Since Dr. Tina Petersen’s last update on 5/1/2026, the new schedule shows that, of 28 projects in the Disaster Relief (DR) and Mitigation (MIT) groups, expected completion dates have:
Marcus Stuckett, new Executive Director of HCFCD, at Taylor Gully/Woodridge Groundbreaking on 7/20/26
Of an additional seven neighborhood drainage projects, six should finish before the end of this year.
Beating the CDBG Clock
Stuckett replaced Petersen a little more than a month ago. Petersen resigned under pressure when it finally became clear that the county could lose hundreds of millions of dollars due to missed deadlines on CDBG jobs.
As Petersen came under increasing pressure, she developed a plan with the Texas General Land Office (GLO). The plan applied spending from three different types of CDBG jobs against the $322 million designated for the DR group. Those have the tightest deadline – February 28, 2027. Just seven months away!
The other two types of projects being applied against the DR total include Mitigation (MIT) and neighborhood drainage.
By applying spending from the latter two groups against the DR total, HCFCD hopes to meet its obligation to spend $322 million by the end of February, 2027. Worst case, HCFCD will reduce its potential losses.
Only $56.77 million has been spent to date in the DR and MIT groups, with $67.33 million in the neighborhood drainage group. Those total $124.1 million. That means…
…the $322 million finish line is still $197.9 million away.
Calculated from HCFCD spreadsheet submitted to Commissioners Court for 8/6/26 meeting.
How Deep is the Hole?
This transmittal shows that Stuckett still needs to get HCFCD out of a deep hole that Petersen left HCFCD in.
About one third of the $322 million has been spent to date.
That leave two thirds to spend within the next seven months.
Seven months represents about 15 percent of the time between the announcement of the CDBG-DR award and the deadline for spending it.
So, HCFCD must spend the remaining two thirds in 15 percent of the time.
That’s a tall order. It’s sad that Precinct 2 Commissioner Adrian Garcia defended Stuckett’s predecessor to the bitter end and delayed her exit by a year or more as the CDBG funds fell into a deeper and deeper hole.
Now, it will take extraordinary effort to climb out of that hole.
The spreadsheet submitted by Stuckett for the next commissioners court meeting is extremely detailed: about 40 lines deep by 51 columns across.
Such updates will hopefully let commissioners discuss any concerns they have. And help HCFCD answer their questions.
In the next few months, accurate and timely updates will also show whether the current “running rate” will get us to the $322 million finish line in time.
Posted by Bob Rehak on 8/1/26
3259 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/08/Stuckett-at-Woodridge-Groundbreaking.jpg?fit=1100%2C733&ssl=17331100adminadmin2026-08-01 17:07:542026-08-01 18:44:27HCFCD Still Has Steep Hill to Climb on CDBG Projects
07/28/2026 – Harris County Flood Control District (HCFCD) has released new figures showing where it has spent money through 2026 Q2. The County has spent only $49.15 million dollars in the entire San Jacinto Watershed since passage of the 2018 Flood Bond eight years ago.
That compares with $367,450,000 worth of projects advertised for the San Jacinto in the 2018 Bond Project list.
Thanks goodness HCFCD got a new executive director last month!
Little Money Spent on Construction
The previous executive director kept slighted the San Jacinto watershed for years. Studies dragged out for years with no end in sight. HCFCD spent little money in the watershed. Period. And it spent even less on construction.
When you look at the spending by project stage, construction ranked highest. That actually surprised me.
Calculated with data from HCFCD Activities Page
But of the $21.7 million total spent on construction, HCFCD spent only one third on capital improvement projects (CIP construction = $7.28 M). The remainder went to maintenance.
While maintenance spending is absolutely critical, we shouldn’t forget that it is designed to keep flooding from getting worse as opposed to CIP projects which actually improve flood risk.
So, in eight years, HCFCD spent only about $7 million to actually improve flood risk in the county’s largest watershed.
To date, HCFCD hasn’t come close to delivering what was promised in 2018.
What Did Bond Advertising Promote?
The final project list came with 13 Bond IDs for the San Jacinto Watershed; each contained one or more projects. Together the money allocated for them totaled $367,450,000. So, with only $49.15 million spent to date, just 13% of promised funding has been delivered in the last 8 years.
Start drilling down further; you will find even more egregious examples.
Floodgate Example
Take for example the new floodgates on Lake Houston. Initial plans allocated $70 million ($50 million coming from the federal government and $20 million from the flood bond as a local match).
