New data obtained from Harris County Flood Control District via a FOIA Request breaks down flood-mitigation funding by watershed through the end of 2021. It shows where your flood-bond money is going. It also debunks some popular myths. Those include the oft repeated:
Rich watersheds get all the funding; poor watersheds get none.
Partner funding favors rich watersheds because home values are higher.
HCFCD has historically discriminated against low-to-moderate income (LMI) watersheds.
Eight out of 23 watersheds in Harris County have a majority of residents that fall into the LMI category. That means a majority make less than the average annual income for the region. As the data below shows, those eight LMI watersheds get the vast majority of county, partner, and total funding. In fact, four have received 54% of total flood-mitigation funding since 2000.
Funding now correlates more highly with LMI population than damage!
Before I dive into the data, though, let me point out that between the 3Q21 and the end of last year, the county changed the way it compiles historical data. Instead of using the start/stop dates in project management software and reporting only completed projects, the county is now using invoice dates. This produces much higher accuracy. Dollars do not spill over from one period into another. The new data also reflects spending on projects that are ongoing, but still open.
In response to my FOIA Request, the county provided spending using both the old and new methods. They differ by roughly $615 million. Of that, approximately $215 million reflects actual fourth-quarter spending and $400 million reflects the change in when expenses are recognized.
Spending by Watershed
The rank order of spending by watershed has not changed much since last year. Several watersheds moved up or down by a place or two.
The top four are still the top four in the same order. But some of the amounts changed radically, mostly due to the change accounting. For instance, White Oak increased from $387 million to $521 million. But out of the $134 million difference, $102 million comes from when expenses are recognized.
Because this gets so confusing, and because the rank order did not change much, I will use only the new totals compiled by invoice date from now on. I will not compare old and new totals based on the different accounting methods.
Spending by watershed between 1/1/2000 and 12/31/2121 broken down by county and partner contributions, and LMI/Other watersheds.
Graphs of Spending
Here’s a graph of total funding by watershed since 2000, arranged from highest to lowest.
Watersheds rank ordered by amount of flood-mitigation funding received between 1/1/2000 and 12/31/2121.
Funding correlates with population. But you can see notable exceptions below. Some watersheds get far more funding than their proportion of the population, i.e., White Oak, Sims and Greens. Others get far less.
Spending is not allocated proportionately to population in all cases. Six out of eight LMI watersheds received more funding than their population alone would justify.
But population alone does not tell the whole story. Some watersheds are huge and some small. So I also looked at population density per square mile. The curves correlated even less.
Graphing population density vs. total spending shows more variance. Of the eight LMI watersheds, four (Brays, White Oak, Sims, and Greens) get far more than their population density alone would dictate.
As we saw last year, funding flows primarily to damage. The chart below plots funding versus the total number of structures in each watershed damaged in five major storms (Allison, Tax Day, Memorial Day, Harvey, and Imelda). The slope of the curves closely match. But several major exceptions exist.
Historical Discrimination?
Many community groups from LMI neighborhoods have alleged historical discrimination in the distribution of flood-mitigation funding. I just don’t see it. All of the pie charts below take into account all funding between 1/1/2000 and 12/31/2021 based on invoice dates.
The county itself sent almost 60% of its flood-mitigation funding to one third of the watershedswith majority LMI populations.An even larger percentage came from partner funding.Whether you look only at county funding, partner-funding, or the total, the picture is still roughly the same.One third of the watersheds get almost two thirds of the funding.Top 4 include Brays, White Oak, Sims and Greens. All have an LMI percentage higher than 50%.
LMI Population Now Correlates Higher with Funding than Damage
A coefficient of correlation of 1.0 is considered perfect. A good example: between gallons of gas in your car and the distance they will take you.
As a result of the constant tweaking of the equity funding formula, “Population” and “LMI Population” now correlate more highly with “Funding” than “Damage.” The correlation between “Funding since 2000” and:
Population Density = .54
Damage = .85
Population = .87
LMI Population = .89
Statisticians consider all of the last three very high.
Tonight, members of the Harris County Community Flood Resilience Task Force will vote whether and/or how to recommend changes to the equity funding formula for the third time in three years. On the table for discussion: partnership dollars.
