Kingwood Diversion Ditch Project Delayed Again
3/13/26 – Harris County Flood Control District (HCFCD) has asked for a 20-month extension on the Kingwood Diversion Ditch Project scheduled to take 24 months. The original period of performance for the contract was from 4/1/24 to 4/1/26. But backup provided to Commissioners Court shows HCFCD doesn’t even expect to give the vendor a notice to proceed until 4/27/26.
The announced reason for the extension request: “…an unforeseen delay in project cost negotiations to remain within budget…”
“Who negotiates with a vendor for two years on a job with a two year deadline?”
Bob Rehak
See Item #148 on the agenda for March 19, 2026 and the explanation sent to commissioners and the EPA (the grantor).
Top Priority or Lowest?
The Kingwood Area Drainage Analysis recommended expanding the Diversion Ditch as the top priority in Kingwood in 2020.
Preliminary engineering on the project began in 2021. But then the Democrats on Commissioner’s Court forced a management change at HCFCD.
The preliminary engineering was supposed to take 330 days, but it took four years instead. Worse, after all that time, it was criticized for not reflecting actual conditions and obvious recommendations. HCFCD blamed the problems on vendor “personnel issues.”
But it took HCFCD another seven months from publication of the preliminary engineering report to the time they officially delivered it to Commissioners Court for formal approval.
Congressman Dan Crenshaw first requested a $1.6 million grant for Diversion Ditch design in 2021. It was approved in the fiscal year 2022 budget by Congress. Now, HCFCD is requesting a two-year extension until December 31, 2027.
From the identification of the need in the Kingwood Area Drainage analysis on 10/20/20 to the projected end date of 12/31/27, 2628 days will elapse (assuming no more delays).
To put that in perspective, the U.S. won World War II in 1348 days.
So, it will take almost twice as long to redesign a channel as it did to win World War II! That takes some real talent! I’m not sure it’s possible to walk a project any slower and not have Commissioners Court notice. To be fair, the Diversion Ditch IS more than three miles long!
Posted by Bob Rehak on 3/13/26