If the reported figures are accurate, the county actually spent only $20,000 so far – one thousandth of the local match. And 1/3,500th of the total. In fairness, perhaps they’re waiting for the City to finish the engineering.
Dredging Example
And then there’s dredging. Dredging was supposed to receive $50 million ($10 million from local funds with a $40 million match). But so far, HCFCD reports only $7.28 million spent for dredging. (See CI-61.)
Hopefully, Marcus Stuckett, HCFCD’s new executive director, can right some of the slights from the past administration. On a positive note, the recent start of construction on the Taylor Gully/Woodridge project may help turn the San Jacinto spending drought around.
Posted by Bob Rehak on 7/28/2026
3255 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/07/HCFCD-Spending-by-Stage-in-San-Jacinto-2018-2026.png?fit=2018%2C1190&ssl=111902018adminadmin2026-07-28 21:46:362026-07-28 23:35:41HCFCD 2026 Q2 Spending Update: San Jacinto Watershed Still Ignored
07/27/26 – New spending figures are available from Harris County Flood Control District (HCFCD) through the end of 2026 Q2. This quarter marks the end of Dr. Tina Petersen’s administration and the start of new Executive Director Marcus Stuckett’s. In that sense, it represents (pardon the pun) a watershed moment.
HCFCD spending data shows that Stuckett inherits a production pipeline that was not pushing flood-mitigation projects into and through construction at historically normal rates.
Eight years into what was supposed to have been a 10-year bond program, Harris County has spent only 37% of the dollars approved by voters while inflation in the heavy-construction sector of the economy has totaled more than 50%.
As a consequence, inflation is taking a huge toll on the Flood Bond’s purchasing power…and making residents live with higher flood risk longer than necessary.
But there’s also some good news: 6 HCFCD construction jobs on the Harris County Commissioners Court Agenda this week!
Let’s look at each of these points.
Construction Slowdown
Shortly after voters approved the flood bond in 2018, spending on flood-mitigation projects soared. But then, the team that sold the bond and defined hundreds of projects was pushed out by Democrats starting in 2021.
Precinct 2 Commissioner Adrian Garcia managed to get Dr. Tina Petersen appointed head of HCFCD at the start of 2022. And ever since, for whatever reason, project activity has plummeted. You can clearly see it in the rate of spending below – despite having billions of dollars available.
HCFCD spending since 2018 Flood Bond as of 26Q2.Far right reflects only 2 quarters. But even doubled, 2026 would represent a continuation of the long-term decline.
The gray area in the graph above represents construction spending. It has dropped almost by half since its peak during the previous administration. Construction is down to $90 million per year [annualized] from $160 million per year [actual].
As a result of the slowdown, Harris County could lose hundreds of millions of dollars in HUD Community Development Block Grants for Disaster Relief, whose deadlines are fast approaching.
Lower-than-Normal Construction Expenditures as Percent of Total
Typically, construction accounts for about 65% of most flood-mitigation projects, give or take 10%.
That number can vary even more depending on land-acquisition costs, environmental permitting, etc. There are always exceptions. But on average, 65% is considered a defensible rule of thumb for planning purposes by many flood experts; some suggest the figure may even be higher.
So, how has HCFCD spending compared? It falls far short of 65%. Looking at everything spent to date, only 46% has been on construction. But even that number may be deceptively high.
Construction spending on maintenance masks what’s happening on the capital-improvement side. So let’s also look at each sub-category.
HCFCD capital-improvement construction spending to date is just 37% of all capital improvement costs. And the Total percentage is buoyed up by construction spending on Maintenance.
Remember that only capital-improvement construction dollars actually reduce flood risk.
Only 37% of Bond Money Spent After 8 Years into 10-Year Bond Program
There’s another significant takeaway from last quarter’s update. HCFCD has spent only 37% of the bond money approved by voters – eight years into what was supposed to have been a 10-year bond program.
Sorting expenditures on the HCFCD Activity Page by “Fund Source” shows that only $932.69 million of the $2.5 billion bond has actually been spent to date. This excludes district and partner funds.
54% Inflation in Heavy Construction Sector Since Start of Flood Bond
But all the data above illustrates only part of the problem. Cumulative inflation in the heavy-construction sector of the economy totals 54% from mid-2018 (when voters approved the Flood Bond) to mid-2026. (Source: Federal Highway Administration’s National Highway Construction Cost Index, considered by many as a good analog for flood-control work).
This inflation has progressively eroded the purchasing power of flood-mitigation construction budgets.