One of the proposals under consideration is NOT to consider potential partnership funding. Said another way, taxpayers would pay for projects out of pocket rather than wait for federal and state dollars to filter down to the county level.
The main argument FOR this? Low-to-moderate income neighborhoods would not have to wait for HUD or FEMA dollars to begin construction.
The main argument AGAINST? Partnership dollars have funded roughly one-third of all flood-mitigation projects in Harris County since 2000.
So saying that you’ll bypass partnership dollars could eliminate one third of all flood-mitigation funding unless you want to increase taxes.
A highly publicized setback in the Texas GLO competition for HUD funds last year delayed a recommended $750 million award to Harris County. The delay hurt, but there’s still hope. HUD did not reject the GLO application. They just said they needed additional documentation. The two agencies have met several times since. GLO has already started reformulating its proposal and expects a decision as early as next month.
Should We Turn Our Back on Hundreds of Millions?
So should the plan now be to turn our noses up at the $1.15 billion that the county has received in partnership dollars since 2000. Should we say, “Let’s go it alone!” from now on? Should we stand by while that money goes to other areas that need it less?
LMI Neighborhoods Would Be Hurt the Most
Another argument proposed for ignoring the partnership funding: it disadvantages LMI neighborhoods because affluent neighborhoods have higher home values and therefore get higher Benefit Cost Ratios.
$797.4 million out of $1.149 billion in total partnership funds went to LMI watersheds. Percentages just happen to equal those in graph above.
While the logic sounds plausible, the only problem is that the eight LMI watersheds in Harris County (those where a majority of residents make below the average income for the region) actually receive 69% of all grants. Since 2000, they have received $797 million out of $1,149 million. So one third of the watersheds received more than two-thirds of all partnership funding.
That closely reflects the percentage of all spending (local + partnership) since 2000. The eight LMI watersheds received $2.3 billion out of $3.7 billion – 62%. Harris County has 23 watersheds in total.
The data clearly does not support discrimination against LMI neighborhoods in either partnership or overall spending. Greens Bayou for instance has received more money overall ($436 million) than all but three other watersheds since 2000. It also ranks #3 in partnership funding with $200 million. Partner dollars paid for 46% of the projects there.
Placing a Third of All Projects in Jeopardy
Eliminating partnership funds and relying on local funds will disadvantage Harris County taxpayers everywhere or cause a third of projects to be eliminated.
Date of Damage Assessments, Mitigation Also Crucial
Partnership funds can make a huge difference in watersheds in terms of flood reduction. Sims Bayou was the only bayou in Harris County that didn’t flood during Harvey. Of the $201 million it received in partnership funds since 2000, $198 million came before Harvey.
Sims also illustrates the problem with another proposal on the table tonight – using flood data going back to 1977 to determine who deserves more money. That will artificially disadvantage outlying neighborhoods which didn’t even exist in 1977. And it will funnel money into a watershed that has already largely been remediated.
When people come at these decisions from an ideological perspective without looking at data, it hurts everyone…sometimes even themselves.
My personal opinion is that when people talk about partnership funding, the debate should be, “When do you go it alone?” not “Should we go it alone?”
Ever wonder where your tax and flood-bond dollars go? Harris County Flood Control District shows all its active projects on one page. You can review those projects in tabular form or on a map. You can even click on links to learn more about each project. Or explore it in depth by going to its related “watershed” page.
Active maintenance (orange) and capital (purple) flood mitigation projects in Harris Countyas of 1/4/22 shown against backdrop of precinct boundaries adopted on 10/28/21.Purple = P1, Green = P2, Red = P3, Yellow = P4.
Paragon of Transparency
HCFCD’s Active Projects page is a paragon of government transparency. You can even switch out base maps to see where the projects fall in terms of the old or new precinct boundaries approved on October 28, 2021.
One side benefit of the two base maps is that they give you a clear, unambiguous view of the redistricting boundaries.
Zoom far enough in on the map and you can even see your street, home, and the drainage features around you (streams, channels, storm sewers, etc).
Physically seeing work in progress is difficult. Construction zones are dangerous and often fenced off or hidden behind trees. They’re also so large that seeing them from an entrance at ground level is almost impossible.
The good news: the projects almost always include hike and bike trails, like the one below, which you can enjoy upon completion.
