Zero, the county’s effort to eliminate traffic fatalities. 
  • Nothing notable has happened lately on Low Impact Development, Green Infrastructure, or other environmentally-friendly projects.

Lack of Clarity, Direction

Another major problem contributing to the chaotic work environment: lack of clarity and direction. One mid-level manager told me, “We would often be moving in a direction when everything kind of went on pause because we were waiting to see which direction to go. But we couldn’t ever narrow down a direction. It felt as if, in every single Commissioners Court meeting, we spent all day watching mommy and daddy fight. Even among the Democrats.”

Lack of Attention to Operational Details

Former managers of various Harris County departments also complained about lack of attention to operational details. 

“Ellis’ office and the Judge’s office would work together to develop these big picture concepts of where we were going. But it was never clear how we would get there,” said one person.

“We’d sit there and go, ‘Well, that’s great. But you didn’t set up any funding for it. For example, we talked about big sweeping programs like MWBE – the Minority/Women-owned Business Enterprise program. That was four years ago and it’s still not off the ground.”

Hiring People Without Relevant Experience

They hired Pamela Chan to set up the new Harris County Department of Economic Equity and Opportunity. According to one person I talked to, Chan was a “a great academic,” but had no real-world, operational MWBE experience. Another said, “the guidance and support that Chan got was like almost nil and then she’d get beat up at court.” She soon left. That department has had two executive directors in a little more than a year. 

Universal Services, the County’s information technology (IT) department, has the same problem. Its leader, Major General Rick Noriega has no IT background. Think what would happen if you put a computer programmer with no military experience in charge of a tank battalion. You’d probably have a high casualty rate. And that’s exactly what happened in Universal Services. 

100% of Group Heads Leave Within 17 Months

According to many of his employees, Noriega’s lack of IT understanding contributed to high turnover beneath him at multiple levels. And that rapidly compromised the integrity of systems. 

Noriega also pushed out people with excellent professional credentials and replaced them with political appointees in many cases.

Not long after Noriega took over the department, he lost his Chief Administrative Officer, Chief Operating Officer, Chief Technology Officer, and Chief of Cybersecurity (twice). 

The department also lost 100% of its group directors beneath them and approximately one third of its employees in 17 months. 

So many employees have left that the department doesn’t even put names on org charts anymore. 

Incomprehensible Org Chart Without Names Revised More than 30 Times

In fact, the department doesn’t even call organization charts ‘org charts’ anymore. It refers to them as its “ecosystem.” See below.

Harris County Universal Services Ecosystem Chart, Revision #25. For a high resolution, full-size PDF click here.

At this point, the chart above has reportedly gone through more than 30 revisions under Noriega. Yet multiple sources told me, “No one understands it.”

Toxic Work Environment Accelerates Already High Turnover

The work environment in Universal Services has become so toxic according to sources that approximately one third of the department has left in 17 months and the rate of attrition is reportedly accelerating. 

Universal Services org charts updated the day before Commissioners Court appointed Noriega the permanent department head show everyone who left since his arrival. The source told me that some positions have turned over more than once. So this 12-page chart understates the numbers involved. It shows that at least 134 people have left since Noriega assumed command. That’s out of approximately 400 to 450 total employees. The highlighted names represent people who left the organization in the last 17 months.

One third of a workforce turning over would not be surprising in fast food. But these are professional jobs with highly skilled people doing complex work that few understand.

Noriega reportedly tried to dismiss the turnover. But significantly, 100% of his group directors left, leaving much of the department rudderless, especially since Noriega did not have an IT background himself.

Page 2 of 12-page Harris County Universal Services Org Chart as of 9/21/22. Highlighted group directors have left. To see turnover at lower levels, click here.

Most employers, especially in government, try to hold attrition to 10% or less. High turnover disrupts service. It also costs time and money. This survey found that replacing workers costs an average of 33% of their yearly salaries.