A Bad Institutional Hangover
Problems moving projects into and through HCFCD’s production pipeline in a timely way has resulted in:
Inflation gobbling up a large percentage the bond’s purchasing power
Fast-approaching deadlines jeopardizing hundreds of millions of dollars in federal funding
People living with higher flood risk longer than necessary.
There is some good news in all of this on the horizon. It looks like HCFCD’s new Executive Director, Marcus Stuckett, is making an immediate impact. This Thursday’s Commissioner’s Court agenda shows six CIP projects starting construction or going out for construction bids. They include:
Meyergrove Stormwater Detention Basin
Halls Bayou Channel Conveyance Improvements – Phase II
T.C. Jester Stormwater Detention Basins – Compartments 1A and 2
Hopefully Stuckett can get construction projects moving again.
Posted by Bob Rehak on 7/27/26
3254 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/07/Construction-as-Percent-of-Total-Table.png?fit=1880%2C584&ssl=15841880adminadmin2026-07-27 17:38:302026-07-27 17:38:32HCFCD Construction Slowdown May Be on Verge of Turnaround
6/17/26 – Harris County Precinct 3 Commissioner Tom Ramsey PE addressed the Kingwood Executive Group this morning about flooding and infrastructure as the season’s first tropical storm formed less than a hundred miles away from Houston. Local business owners comprise the group. Many had flooded badly during Hurricane Harvey.
Kingwood Executive Group with Ramsey and State Rep. Charles Cunningham in blue blazers, center/front row.
They came eager to learn more about the status of flood-mitigation efforts in the area, turmoil at the Harris County Flood Control District (HCFCD), and a new, 5,300-acre proposed floodplain development just upstream from Kingwood. And true to form, Ramsey addressed each issue head on. But first…
Tropical Storm Arthur
Ironically, just as Tropical Storm Arthur formed, the rain started to end in the Lake Houston Area. That’s because of the lopsided nature of Arthur. See the infrared water-vapor satellite image below. Most of the rain is falling offshore and to the east of Galveston Bay.
NHC expects Arthur to dump torrential rains on East Texas and Louisiana as it moves inland – up to 20 inches in places. Freeport received 9 inches this morning. However, totals dropped off farther inland with much of SE Harris County receiving only 2-4 inches. My rain gage in Kingwood recorded less than a half inch between midnight and 11 AM.
Arthur has affected primarily coastal counties as it tracked NE parallel to the coast. It should make landfall near High Island late this afternoon or early this evening.
Arthur formed a timely and ironic backdrop for a speech about flooding to many whose homes and businesses flooded severely.
Ramsey’s Priorities
Ramsey began his talk to the Executive Group with a story about his focus compared to others on Commissioners Court. “My job is to, number one, take care of infrastructure,” he said. “That’s what I get most of my calls on. Most people don’t call me about my policies. They call me on, ‘When are you going to fix something?’ My colleagues, on the other hand, are focused more on social programs.”
Ramsey puzzling over the budget priorities of some other commissioners
He then added, “We will appoint a new director next week. And it will be an engineer, not a politician. An engineer who can deliver projects, not hold press conferences and tell you what you want to hear. It will be someone that actually understands what it takes to get projects delivered.”
Flood Bond Update
After emphasizing the need to speed up project delivery, Ramsey gave a brief update on the 2018 Flood Bond. The $2.5 billion approved by voters attracted another $2.7 billion in matching funds for a total of $5.2 billion available. But the county has only spent about $1.5 billion of that since 2018.
“So, we have a lot to do,” said Ramsey. “Probably another $3+ billion in the next four years. You better have someone who understands construction, who can deal with the things that happen during construction. My concern is that the easiest part is done. Design work is the easy part. Go actually build $3.5 billion worth of improvements! That’s a huge deal.”
Kingwood Flood-Mitigation Projects
Ramsey noted that the Taylor Gully/Woodridge project has started construction, but that the Kingwood Diversion Ditch project is still being studied. He wants to put the pedal to the metal on that one too. HCFCD spent 4 years doing a preliminary engineering review on the Diversion Ditch that was supposed to have taken 300 days. The latest Flood Bond Update shows the project may start construction in 2030, after HCFCD completes another study.
“You must have other projects queued up ready for construction,” Ramsey said. “I don’t know that we have all the money lined out for that construction, but you have to get the design work done. I’d rather have a whole lot of projects sitting on the shelf ready to build, than sit around and wait for someone to decide for us what the priorities are.”