However, if you want to monitor work in progress, your best bet is a drone.
Good News from Commissioners Court Today
Commissioner Tom Ramsey introduced a motion to affirm Commissioners’ intentions to complete all projects in the flood bond. Despite several previous attempts to cancel projects and change bond priorities, commissioners voted unanimously to complete the entire bond package. Ramsey will be the new commissioner for the Lake Houston Area if the Ellis-3 redistricting plan survives court challenges. See the sprawling red area on the map above.
Posted by Bob Rehak on 1/4/2022
1589 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2022/01/HCFCD-Actived-Project-Map-12.21.jpg?fit=1200%2C793&ssl=17931200adminadmin2022-01-04 16:43:232022-01-04 16:48:56How to Find HCFCD’s Active Projects in Your Area
To compensate for the potential shortfall, Commissioners established a flood-resilience trust with money from other Harris County departments and changed equity guidelines in June.
To help you follow this story, I make quarterly FOIA requests for Harris County Flood Control District spending and post the analyses on a dedicated funding page.
Sand-Mining Best Management Practices
Activists led by the Lake Houston Area Flood Prevention Initiative and the Bayou Land Conservancy petitioned the Texas Commission on Environmental Quality (TCEQ) to establish best management practices for sand mines in the San Jacinto watershed. We didn’t get everything we wanted, but we got a vast improvement over what we had. And the new BMPs may help reduce erosion that contributes to future floods in this area.
West Fork Sand Mine illustrates need for vegetative controls to reduce erosion.
May 9, 2021, was 1349 days after Hurricane Harvey ravaged Texas and the Gulf Coast. That’s the number of days it took the US and its allies to win World War II. But during that time we’ve had few victories in the fight against future flooding in the Lake Houston Area with the exception of dredging, So far, we’ve mainly completed studies. And many of those are still in the works.
For instance, the City of Houston has been studying ways to increase the release capacity of the Lake Houston Dam. Right now, the release capacity is one-fifteenth that of the gates on Lake Conroe. That makes it difficult to shed water quickly before and during floods. FEMA gave the City money to study the problem, but is still finalizing recommendations. The City hopes to make an announcement in January.
The Texas Attorney General is still suing the Triple PG Sand Mine in Porter on behalf of the TCEQ. There has been little movement on the case in the last 18 months. The mine’s owner changed legal counsel in July 2020. A TCEQ representative says the AG has not given up. The two sides are still in discovery.
Approximately 1700 homeowners in the Lake Houston Area sued sand mines for contributing to flooding during Harvey. The cases were consolidated in the 281st Harris County District Court under Judge Sylvia Matthews. She recently set deadlines in the first half of next year for motions, depositions, joinder, expert witness testimony and more. The case is known as “Harvey Sand Litigation.”
Various lawsuits against the SJRA for flooding during Harvey are still working their way through the legal system.
Kingwood residents reached a settlement with Perry Homes, its subsidiaries and contractors this year over two floods that damaged hundreds of homes in Elm Grove and North Kingwood Forest during 2019. The incidents had to do with development of Woodridge Village, just across the Harris/Montgomery County line.
East Fork Dredging. Photographed in early December between Huffman and Royal Shores in Kingwood.Looking south toward Lake Houston.
Bens Branch and Taylor Gully Cleanouts
In Kingwood, HCFCD finished excavating both Bens Branch and Taylor Gully to help restore their conveyance. Through gradual sediment built up, both had been gradually reduced to a 2-year level of service in places. That means they would come out of their banks after a 2-year rain.
Final phase of Bens Branch maintenance between Kingwood Drive and Rocky Woods. Note Kingwood High School in upper right.
GMA-14 will take a final vote on January 5 on the final DFCs. You still have time to protest.
Posted by Bob Rehak on 12/31/2021
1585 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/06/20210303-RJR_5778.jpg?fit=1200%2C800&ssl=18001200adminadmin2021-12-31 10:48:382021-12-31 11:09:51Top Stories of 2021 in Review
A myth being promulgated in Harris County Commissioners Court and certain low-to-moderate income (LMI) watersheds these days goes something like this:
The FEMA Benefit/Cost Ratio (used to rank grant applications for flood-mitigation projects) favors high-dollar homes.