If that percentage holds true in IT, losing one third of your workforce would cost one third of your payroll. 

Self-Inflicted Damage

Some damage has been self-inflicted. While most IT companies let employees work remotely, Noriega forces managers to come into the office. This policy goes against the industry norm and has reportedly contributed to several of the departures at the managerial level. 

“It’s Scary.”

One former IT employee told me Universal Services has refilled so many positions with inexperienced people that “They can’t even support the simple stuff. It’s scary.” This person called the replacements “Garcia’s puppets.” 

Commissioner Adrian Garcia recommended Noriega for the job. Another Garcia loyalist, James Henderson, is Universal Services new Deputy Executive Director and Chief Operating Officer. They have reportedly replaced many departing employees with people loyal to Garcia.

Can It Be Saved?

When the department’s crucial JWEB program went down recently, IT staff reportedly worked 8 hours on and 4 hours off around the clock trying to restore the system. But they couldn’t get it back up. So, hundreds of criminal suspects didn’t receive probable cause hearings in time and had to be released.

A former manager in the department told me, “I don’t think enough meat is left on the bone to fix what’s going on there.”

Harris County’s annual budget next year will exceed $3.5 billion. We’re one third of the way through a $5 billion flood bond. And these are the custodians of our tax dollars.

Posted by Bob Rehak on 5/1/2022

1706 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

More than $400 million in Unexplained Harris County Transfers Receive No Discussion During Rants On Other Items

A Harris County Commissioners Court meeting yesterday lasted 8 hours and 30 minutes. While viewers were repeatedly treated to rants alleging racial discrimination, partially documented transfers of approximately $470 million received absolutely NO discussion.

Let’s begin with the rants. Here’s one example. A revision to equity guidelines for the Flood Resilience Trust consumed 20 minutes of discussion including a 6-minute monologue from Commissioner Rodney Ellis. In essence, Ellis said, “I support the new formula” in 894 words. I transcribed the rant in its entirety below. See if you can follow it. Among other things, Ellis:

  • Says he hopes to reduce a HUD appropriation from $750 million to $250 million. 
  • Confuses the County with the City; and flood mitigation with parks and police. 
  • Drags Harris Health into the discussion for some unexplained reason. 
  • Invokes ‘back of the bus’ language to describe watersheds receiving the lion’s share of funding. 
  • Threatened to sue a federal agency trying to give the county $750 million.
  • Claims the County didn’t make specific project recommendations/allocations for the flood bond (which it did).
  • Overlooks the contribution of partner funding to build a case for not chasing partner funding.

It gets better! Read on.


Rodney Ellis on New Equity Formula

“Commissioner Garcia, some of the issues that you were raising and Commissioner Ramsey were raising, I think that this proposal for prioritization-framework modifications will address some of them. Commissioner Ramsey, first of all, I want to point out that the 2018 package of $2.5 billion would in no way fund all of the projects that people talked about. I also want to reiterate that coming off city council a long time ago, I argued to list specifically what the projects were. It was a short fuse. If you remember Commissioner Cagle, you might agree with me. I was worried about having the election in August, as opposed to when more people would show up.

“But I didn’t win that battle and it passed despite my misgivings. But we were on a short time frame and I was told you cannot lay out the specific projects, because if a project…If you put in 20 million and it costs 50 million, can you get the creek? Or you put in 50 million and it costs 40 million and it didn’t quite sound right to me. Because unless the city did a better job of projecting what parks and police command stations will cost, you know, inflation. But that’s what was said. And I was not going to argue with it and didn’t think I had the support of the court anyway.

“But 2.5 billion was never going to fund all of the items that were on the radar, shall we say, because a decision was made not to lay them out with specificity was how to do a cap improvement program. I also want to say that to my knowledge, maybe others’, two projects had come to my mind that weren’t on the radar. One was in your precinct. The education project came from them.