Scarborough Floodplain Development
Ramsey next addressed the proposed 5,300-acre development north of Harris County in the floodplain at the confluence of the West Fork of the San Jacinto River and Spring Creek. He called it “A really bad idea.”
“Some ill-advised folks are trying to do some development there.” Ramsey suggested instead that the area should become a park. “What a great park that 5,000 acres would make for this entire area. What a great location for significant flood mitigation for the entire county!”
He emphasized that every drop of rain falling north and west of the confluence funnels past Kingwood. “Sometimes we lose sight of that,” he said.
Ramsey spent much of the rest of his time discussing a series of related issues, their connections, and finding funding for them.
In regard to adding more floodgates to the Lake Houston Dam, he noted potential significant cost escalation. That led to a discussion of partnership funding, surplus toll-road income, and using money for pressing state-mandated obligations versus other issues that have no constitutional mandate.
Before becoming commissioner in 2020, Ramsey began his engineering career 50 years ago designing drainage systems in the Porter/New Caney area. So, he is thoroughly versed on infrastructure issues in the Lake Houston Area and is fighting to make us safer.
The timing of his talk as Arthur was forming in the Gulf provided an irony worthy of a Hollywood movie!
Posted by Bob Rehak on 6/17/2026
3214 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/06/DSC_5428.jpg?fit=1100%2C407&ssl=14071100adminadmin2026-06-17 13:56:532026-06-20 18:39:24Ramsey Addresses Kingwood Group as Tropical Storm Forms Offshore
6/8/2026 – In their 6/11/2026 meeting, Harris County Commissioners will revisit the future employment of Harris County Flood Control District (HCFCD) Executive Director Dr. Tina Petersen, PhD, PE. The immediate issue: slippage of 11 CDBG-DR projects that could cost the county $322 million if they miss their deadlines on February 28, 2027.
Roughly 84% of the time for those has elapsed with less than 4% of their budgets expended.
Despite deadlines only a little more than eight months away, the projects typically take 1-2 years to construct.
HCFCD also expects to miss deadlines on 13 of 18 CDBG Mitigation Projects (CDBG-MIT) worth another $362.7 million dollars. But that deadline is 3/31/28.
Predictably, the parties involved are offering their own versions of how we reached this point. Dueling press releases today differed starkly.
The GLO says HCFCD promised it “shovel-ready” projects.
On the other hand, HCFCD calls them “complex, large-scale flood risk reduction projects under strict federal timelines, evolving program requirements, construction market pressures, and funding structures that were not originally designed for this level of accelerated delivery.”
Unusual 5-Part GLO Press Release
The GLO issued a five-part press release, unusual in its detail. There was:
The press release itself
An open letter to Harris County Judge Lina Hidalgo
Photographs of 11 projects supposedly under construction, only three of which were actually moving dirt.
Timeline of critical events during the life of the CDBG-DR Program (the one with the most pressing deadline).
A list of “Failures” by HCFCD.
The GLO press release summarized the letter to Hidalgo. It quoted GLO Commissioner Dawn Buckingham as saying Harris County needed “Shovels, Not Scapegoats.”
The press release also said that, “We have grave concerns about Harris County Flood Control District (HCFCD) not meeting its benchmarks…” It went on to say that if the county didn’t change its business processes…
“…there is likely zero chance of successfully meeting the grant timeline established by the U.S. Department of Housing and Urban Development.”
Dawn Buckingham, GLO Commissioner
Buckingham stated that the GLO spent more than $5 million of its own grant funding to teach HCFCD about grant requirements and provide technical support with grant applications. The GLO claims its team conducted more than 750 meetings “to provide staff support to Harris County to ensure these projects are completed on time in accordance with the federal deadline, yet there are still too few shovels in the ground.”
Commissioner Buckingham concludes her letter by saying, “It’s time to … finish the job. Shovels, not scapegoats.”
Page 15 of 18 shows that with roughly 84% of time elapsed, HCFCD has spent only about 3.9% of available DR funds.
Page 11 of 18 shows that HCFCD has spent only 4.4% of available MIT funds.
HCFCD Paints Rosy Picture Despite Obstacles
The GLO press release this morning emphasized that in 2023 projects were supposed to have been shovel ready. HCFCD’s press release this afternoon never mentions “shovel ready.” Instead it paints a nightmare picture of impossible complexity before claiming it has, ta da, a “plan” to solve the problem.
HCFCD will unveil its new “plan” to commissioners on Thursday. According to HCFCD, it “protects federal funding, maintains and strengthens our commitment to communities, and ensures residents receive the flood risk reduction benefits these programs were designed to deliver.”