That disadvantages less affluent, inner-city neighborhoods compared to more affluent suburbs.
Therefore, less affluent neighborhoods get no help and the more affluent neighborhoods get it all.
This post busts that myth. But it won’t stop activists from demanding more “equity.”
If you look at all flood-mitigation spending in Harris County since 2000, on average, less affluent watersheds already receive 4.7X more partner funding per watershed than their more affluent counterparts.
Analysis of data obtained via FOIA request
Myth Ignores Other Factors, Frequently Leaps to Wrong Conclusions
Like much of political discourse these days, the myth focuses on a narrow sliver of truth, ignores other factors, and frequently leaps to the wrong conclusions.
An analysis of Harris County Flood Control District data going back to the start of this century shows how far off the myth can be.
Today, I focus on partner grants because they represent such a huge percentage of the flood-bond budget and because there is so much misinformation floating around about them.
And I will look at partner funding from the standpoint of outcomes, not just processes (as in the myth).
Methodology for Analysis
For this analysis I obtained Harris County Flood Control District spending data between 1/1/2000 and 9/31/2021 via a Freedom of Information Act (FOIA) request. I requested the data by watershed, decade, pre-/Post Harvey, source of funding (local vs. partner), and type of activity (i.e., engineering, right-of-way acquisition, construction and more). I cross-referenced this with other data such as flood-damaged structures, population, population density, and percentage of low-to-moderate income (LMI) residents.
When considering grants, the percentage of LMI residents in a watershed takes on special significance. Department of Housing and Urban Development (HUD) grants often require high percentages of LMI residents in the area under consideration.
In the charts below, you will see references to watersheds with LMI populations above and below 50%. Above 50% means more than half the residents in the watershed have an income LESS THAN the average for the region. Below 50% means more than half the residents earn more than the regional average.
Harris County has 23 watersheds. Eight have LMI percentages above 50% (less affluent). Fifteen have LMI percentages below 50% (more affluent).
When reviewing the charts below, pay particular attention to the italicized words: Total, Partner, and On Average. They represent three different ways to look at the same question: Do housing values disadvantage an area when applying for grants?
For this analysis, I focused only on the long term, since decisions on more than a billion dollars in flood-bond grants are still outstanding.
FOIA Analysis Contradicts the Popular Myth
One of the first things you notice when you look at watersheds above and below 50% LMI, is that the eight least affluent watersheds have gotten more than 60% of all dollars actually spent on flood mitigation since 2000.
Less affluent watersheds, despite being half as numerous, received 60% of all dollars since 2000.
Because the allegation was that partnership grants favored affluent areas, I then analyzed whether partner dollars went mostly to affluent or less-affluent watersheds. The answer is less affluent…overwhelmingly.
More than 70% of all partner dollars in the last 22 years went to the eight less-affluent watersheds.
The last observation by itself is telling. But because of the widely different number of watersheds in each group, I also wanted to calculate the average partner dollars per watershed in each group. This blows the “rich neighborhoods get all the grants” argument to pieces. Less affluent watersheds got, on average, 4.7X more.
Dividing the total partner dollars by the number of watersheds in each group shows that less affluent watersheds average 4.7X more than affluent ones.
This busts the myth. But digging even deeper into the data reveals two things: wide variation between sources of funding and withinLMI groupings.
USACE Funding Skews Partner Totals
The U.S. Army Corps of Engineers (USACE) accounts for much of the partner funding. USACE has provided significant funding for projects in the Sims, Brays, White Oak, Hunting, and Greens Bayou watersheds. The Clear Creek watershed will also soon see work on a new USACE project. USACE has completed its planning process and proved positive benefits to national economic development. That made projects worthy of Federal investment.
Halls Bayou: Digging Deeper
The Halls Bayou watershed also went through the USACE planning process, but the results did not show enough flood-damage-reduction benefits to outweigh the costs of the proposed projects. Thus, the Halls Bayou watershed currently has no USACE-funded projects.
Despite that, Halls has received more partner funding than 16 other watersheds since 2000. Only two watersheds in the affluent group of 15 received more partner funding. See the table below.
Total and partner spending by watershed since 2000 arranged in order of highest to lowest LMI percentages.
