Wasted Time, Money Could Have Built All Flood-Bond Projects in Seven Poorest Watersheds
11/19/26 – Time and money squandered by Harris County Flood Control under its previous director cost more than it would have taken to construct every flood-bond project in seven watersheds with the County’s highest percentages of Low-to-Moderate Income (LMI) residents.
Time Lost
Almost from the moment that the 2018 Harris County Flood Bond passed, it became mired in politics. Judge Ed Emmett subsequently lost his 2018 re-election bid. Lina Hidalgo won. Democrats gained a majority on Commissioners Court. They implemented a controversial “equity prioritization plan.” They also pushed out highly qualified professionals running the Flood Control District and brought in a new, ineffective executive director who slowed things to a crawl. The graph below shows spending by year up to the point she left in June 2026.

Precinct 2 Commissioner Adrian Garcia defended the past executive director (whom he pushed for the job) long after other commissioners and Judge Lina Hidalgo lost confidence in her. She finally resigned under pressure in June 2026.
“Time is money” as the saying goes. The slowdown affected possibilities in several ways.
Losses Due to Inflation
We lost an estimated 30% of the purchasing power[1] of the flood bond due to inflation during the previous director’s tenure. Thirty percent of $4 billion[2] left in the bond and partnership funds when she assumed office is approximately $1.2 billion lost.
Losses Due to Bad Estimating
Taxpayers lost another $113 million due to bad estimating under the previous director. A report by the new director showed that the previous director inflated construction estimates when applying for federal grants. Actual construction bids came in far lower.
Had the estimating been more accurate, HCFCD could have done more projects with available grant money. At this point, it’s probably too late to get additional projects approved to use up that money.
Losses Due to Slowness
HCFCD’s new executive director has accelerated construction activity 6X. Regardless, he estimates HCFCD will lose another $207 million in federal funding due to projects that will finish after already extended deadlines.
Totaling the Losses and Their Impact
Altogether Harris County taxpayers have lost at least $1.52 billion in the original flood bond:
- $1.2 billion lost due to inflation
- $117 million lost due to bad estimating
- $203 million lost due to missed deadlines
What We Could Have Bought with $1.52 Billion
The table below shows the total value of ALL projects in the flood bond by watershed.
It also shows those watersheds ranked by the percentage of Low-to-Moderate Income (LMI) residents within the total watershed population. The seven shaded watersheds have a grand total of $1.434 billion.

The money we lost was enough to pay for every project in every one of the seven shaded watersheds above. Or a quarter of all projects in the entire bond.
If We Focus Only on Equity, We’re Focusing on the Wrong Question
This loss of purchasing power is reigniting debates over “equity” and “historical discrimination.” With almost half of the flood bond money already spent, other watersheds should be getting the attention they were promised. But some people are pushing to finish remaining projects in LMI watersheds first.
That will leave projects in other watersheds without funding. Thanks to Adrian Garcia.
Elon Musk took approximately five years to develop the system that catches rockets returning from space. The flood bond passed eight years ago. And it’s about digging holes in the ground.
Meanwhile, the San Jacinto watershed had the highest flooding in the county during Harvey. And yet it has received only 14% of the dollars promised.
And the Halls Bayou watershed, the poorest in the county, has received only 16% of the money promised to it.

In my opinion, the debate should not be about equity. It should be about speed.
Posted by Bob Rehak
3370 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
[1] 30% inflation rate was estimated by Dr. Tina Petersen, previous head of the Flood Control District. It also coincides closely with the cumulative inflation rate estimated by TXDoT during Petersen’s time in office. TXDoT and HCFCD are both in the construction segment of the Texas economy and both deal with cement, dirt, trucks, diesel fuel, etc.
[2] Total dollars in the Flood Bond stand at $5.3 billion. When Petersen took office, $1.1 billion had already been expended. I obtained $1.3 billion lost to inflation by multiplying $4 billion by 30%. While the $4 billion is rounded down, it provides a conservative estimate.




