HCFCD had planned a press conference tomorrow to explain the plan to reporters, but cancelled it late today.
Proposed Solution
While details of the plan have not yet been divulged, in principle, GLO and HCFCD agree on the following outline. It involves:
2) Billing everything possible from that giant bucket against the DR budget before the 2/28/27 deadline.
3) Billing the rest against the MIT budget, which has a 3/31/28 deadline.
This approach at least kicks the can down the road past the next election. However, Buckingham cautions that the 2/28/27 deadline is firm. Without taking a position on Petersen’s employment, GLO does warn that HCFCD and the County need to move much faster.
Thursday’s Decision on Petersen
GLO’s list of Harris County “failures” is unambiguous. Ramsey can elaborate on them at length and provide examples. Despite extensive support provided by GLO, they include:
Missed deadlines
Reprioritizing projects repeatedly
Submitting incomplete or inaccurate documentation that failed to adhere to federal grant regulations
Failing to respond to GLO requests regarding federal grant processes
Significant employee turnover and loss of experienced staff capacity
Failure to achieve timely engineering design, environmental clearance, procurement, vendor contracting and construction starts…
HCFCD’s own spending data shows that its slowdown cuts across project phases, types of projects, and funding sources. The graph below shows all 2018 bond spending. You can see that problems go far beyond CDBG, GLO and HUD.
The downturn you see coincides with Petersen’s appointment to manage HCFCD.
HCFCD spending over time. Petersen took over in 2022after Democrats started pushing out the previous management team in 2021.
Changing Horses in Midstream
Petersen supporters argue that it could be dangerous to change horses in midstream, especially now that the immediate crisis seems to be solved with the “one big bucket” plan.
But her opponents argue that staying with the status quo carries the larger risk. They argue that poor performance during a crisis may be a reason for change, not a reason against it.
In my opinion, the real question is not whether you’re midstream, but whether the current horse is still the best one to get you across.
Buckingham answered, “This patient is in the middle of a code and about to die.”
Posted by Bob Rehak on 6/8/2026and updated with Fox link on 6/9/26
3205 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/04/2018-Bond-Spending-by-WS-Incremental.png?fit=2060%2C778&ssl=17782060adminadmin2026-06-08 23:18:502026-06-09 22:30:07Showdown Over Slowdown at HCFCD
5/4/2026 – On May 1, 2026, Harris County Flood Control District (HCFCD) finally submitted a detailed spreadsheet demanded by Harris County Commissioners. It shows key milestones in Community Development Block Grant (CDBG) projects receiving $868 million in federal funding.
The data raises two red flags:
Only 11 of 28 projects will meet deadlines
Construction bids far below initial estimates could leave tens of millions of dollars on the table.
Here is the detailed spreadsheet. The data directly contradicts rosy, high-level claims made by Dr. Tina Petersen, HCFCD’s executive director, in Commissioners Court on January 8, 2026. At that time…
So, let’s look at the deadlines with the detailed information now in hand. This story has the sad feeling of a football game with the home team down 30 points and only three minutes left on the scoreboard clock.
Deadlines Looming
The 28 CDBG projects are split into two groups with different deadlines:
11 CDBG-Disaster Relief (DR) worth $322 million
17 CDBG-Mitigation (MIT) worth $546 million.
DR projects have, by far, the tightest deadline – February 28, 2027. MIT projects have longer; 50% of that money must be spent by March 31, 2028, with the remainder spent by 2032. So, let’s look at DR projects now and save the MIT discussion for another day.
New Doc Predicts Only Five DR Projects Will Beat 2/28/27 Deadline
Of the 11 DR projects, HCFCD now predicts that only five will beat their deadline. (Estimate “substantial completion” dates shown in parentheses below.)
Of these five projects, HCFCD is only actually moving dirt on two so far.
Arbor Oaks (30% complete with 51% of construction days elapsed)
Brookglen (8% complete with 9% of construction time elapsed).
Can they be completed in time? The Arbor Oaks job is a cautionary example. Contractors have completed only 30% of the job in half the allotted time.
Six DR Projects Now Predicted to Miss 2/28/27 Deadline
According to HCFCD’s latest spreadsheet, the six projects below will miss their deadlines. Construction bids on four of the six have not even been awarded yet (Genoa, Kluge, Isom, Dinner).
HCFCD is not moving dirt on ANY of the projects in this second group yet, though a construction trailer is on the East TC Jester Site and clearing reportedly started last week.
Less than 10 months remain on the game clock for the 11 DR projects.