USACE also evaluated the more affluent Buffalo Bayou; results showed that costs outweighed the flood-damage-reduction benefits there.
Despite Halls having the highest percentage of LMI residents in Harris County, Halls has received more total funding and 2.5X more partner funding than Buffalo Bayou in the more affluent group.
FEMA Considers More than Home Values, Not All Grants Come From FEMA
While it’s true that FEMA considers housing values as a factor in benefit/cost ratios, benefit/cost ratios (BCRs) also consider factors such as:
The number of structures damaged
Threats to infrastructure
Proximity to employment centers
Need for economic revitalization
Percentage of low-to-moderate income residents in an area
Number of structures that can be removed from the floodplain by a project.
USACE funds dozens of different types of flood-mitigation programs. Many support national defense, the national economy, strategic interests, the environment, commerce and navigation.
So don’t settle for soundbites. They often mislead.
Posted by Bob Rehak on 12/30/2021
1584 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/12/Screen-Shot-2021-12-29-at-4.53.47-PM.png?fit=1366%2C740&ssl=17401366adminadmin2021-12-29 21:28:052021-12-30 14:37:20Equity Myth Buster: “Rich Neighborhoods Get All the Flood-Mitigation Funding”
Making conclusions based on hearsay or a glance at a chart could be self-defeating. There is more to the story.
Partner Funds Make It All Possible
We anticipated 43% of the dollars in the flood bond would come from partners such as FEMA, HUD and the TWDB. We also anticipated it would take another 16% in local matching funds to attract the 43%. So 59% of the flood bond revolved around partner funds. Only 41% was local cash to pay for projects totally out of pocket.
From the project spreadsheet approved by voters in 2018.
Excluding Partner Funds Could Accelerate Construction in LMI Neighborhoods, Deny Others
David Berry, the County Administrator, proposed the partnership exclusion to accelerate construction of projects in Low-to-Moderate Income (LMI) watersheds, such as Halls. Halls, in particular, has waited on grant awards from the US Department of Housing and Urban Development (HUD) longer than most.
A HUD decision is expected sometime in January, according to the Texas General Land Office, which distributes HUD grants in Texas. So it’s not clear how much residents gain by Berry’s proposal. And they could lose big.
Most of the HUD grant applications for Halls are on a 90:10 basis, meaning the local share is only 10%. So excluding these grants means increasing the local contribution for that portion of the budget by 9X. That could cost local taxpayers hundreds of millions of dollars. For instance, HCFCD budgeted $500 million for Halls drainage alone. 90% of that is $450 million…to cover 2.4% of the county!
The effect would be to take money from affluent watersheds – which don’t qualify for HUD 90:10 grants – and shift it to LMI watersheds. No one then would get the grants and something would have to give somewhere down the road.
One Third of Way Through Flood Bond: Good Time to Take Stock
At the end of this month, exactly one third (3 years, 4 months) of the 10-year flood bond will have expired. So this is a good time to review spending versus projections.
Thirty-three percent of the way in, we’ve expended a little more than 16% of the flood-bond funds. While that may sound like a slow start, one must consider project lifecycles. Projects start with studies (feasibility, preliminary engineering, final engineering, design). These determine and validate cost projections. They also form the basis for grant applications, a plan and bids. But they are the least expensive part of a project. Together, they comprise only one eighth of project costs.
The expensive parts follow. They include right of way acquisition and construction. Those comprise more than three-quarters of all project costs. See the pie chart below which shows averages for the last two decades.
Average percent of costs in various project stages since 2000. ROW (Right of Way) Acquisition includes purchase of land upon which projects will be built.
For most flood-bond projects, we’re just now getting to the expensive phases. So I wouldn’t worry too much about that 16% overall average right now.
Spent/Unspent Funds by Watershed Gives Greater Insight
You can gain more insight by looking at spent and unspent dollars in each watershed.
Height of bars shows total amount budgeted per watershed in flood bond. Blue areas show dollars spent to date. Does not include any funds spent prior to flood bond.
From the charts above and below, you can see that spending rates vary widely among watersheds. Brays has consumed 57% of its budget already. On the opposite end of the spectrum, Sims has consumed just 1.6% of its. Why the wide variation?