“The other one was in another county – Commissioner Cagle’s area. I don’t know where it is now, buying some land in another area that certainly had some political gravitas to it.

“I argued for two things. The varnish was coming off. What I wanted to despair to say, and everybody said that they were for getting rid of disparities until it was time to vote. Send somebody to do statistical analysis to see if they had one. And I was told, you pay for it. And you can do it. So Precinct One paid for it. Thank you to the women. Precinct One, you added $660,000 back. And of course, it showed there was a tremendous disparity. I would encourage you to listen to Harris Health’s discussion of why they’re going to lay off the expert study off. So it will be interesting to see what Bert came up with, but that’s history. Going forward, we will do better as we are doing better here, I think. 

“The other item I wanted was the equity guidelines. Now, once it passed, there were those who thought equity meant just split 2.5 billion…four ways…which would be highly inequitable if we all agreed that chasing federal money with a cost benefit ratio and a host of other issues meant certain neighborhoods that flooded all the time didn’t get funding regardless of why, chasing federal money, that’s what happened. So all of these projects were started. We know three big ones, Commissioner Garcia, in your precinct and mine, and might touch all our precincts, in Halls and Greens.

“We were chasing GLO money or federal money that never came, so they were delayed. So, then resiliency was created as a way to get stuff here created to fill up the gap. And whether or not it would fill it all up, I don’t know. But I, for one, would not just talk the talk. You got to pay for it, pay for it. Or maybe politely find a way to just pass a resolution and say you resolve to do it down the road. This prioritization framework makes sense because it places a greater emphasis on the number of people that a project would address instead of what neighborhood you live in.

“I can’t say it enough. Something’s wrong. When this county had a system where you protect the neighborhood I live in now, but the neighborhood I came out of – even if that one historically flooded more. It also says we do not consider partner funding as a factor because who gets partner money? Well, that’s part of the funding.

“The neighborhoods have always been privileged. It’s just that way. And we use the latest data to invest in projects that address structural delay both inside and outside the 100-year network. So, I can’t wait until you bring it up and I’m going to vote for it when it comes up.

“And I tell you, just as I’m proud of what Texas Housers did, and I’m proud of what HUD did to get us our 750. Hope we get down to 250 and I hope the city gets this bigger because they deserve it. We both do.

“And if we don’t follow prioritization framework like this, I will be the first one finding somebody to file a lawsuit and raising all kind of hell at HUD because we will continue to neglect those neighborhoods that have always been on the back of the bus. But other than that, thank you very much.”

– End of Ellis Monologue –


Diversionary Tactic?

How can one react to rambling, unsubstantiated rants such as this!

During the meeting, as I tried to look for backup on several agenda items, the county website froze on numerous occasions – shades of the IT debacle at Universal Services.

To set the record straight, Brays Bayou, the watershed in which Commissioner Ellis grew up AND in which he now lives, has received $575 million in flood-mitigation funding in the last 22 years. White Oak, the watershed where Commissioner Garcia now lives, has received $525 million in funding. That’s almost one third of all the flood mitigation money spent in the county since 2000 – on two watersheds out of 23. No watersheds have received more!

Flood mitigation spending in Harris County during first quarter 2022 and since 2000. Obtained via FOIA Request.

Greens and Halls received another $620 million. That makes $1.72 billion. And that’s 46% of all the flood mitigation money in recent history.  

More than one long-time Harris County insider has characterized such rants as a diversionary tactic. Elsewhere on the agenda yesterday was a motion to make “routine transfers” between departments (see Item 17). 

It received absolutely NO discussion and the Budget Management Department provided no backup for the agenda item. But the transfers totaled almost half a billion dollars. I had to obtain the backup through a special request. Notice how many of the transfers do not follow the industry standard for double-entry accounting – even though the forms request it.

Double-entry accounting shows where money is coming from and going to. That facilitates balancing the books and auditing. But in this case, the ‘from’ or the ‘to’ were omitted in 21 of 39 transactions for this year. Those 21 transactions alone totaled approximately $470 million.