How Reliable are Completion-Date Estimates?
But how much can we depend on HCFCD projections given delays and promises to date? We should remember that under Petersen, HCFCD attempted to build the Mercer SWDB on an expedited basis in ONE YEAR. It took FOUR!
Is There Flexibility in Deadline?
The Texas General Land Office (GLO), which administers US Department of Housing and Urban Development CDBG funds in Texas, has given itself a year after 2/28/27 to close out all DR jobs.
GLO might be able to give up a few months of that year – if projects are close to completion. For instance, several projects in the second group are currently projected to miss the deadline by less than three months.
However, GLO needs the rest of that year to do its work. Beyond that year, it would literally take an act of Congress to extend the deadline. Good luck with that, given the current political gridlock in Washington.
All Construction Bids Lower than Estimates So Far
Close examination of the HCFCD CDBG spreadsheet shows that ALL DR construction bids so far have come in lower than engineers’ estimates. This could create a budget surplus.
A GLO spokesperson says that in cases like that, the money could be shifted to other projects within the group that might have a deficit. Potentially, extra projects might also be possible.
However, at this stage of the game, finding a shovel-ready project that could be bundled into the DR group would be difficult. Any surplus would likely be grouped into a Disaster Recovery Reallocation Program (DRRP) at some future date.
We saw this recently when the GLO allocated unspent funds from disasters before Harvey to Harvey-related projects. That sweetened HCFCD’s DR pot by more than $100 million.
At this very moment, county and GLO officials are scrambling to identify eligible projects. However, construction experts I talked to doubt there’s time to do them before the deadline – even if one or more could be identified.
Posted by Bob Rehak on 5/4/2026
3170 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/05/DR-and-MIT-Project-Locations.jpg?fit=1100%2C823&ssl=18231100adminadmin2026-05-04 21:20:512026-05-05 08:10:38HCFCD Document Shows It Misled Commissioners, Public on CDBG Funding Worth Hundreds of Millions
4/21/26 – Harris County Flood Control District (HCFCD) has taken more than 4 years to spend about 4% of the $322 million that HUD allocated to HCFCD for Community Development Block Grants for Disaster Relief (CDBG-DR). That figure is carved out of a larger total ($868 million) that also includes CDBG Mitigation funds.
Former Texas General Land Office (GLO) Commissioner George P. Bush announced his intention to allocate $750 million of US Department of Housing and Urban Development (HUD) funds to Harris County on 5/26/21. HUD approved that amount on 3/18/22. Subsequently, it increased when the GLO also re-allocated unused funds from storms before Harvey to Harris County.
Here’s a high-level breakdown as of today.
Source: Texas General Land Office. 4/21/26.
HCFCD has spent only 3.59% of the CDBG-DR project funds to date. That group has the tightest deadline, just 313 days away and involves roughly a third of a billion dollars.
Feasibility, preliminary-engineering, and final design studies
Cost estimates
Bids
Property acquisition (for some projects)
Obtaining GLO and HUD approval for all of the above.
But still…
Unnecessarily Burdensome Processes, Changing Horses in Midstream
Harris County made it more difficult than necessary with its own equity prioritization framework, which changed several times.
Judge Hidalgo and Commissioners Ellis and Garcia also forced out the management team that developed and sold the 2018 flood bond. Their replacement, Dr. Tina Petersen, had a long, steep learning curve and big shoes to fill. She also lost many key employees. That disrupted business continuity and cost institutional knowledge.
Since she took office, spending has gone down consistently as the pace of work slowed, partly as a consequence of a management style she calls “being more intentional.”
Self-Inflicted Wound
Having spent four years bickering about equity, the county now has just 10 months left to actually build all the jobs in order to beat a firm 2/28/27 deadline and avoid losing potentially ALL of the CDBG-DR funds.
According to a document submitted to commissioners court on 4/16/26 by Petersen and aerial photographs that I have taken, it appears that contractors are actually only turning dirt on one of 11 CDBG-DR projects.
Compare that with the TC Jester Basin project shown below. Both photos were taken on 4/19/2026.
TC Jester East Basin will go in the big treed area in the center. “Construction” was announced last December 5.
Past Experience a Logistical Red Flag
If history is any indication, the vast majority of the CDBG-DR projects will take longer than 10 months to build. Ten of the 11 are large detention basins that typically take one to two years to build. The Mercer Basin on Cypress Creek, finished just last week, took three years. And TC Jester, above, is 55% larger.