To understand, we need to look at unique circumstances in each watershed. The chart below makes it easier to see actual spending as a percent of the budget that voters approved for each watershed in the flood bond.
Percentages represent the portion of budget spent to date. See discussion below for explanations of ranks.
The height of some of the bars above could be “predicted” by referring to the flood bond equity prioritization framework. Brays and Greens Bayous, for instance, are two watersheds with high percentages of LMI residents (58% and 57% respectively).
But others cannot. More than half the residents in Goose Creek/Spring Gully, Hunting, White Oak, Halls, Vince and Sims Watersheds also qualify as LMI. But dollars spent to date in those watersheds are far lower as a percent of the total budget. To see why, you need to put the numbers in a bigger context that includes:
Investment Prior to Flood Bond
Size of Total Budget for Each Watershed
Percentage of Partner Funds
Grant Application Status
Stage of Project Lifecycle
Bigger Context Shows Reasons for Variance
Brays and Greens had a large number of shovel-ready projects that had already been studied and approved when the flood bond passed. They were just waiting for dollars to become available. So they had head starts.
Other factors explain LMI watersheds further down the curve:
Sims received $380 million in federal funding for 23 Army Corps projects that finished construction by 2015. As a result, Sims was the only bayou in Harris County that stayed within its banks during Harvey. None of that spending shows up in the Bond Program charts. Because it’s already done!
White Oak received full funding in the Bi-Partisan Budget Act of 2018. The Army Corps also started addressing many projects there before the flood bond.
Vince lies wholly within the City of Pasadena and is primarily the City’s responsibility.
Halls is the poorest watershed (71% LMI) and has only spent 6% of its projected budget to date. Lest you attribute this to racism, understand that the bond allocated more than HALF A BILLION DOLLARS to Halls. In percentage terms, the $29 million dollars spent to date looks small. But in absolute dollars, it outranks 15 other watersheds.
Far more affluent watersheds – such as Buffalo Bayou, Cedar Bayou, the San Jacinto River, Barker, Willow Creek, Armand Bayou, Galveston, Luce Bayou and Jackson Bayou – have each received fewer dollars from the flood bond than Halls.
HCFCD had just finished a watershed plan for Halls Bayou in 2018 when the flood bond passed. That explains the size of the watershed budget as well as the late start compared to Brays, White Oak, Greens, and Sims.
Other factors also explain affluent watersheds further up the spending curve, such as Little Cypress. HCFCD started working on that watershed long before the flood bond, too. Dollars spent to date on Little Cypress primarily reflect right-of-way acquisition costs, not construction. It’s also important to understand that the total budget for Little Cypress is only 37% of the total budget for Halls.
Creating a Win-Win For Everyone
In another three years and four months, these charts will look totally different than the ones you see today. Construction costs will surge for some and be long gone in the rear view mirror for others.
In my opinion, we need to stop creating chaos with endless tinkering in the bond program. The people have spoken. Leaders should listen. Let’s stop changing the allocation formula, focus on construction, and work like hell to win those grants. Then everybody wins.
Posted by Bob Rehak on 12/28/2021
1582 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/12/Flood-Bond-Allocation.jpg?fit=1200%2C804&ssl=18041200adminadmin2021-12-27 20:18:272021-12-28 13:28:32“Excluding” Partner Funds Could Lead to Shortfalls in Flood-Mitigation Funding
At the last meeting of Harris County Commissioners Court, Harris County Flood Control District (HCFCD) released a flood-bond update that shows spending through the end of November 2021. It provides a quick and easy way to see what your money is being spent on and where it is going. This differs from data reported recently from my FOIA Request. That data goes back to 2000 and looks at data pre- and post-Harvey, not just the start of the flood bond.
November Highlights
Below, some of the highlights from the November spending update:
Professional services invoices paid to date total $296 million. In November, payments totaled $338 thousand. Three quarters of that amount went to minority- or women-owned businesses.
HCFCD has awarded $354 million in construction contracts. Five more were awarded last month totaling $335 thousand.
Total spending since the approval of the flood bond through the end of November totaled $885 million. Of that, $447 million came directly from bond funds. Another $321 million came from grants. Other local funds totaled $117 million.
Three years into a ten year bond program, we’ve expended 17.9% of the anticipated total.