I have no proof that anything illegal occurred and I’m not suggesting it did. But I am suggesting that Democrats, who pride themselves on transparency, could improve on that score.

Eight hour meetings filled with incomprehensible rants, agenda items without backup, backup that omits crucial elements, and a website that intermittently stopped responding during the meeting create barriers to public participation and government oversight.

Posted by Bob Rehak on 4/27/2022

1702 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Harris County still has not posted video of yesterday’s meeting. Here’s an audio recording of Mr. Ellis‘ rant so you can check the transcription yourself. He is admittedly hard to understand at times.

First Quarter 2022 Flood-Mitigation Spending Update, New Equity Formula

In the first quarter of 2022, Harris County Flood Control District spent a total of $84 million. That brought the total of flood mitigation spending since 2000 up to almost $3.8 billion.

For the first time since ReduceFlooding.com started tracking these numbers via Freedom of Information Act requests, spending in the Hunting Bayou watershed led all other watersheds. Brays Bayou, the previous front runner, dropped into second place. Cypress Creek, White Oak Bayou, Clear Creek, and Halls and Greens Bayous virtually tied for third place in spending. The San Jacinto Watershed came in 17th despite the fact that it is the largest in the county.

Watershed spending by Harris County Flood Control District last quarter and since 2000. Includes partner funds and all phases of all projects.

The Galveston Bay and Vince Bayou Watersheds had no invoices reported during the quarter. Totals for Jackson and Addicks were restated to account for a change in accounting, resulting in negative numbers. Previously HCFCD reported dollars spent by project management status. The District now reports totals by invoice date. The new method is more precise.

First Quarter 2022 Watershed Rankings

Negative numbers reflect adjustment for change in accounting described above.

Cumulative Spending Since 2000

Ratio between highest and lowest is almost 100 to 1.

Totals Since Harvey

Between Harvey and the end of 2021, HCFCD spent $1.45 billion on all watersheds. The $85 million spent in the first quarter of 2022 brings the total since Harvey up to $1.535 billion.

San Jacinto Watershed

Of the almost half million dollars spent in the San Jacinto Watershed during the first quarter of 2022, virtually all of it was spent on preliminary engineering and design. The Harris County Flood Control District shows only one active capital improvement construction project in the San Jacinto Watershed valued at $1,000. That’s the Excavation and Removal Contract on the Woodridge Village Property to develop additional floodwater detention capacity. Compare that to the $15.6 million spent on construction in Hunting Bayou.

Equity Formula Being Changed Again

The disparity in totals between watersheds largely has to do with Federal partner funding and the equity funding formula passed by three Democrats at Harris County Commissioners Court. The original formula has been revised again and again to send more and more funding to watersheds with high percentages of low-to-moderate income residents. Commissioners started debating another set of changes to the formula today that would apply to money in the Flood Resilience Trust, but did not vote on it.

The changes recommended include:

  • Prioritizing people over structures
  • Eliminating partnership funding from consideration
  • Recommending proxies for FEMA data since 1977
People Over Structures

This change would favor spending in densely populated neighborhoods inside Beltway 8 as opposed to neighborhoods with more single-family homes outside Beltway 8. For example, 100 people could live in an apartment building on a single acre. So could 3 people in a single family home. The only problem: Flood control has no way of determining how many people live in an apartment building. So the District will have to use an average for the watershed, according to Dr. Tina Petersen, the new head of flood control.

Partner Funding

Democrats don’t want to wait for partner funding. They want to start projects right away, using bond money and other funds diverted from the toll road. Using out of pocket money could speed up flood-mitigation projects in low-to-moderate income neighborhoods, but it could also reduce the size of the total pot, jeopardizing badly needed projects somewhere.