If Petersen can pull the projects off before the buzzer sounds, she deserves that $90,000 raise she got last year. If not, she won’t be the only one with egg on her face.
Posted by Bob Rehak on 4/21/26
3157 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/04/DR-MIT-Totals-for-HCFCD-and-HCD-as-of-2026-04-21-1-scaled.png?fit=2560%2C491&ssl=14912560adminadmin2026-04-21 19:49:302026-04-21 22:11:14HCFCD Has Taken 4 Years to Spend 4% of HUD CDBG-DR Funds
3/28/26 – At the San Jacinto River Authority (SJRA) Board Meeting on 3/26/26, HCFCD Executive Director Tina Petersen updated the board on a number of Lake Houston Area projects including the Kingwood Diversion Ditch. She confirmed it is fully funded – through construction.
However, design of the Diversion Ditch Project has not yet started. It should begin in April and finish by the end of 2027.
A year ago, the preliminary engineering study estimated the cost of the project at $40.7 million. Current estimates put the cost at $43 million, according to Petersen.
Looking N at the Kingwoodwood Diversion Ditch from over the Walnut Lane Bridge
Relationship to Bens Branch Flooding
The Diversion Ditch splits off of Bens Branch near St. Martha Catholic Church north of Northpark Drive.
Stormwater flow to Bens Branch will be restricted by pipes. That will force more stormwater into the expanded Diversion Ditch. In the process, that would take enough stormwater out of Bens Branch to improve it from a 2-year level of service to a 100-year level.
Red Diagonal = Bens Branch. White = Kingwood Diversion Ditch. Green = new outfall to river.
Diverting water from Bens Branch is important because Bens Branch runs through Kingwood Town Center where 12 people died from Harvey flooding.
Crenshaw Connection
Ironically, funding obtained by US Congressman Dan Crenshaw back in 2024 to widen the bridge shown above at Walnut Lane saved this project from the chopping block – even though it was ranked the most important project in Kingwood by the Kingwood Area Drainage Analysis.
At the time, Precinct 3 Commissioner Tom Ramsey PE warned that killing projects in Quartiles 2, 3 and 4 could have dire unintended consequences. The Diversion Ditch project fell into Quartile 3.
After the Democrats saw how much partnership funding they would lose by killing projects in the lower quartiles, they relented. In their next meeting, they voted to exempt projects in the lower quartiles that already had partnership funds committed.
That breathed new life into the Kingwood Diversion Ditch project because it included widening of the Walnut Lane Bridge which Crenshaw had already secured funding for.
HCFCD spokesperson Emily Woodell confirmed the Diversion Ditch funding today. “It was categorized as a partnership project during the bond update presented to commissioners court in August [2025] which means it is fully funded through construction.”
For Updates on Other San Jacinto Watershed Projects
It covers a lot of territory including the history of HCFCD, status of the bond program, partnership funding, maintenance programs, gauges, the flood-warning system, and more.
Other capital improvement projects in the Lake Houston Area that she discusses include:
Woodridge Village/Taylor Gully – Construction starting in April.
Jackson Bayou Detention Basin – Construction starting Q3/2026.
Barrett Station Drainage Improvements – Currently in Design Stage.
Lake Houston/East Fork/West Fork Dredging – Completed.
Lake Houston Gates – Engineering should finish by end of this year.
1/30/26 – A four-million dollar earmark secured by U.S. Representative Dan Crenshaw for widening the Walnut Lane Bridge in Kingwood saved the entire $44 Million Kingwood Diversion Ditch Project from being killed by the Democratic members of Harris County Commissioners Court.
U.S. Rep. Dan Crenshaw gives the thumbs up to the Walnut Lane Bridge project. Widening the bridge is necessary to widen the Kingwood Diversion Ditch (background) which will also help reduce flood risk along Bens Branch.
At the time, Precinct 3 Commissioner Tom Ramsey PE warned that killing projects in Quartiles 2, 3 and 4 could have dire unintended consequences. The Diversion Ditch project fell into Quartile 3.
After the Democrats saw how much partnership funding they would lose by killing projects in the lower quartiles, they relented. In their next meeting, they voted to exempt projects in the lower quartiles that already had partnership funds committed.
That breathed new life into the Kingwood Diversion Ditch project because it included widening of the Walnut Lane Bridge which Crenshaw had already secured funding for.
Multiple Benefits: A Texas Twofer
But the project will benefit far more of Kingwood than just the people who live in Diversion Ditch floodplains. It will also benefit people who live near Bens Branch. That includes the Villages of Bear Branch, Kings Forest, Hunters Ridge, Town Center, Kings Harbor and Kingwood Greens.