Home buyouts continue to drag out. HCFCD has completed 676, but 613 remain in the pipeline.
Brays Bayou still leads the dollar derby by a factor of two compared to the next three contenders. Brays has received $162 million flood-bond dollars to date. Cypress Creek, Addicks, and Greens Bayou have each received approximately half that. Then there are all others.
Where your flood-bond dollars have gone through the end of Nov 21..
Dollars spent in each watershed through the end of November.
Dollars funded in each watershed through the end of November.
Active maintenance projects and their values in December.
Active capital projects and their values in December.
The visual nature of this report makes it easy to see where your money is going at a glance.
Posted by Bob Rehak on 12/20/2021
1574 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/12/20211220-Funding-by-Watershed-through-Nov-21.jpg?fit=1200%2C916&ssl=19161200adminadmin2021-12-20 21:23:122021-12-20 21:40:09Flood-Bond Update through End of November 2021
Widening of Hunting Bayou, one of the poorest and most flood-damaged watersheds in the county, is kicking into high gear.
Annual Rate of Spending Almost Quadruples since Harvey
According to data obtained as part of a Freedom of Information Act (FOIA) request, Harris County Flood Control District and its partners (mainly the Army Corps and City of Houston), spent $44 million on flood mitigation in the Hunting Bayou watershed between 1/1/2000 and Hurricane Harvey.
That averaged $2.4 million per year for those 18 years. However, in the 4 years since Harvey, HCFCD has spent $37 million – more than $9 million per year.
That rate of spending averages 3.75X higher after Harvey than before.
HCFCD Spending Data Obtained via FOIA Request
Here’s a breakdown.
From FOIA Request.Hunting Bayou flood-mitigation expenditures by time period and category since 1/1/2000 through end of third quarter 2021.
Focus of Current Construction Activities
The upstream portion of Hunting Bayou parallels the south side of Loop 610 for most of its length. Where North Loop 610 turns south, Hunting cuts under it between McCarty and Wallisville Roads. From there it continues east. It then turns southeast at San Pedro Street and eventually joins Buffalo Bayou and the Ship Channel.
Note width of floodplains in red box. HCFCD is now widening Hunting between the left and right boundaries of the box.From Harris County Flood Education Mapping Tool. Blue = 100-year. Green = 500-year floodplain.
The Hunting Bayou watershed has the second highest percentage of low-to-moderate income (LMI) residents in the county (69%) after Halls Bayou (71%) immediately to the north.
Hunting also is heavily industrialized with rail yards, tank farms, manufacturing, and shipping companies. The highest points of land are the railroad tracks. Within the red box above, you can see how they affect the flood plain.
After driving around the neighborhoods along Hunting Bayou for an entire day, it appears that the worst storm damage is in the red box above. Many homes are boarded up and abandoned in this area. Others have been elevated. Some have been renovated and are waiting for the next flood.
Current Construction Photos of Bayou Widening Efforts
HCFCD bayou-widening efforts focus on this area right now. They extend from US59 on the west to approximately Wayside Drive on the east. Bayou widening may be an understatement. HCFCD appears to be creating a long series of connected detention basins, some more than 450 feet wide and several city blocks long that narrow at bridges.
This should help drain water from nearby neighborhoods during heavy storms. See pictures below all taken on Sunday, 12/19/2021. They generally trend from west to east, starting at US59 and heading downstream.
Looking east at first of numerous ponds along channel of Hunting Bayou. Photographed from over US59. Loop 610 is in upper left.
Looking east over Hunting Street. Loop 610 on left.Note new hike and bike trails in this and other pictures below.
Looking east from Kashmere Street at a previously excavated area now covered with grass and newly excavated areas beyond it.
Looking east from over Wipprecht Street at work in progress.
Looking east toward Lockwood from Pickfair Streetand one of the constrictions mentioned above.
Closer shot of constriction at Lockwood.
Looking east from Hutcheson Park
Opposite angle. Looking west over expanse of Hutcheson Park. Loop 610 on right.
Looking NE from the eastern end of Hutcheson Park, where Hunting cuts under 610.
Looking NE from over Loop 610 toward Homestead Detention Pond in background.Kelly Street cuts left to right through top of frame.s
Looking east from over Homestead at limit of current downstream work.