Dated Data

Using 1977 data would disadvantage areas outside the Beltway, which was under construction at that time. Places like Kingwood were just beginning to be built. So using the older data from the Seventies would stack the deck in favor of inner-city neighborhoods. However, there was no universal agreement on a suitable substitute for the FEMA damage claims.

“Who Goes First?” No Longer the Issue

These constant changes to an equity formula which was originally conceived as a “Who goes first?” tool, seem to make less and less sense now that all flood bond projects have started. So commissioners are considering these changes in regard to the Flood Resilience Trust. That money will theoretically allow development of more projects when the flood bond expires. But no one has yet determined the list of projects for that money. So Commissioners still have many details to work out.

One huge related detail is developing a plan for how to spend $750 million in HUD partner funds. The county administrator seems to have turfed the assignment to the Community Services Department. Said another way, they took it out of Flood Control and put it in a department that has had four leadership changes in four years.

Out of 154,000 homes in the county damaged by Harvey, Community Services managed to distribute only $21.4 million in repair funds.

No offense. I’m sure this is a difficult job. And I’m sure the county has talented people. But justifying flood-mitigation grants seems to be more of a job for engineers than people who handle claims. The adventure continues. More details in coming weeks.

Posted by Bob Rehak on 4/26/2022

1701 Days since Hurricane Harvey

Flood Bond Progress: 35% Time Elapsed, 19.4% Money Spent

A February update by Harris County Flood Control District (HCFCD) on the status of the 2018 Flood Bond showed that 35% of the way into the program (42 out of 120 months), 19.4% of the funds from all sources (including grants and partnerships) had been spent. That percentage was based on $967 million spent out of $5 billion projected.

Cost of Studies vs. Construction

While one percentage seems to lag the other by a factor of almost 2X, HCFCD estimates it is virtually on schedule. That’s because studies conducted up front cost far less than construction. And only 44 of 181 Bond program projects have entered construction at this point (24%). As more projects enter the construction phase, the pace of spending should accelerate.

From High-Level Summary to Nitty-Gritty Detail

The 13-page update features three major sections:

  • Summary statistics for the entire bond program
  • Project flow charts showing status of all projects
  • Watershed maps showing the amount spent to date; funded to date; and the values of all active maintenance and capital projects.
Spending by watershed on HCFCD flood bond projects through the end of February 2022.

Skewed Distribution of Capital Improvement Projects

Out of 75 active capital improvement projects, I counted only 13 in Precincts 3 and 4 which have Republican commissioners. Those contracts totaled only about $82 million out of about $249 million. That’s a testament to how thoroughly the Democrat-controlled Commissioners Court has relentlessly tweaked the Equity Prioritization Framework. For instance…

In northeastern Harris County, the update shows only two active capital projects valued at a whopping $1,000 each.

Of the 13 active capital projects in Precincts 3 and 4, six are E&R contracts valued at just $6,125 altogether. See page 13. The report lists no E&R contracts in Precincts 1 and 2.

Excavation and removal contracts let contractors sell dirt they remove from a site as a way of making back their normal profit margin. They’re a good deal for taxpayers as long as the demand for fill dirt remains high. But if demand slows, excavation progress could stall. In other words, they come with uncertainty attached.

Breakdown of San Jacinto Watershed Projects

Of ten bond projects listed in the San Jacinto Watershed, schedules show:

  • 4 in the feasibility-study phase
  • 2 in preliminary-engineering reviews
  • 1 in construction
  • 3 not yet started.

To see the full February Update presented at the March 22, 2022 Commissioner’s Court Meeting, click here.

The February report did not address a method of distribution for $750 million allocated by HUD and the GLO for flood mitigation to Harris County. The award happened on March 18, 2022 and will likely be covered next month.

Posted by Bob Rehak on 3/30/2022

1674 Days since Hurricane Harvey

How Do You Define “Worst First”?

In the rush to mitigate flooding after Hurricane Harvey, most people agreed that we should attack the areas with the worst flooding first. While almost everyone agreed with the “worst first” mantra, no one defined it – until after the flood bond passed.