That’s because widening the Diversion Ditch will take excess stormwater out of Bens Branch and allow water to move safely down the Diversion Ditch. The planned improvements will take Bens Branch from a 2-year level of service to a 100-year level.
Kingwood Diversion Ditch in white, new outfall in green, and Bens Branch in red.
That means homes in the Bens Branch floodplains should be safe in anything up to a 100-year storm. Currently, the stream is at risk of flooding parts of its watershed every two years.
When the Diversion Ditch project is completed, Crenshaw will have helped protect people and property values in approximately half of Kingwood.
Bob Rehak
Crenshaw Support Crucial on Other Projects, Too
The Kingwood Area Drainage analysis found that, based on the number of people who benefit, the Diversion Ditch project is one of the two most important in Kingwood. Another is the Taylor Gully/Woodridge Project which Crenshaw also secured funding for.
Editorial Comment: I interviewed Crenshaw in 2018 when he first ran for Congress and have followed his work in Washington ever since. The man is a warrior, scholar and leader. He fights tirelessly to improve the lives of his constituents. He studies issues. And thoughtfully and patiently explains them. There’s no way he could have known what Commissioners Court would do in 2025 when he proposed the Walnut Lane Bridge funding in 2023. Regardless, his proactive effort will improve the safety of tens of thousands of his constituents.
Two Houston groups – the Northeast Action Collective and Texas Housers – claimed the GLO ignored Houston and Harris County in the distribution of the first tranche of Harvey aid. Houston and Harris County got $0 from the first $1 billion. But the Northeast Action Collective and Texas Housers ignored the fact that ALL of the next $750 million went to Harris County.
Moreover, the GLO announced the $750 million a full month BEFORE the two groups filed their discrimination complaint in 2021.
GLO Cleared
The investigation began on June 25, 2021. The Office of Fair Housing and Equal Opportunity found that “no reasonable cause exists to believe the GLO has violated the Fair Housing Act, Title VI, or the Housing and Community Development Act through its administration of the 2019 CDBG-MIT funds, including the Hurricane Harvey State Mitigation Competition.”
Complainant Allegations
Complainants alleged discrimination on the basis of race and national origin, and that scoring criteria systematically and deliberately advantaged white communities while disadvantaging low- and moderate income (LMI) African-American and Hispanic communities.
GLO Defense
Looking only at the first billion dollars, GLO presented evidence that roughly 1.2 million of the 1.5 million Texans who benefited from the approved projects were Hispanic, Black, Asian, Pacific Islander, or Native American. The GLO also showed that 100% of the awards went to projects in majority LMI areas.
GLO also argued that complainants could not look only at one portion of the grants. Or look only at the first round of Harvey Grants and ignore 2015 and 2016 grants.
Findings
HUD found that the GLO substantially exceeded HUD’s requirement to direct at least 50% of funds to Most Impacted and Distressed (MID) areas. In 2015, 2016 and the first round of Harvey, GLO directed roughly 60% of all HUD funds to MID areas.
GLO later cancelled the second round of Harvey competition and allocated $750 million exclusively to Harris County. The County’s population is 42.9% Hispanic and 18.6% Black – a total of 61.5%. With other minorities, that brought minority beneficiaries for all phases to more than 66%.
Location of HUD/GLO projects in Harris County as of 2024.
Thus the complainants failed to show a disproportionate impact on minorities. Northeast Action Collective and Housers failed to assess the share of total beneficiaries that were black, white or Hispanic compared to the racial demographics of eligible areas.
Even when looking at just Round One of the Harvey competition, “no reasonable cause exists to believe the GLO’s administration had a disparate racial impact on funding.”
The complainants focused on Houston and Harris County not winning any awards during the Harvey Round One competition. Another section of the 22-page legal brief deals with why. To a large degree, not winning any awards in Round One resulted from the Benefit/Cost Analyses of submitted projects. Smaller jurisdictions just had lower costs per beneficiary. (See page 13.)
For instance, one project submitted by the City would have benefitted fewer than 10,000 people, but cost $94 million. In other words, the City was seeking 18% of Round One funds to benefit less than a half-percent of the City’s population.
HUD determined that “Houston’s poor performance in the Harvey Competition is attributable, at least in part, to its expensive, low-impact project proposals.”
Conclusion
“The facts of this case do not suggest that GLO intentionally discriminated against any racial or ethnic group through its administration of the CDBG-MIT funds,” said the final ruling.
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.