Alternative Ways to Define “Worst First”

How would you define the “worst” flooding? The area with the:

  • Most flooded homes?
  • Most frequent flooding?
  • Most damage in dollar terms?
  • Largest population living in a 100-year floodplain?
  • Most low-to-moderate income residents who can least afford to fix their homes?
  • Largest minority populations?
  • Highest Social Vulnerability Index (SVI)?
  • Most damage to infrastructure (bridges, hospitals, grocery stores, schools, sewage treatment plants, etc.)?
  • Highest water above the tops of banks in a widespread storm like Harvey?

You could make valid arguments for each. And people have – almost from the day the flood bond passed – as they fought for more funding for their watersheds.

Least Considered Alternative

But the one I have heard talked about the least is the last one: highest water above tops of banks. Surely, the depth of a flood must count for something. It affects the ability to evacuate and rescue people. It puts lives at risk. Can destroy infrastructure. Spread sewage. Increase erosion. Even cause rivers to migrate. And sweep whole apartment buildings into rivers.

Yesterday, as I reviewed a doctoral thesis from a student at the Colorado School of Mines, I saw a graph that compared the height of the Harvey flood at the San Jacinto West Fork and US59 to other rivers/streams in the region. The West Fork flood towered above the others. So it made me wonder. How did the flood at that location compare to other streams and bayous in Harris County?

How to Determine “Feet Above Flood Stage”

There’s an easy way to find out. The Harris County Flood Warning System contains all the pertinent information.

  1. Go to the home page.
  2. Click on a gage.
  3. Click on the “For more information” link in the pop-up box.
  4. On the new page (dedicated to historical information about that gage), click on the stream elevation tab.
  5. Note the “flooding likely” elevation. This roughly coincides with the top of bank, though banks can vary slightly.
  6. Scroll down to the bottom of the page and note the elevation of the flood at that location during Hurricane Harvey.
  7. Subtract the “flooding likely” level from the Harvey level, to determine the feet above flood stage in Harvey.
  8. Click on the drop-down box with the gage information to compare the same stats for additional gages.

North Harris County Had Highest Floods

This morning, I compiled the data for 33 gages. The chart below shows what I found. Of the gages I sampled, the four highest floods all occurred in the upper San Jacinto River Basin: West Fork at 59, Spring Creek at 45, Cypress Creek at Cypresswood, and West Fork at 99. Also note the preponderance of high water along Greens Bayou at numerous locations.

Data compiled from Harris County Flood Warning System using the technique described above.

Limitations of Measure

“Feet above Flood Stage” by itself won’t tell you which area had the worst flooding during Harvey. It’s just one measure. You must consider other factors, too, such as those listed above.

But this chart sure makes it hard to ignore the fact that something is happening in north Harris County to exacerbate flooding. I’ve chronicled many of those things in the pages of this website: sand mining, development, rapid growth, impervious cover, loss of wetlands, lack of detention ponds, lax regulation/enforcement and more.

One must also acknowledge the role that topography plays in a chart, such as this. A narrow floodplain with steep banks can force water higher. A wider floodplain through a flat area allows water to spread out, lowering the height of floodwaters.

Variations in rainfall across an area can also skew results.

And finally, I didn’t click on every gage in the region. There are hundreds. You wouldn’t have been able to read the chart because the type would have been so small. So investigate on your own and let me know what you find.

Need for Active Discussion/Debate in Upcoming Elections

The Harris County Community Flood Resilience Task Force just voted to change the way “worst first” is calculated – again! The highest correlation between funding and all of the other factors I have evaluated is now with low-to-moderate-income population. It’s not with damaged structures, dollar damage, watershed size, or population density.

If you want to ensure that outlying areas get their fair share of flood mitigation dollars in the future, you need to demand them when you go to the polls this fall.

Posted by Bob Rehak on 3/29/2022

1673 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

HUD Approves $750 Million to Harris County for Flood Mitigation

Today, the U.S. Department of Housing and Urban Development (HUD) approved the Texas General Land Office’s (GLO) amended plan for Community Development Block Grant Mitigation (CDBG-MIT). The amended plan allocates $750 million in funding for Harris County and an $488 million to the Houston-Galveston Area Council for additional mitigation projects in the region. The funds allocated to the county should now mean that the 2018 flood bond is fully funded, if numbers provided last month on partner funding to date are accurate.

George P. Bush Quote on Process

According to a press release issued by the GLO at 7PM, 3/18/22, “Ensuring Texans receive disaster recovery and mitigation funding in a timely manner to recover from Hurricane Harvey has always been my top priority,” said GLO Commissioner Bush. “The Biden Administration’s politically weaponized Department of Urban Development and Housing has forced us to fight through mazes of red tape to secure this direct allocation for Houstonians. I will continue to fight to send money to Texans as quickly as possible. The $750 million allocation will go directly to Harris County for projects that help mitigate future flooding events, creating a stronger more resilient Texas.”

George P. Bush, Commissioner, Texas General Land Office, 2019 photo

$1.138 Billion Total

HUD’s approval of the latest Harvey Action Plan brings the total infrastructure and mitigation investments in Harris County to more than $1.1 billion. HUD’s approval of the GLO’s plan to provide $750,000,000 to Harris County is in addition to HUD’s direct allocation of $61,884,000 to the City of Houston, plus $117,213,862.96 in CDBG-MIT awards for Harris County projects, plus $209,221,800 in infrastructure funds from CDBG-DR, equals $1,138,319,662.96 in total investment in projects within Harris County. Additionally, H-GAC continues to develop its method of distribution on more than $488 million for mitigation projects within the greater Houston region.

Bush first requested a direct allocation for Harris County in May of 2021 after the county received very little money from the first round of competition for HUD. A direct allocation would have allowed Harris County to work directly with HUD and taken the GLO out of the loop. However, HUD reportedly insisted that the GLO remain involved. Subsequently, the GLO developed a 650-page action plan for the $750 million. However, HUD found it insufficient. As of early this week, the action plan exceeded 1000 pages, according to a GLO spokesperson. That apparently provided HUD what it needed. HUD notified the GLO in a letter received after 5PM today.

Method of Distribution Must Still be Developed

However, Harris County won’t get all the money immediately.

Since last November, H-GAC has been developing something called a MOD (Method of Distribution) for its allocation. However, according to the GLO, because of the expense involved, Harris County has delayed developing its MOD until the the award was approved by HUD.

Harris County’s next step will be to develop its MOD which describes where the money will go, how it will be used, and who will get it. GLO will review that and forward it to HUD. After HUD approves the MOD, HUD still won’t write a check for $750 million to the county. The money will be reimbursed to the county in batches as it is spent on approved projects.

Flood Bond Close to Fully Funded Even without Resilience Trust

Still, this will go a long way toward fulfilling the potential shortfall in partner funding for the Harris County Flood Bond. Of the original $5 billion bond, half is being paid for by Harris County taxpayers. The County hoped to get local, state, and federal partners to fund the other half.

Last July, when it looked like the $750 million might not materialize, Harris County Commissioners approved a Flood Resilience Trust that committed $833 million from the Toll Road Authority and other Harris County sources of funding. That, along with partner funding already committed, was enough to keep construction of Harris County Flood Bond projects rolling through approximately 2026.

From a presentation to the Harris County Community Flood Resilience Task Force in February 2022.

Today’s approval should make the flood bond fully funded if the numbers above are accurate. That should come as good news for all citizens who have been fighting for limited dollars. With money in the trust, this should accelerate mitigation projects throughout the county. And even fund some not identified in the original bond!

Posted by Bob Rehak on 3/18/2022

1662 Days since Hurricane Harvey