Funding Flows to Damage
Altogether, the current excavation work stretches 3.33 miles.
In the last five major storms (Allison, Tax Day, Memorial Day, Harvey, Imelda), 15,763 structures have flooded along Hunting Bayou. That ranks 7th among all Harris County Watersheds. But one must remember, that Hunting, comprises only 31 square miles. That ranks it 19th in size out of 23 watersheds. The damage per square mile ranked #2 (508.5 structures).
Another reason spending has accelerated here is political policy – namely the Equity Prioritization Framework implemented a year after the flood bond passed.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/12/20211219-DJI_0152.jpg?fit=1200%2C799&ssl=17991200adminadmin2021-12-19 20:53:442021-12-19 23:31:42Widening of Hunting Bayou Kicks into High Gear
Since 2000, White Oak Bayou has received $386.8 million in Harris County Flood Control (HCFCD), federal, and local partner funding. That ranks it #2 in dollars received among all 23 Harris County Watersheds, second only to Brays Bayou at $544.5 million. Data received via a Freedom of Information Act (FOIA) request, showed that these two watersheds alone have received close to a billion dollars out of $3 billion spent between 1/1/2000 and the end of the third quarter this year. Said another way…
Two watersheds out of 23 received about a third of all HCFCD flood-mitigation spending in the last 22 years.
White Oak is difficult to photograph. As with Brays, homes and apartments back up to White Oak almost the entire way. They largely conceal most of it from public view except near bridges. Those homes and apartments also conceal the magnitude of construction from public view.
A Low-to-Moderate Income Watershed
Within the watershed, White Oak has slightly more low-to-moderate income (LMI) residents (51%) than those who earn above the average for the region. Other interesting stats:
It comprises 111.1 square miles. That ranks #6 among all watersheds.
White Oak has 468,214 people. That ranks #3 among all watersheds.
White Oak ranks #3 in total damage and #5 in damage per square mile.
Continuous Improvement for Decades
Money has poured into the White Oak watershed – as it has for Brays – because of the large number of flooded structures and associated damage. White Oak has had almost 26,000 structures flooded in the last five major storms – Allison, Tax Day, Memorial Day, Harvey and Imelda. That ranks it #3 in total damage among all 23 Harris County Watersheds.
The 2018 Bipartisan Budget Act helped fund the latest round of construction shown below on White Oak as well as Hunting and Brays Bayous. All three started more than 20 years ago and advance sporadically as more money becomes available.
Fighting Constrictions of Development to Make Room for More Floodwater
The photos below show HCFCD’s and the Army Corps’ commitment to completing a number of major projects along White Oak. Residential and commercial developments pressing against the bayou along its length make that difficult. They leave little room for widening to accommodate more floodwater. As a consequence, HCFCD is forced to buy out whole subdivisions to make room for detention basins.
Regardless, I photographed an impressive amount of construction along the length of White Oak between FM1960 and West Little York. Below are 10 out of more than 120 photographs. I took them all on 12/17/2021.
White Oak Bayou widening and deepening. Photographed from Kari Court.
Note how close houses are to the channel. Making more “room for the river,” as the Dutch say, would require buying out many of the homes you see below.
White Oak Bayou photographed from over Lewis Street.
Looking upstream at White Oak from Gessner
Looking downstream from Gessner. Another example of not leaving “room for the river.” t
Looking SW across large detention basin. White Oak cuts through top of frame from left to right. Fairbanks North Houston cuts through top of frame on right.
Looking NE from over Fairbanks North Houston. White Oak cuts through center of frame. Note Greenspoint on horizon, right of center.
White Oak near Antoine, looking S toward downtown and Galleria on horizon.
White Oak from Tall Pines Drive looking SE.
White Oak from Deep Forest Drive looking downstream.
HCFCD currently has $45 million in ACTIVE construction projects underway in White Oak Bayou. But many more construction projects along the bayou are still pending buyouts to make way for more detention basins.
Of the $386 million spent on White Oak in the last 23 years, $235 million has gone to buyouts and right-of-way acquisition compared to $90 million so far for construction. White Oak buyouts have cost 2.6X more than construction. Normally, buyout and construction costs differ by only a few percentage points.
That tells you how how many homes and businesses are overcrowding the flood plain!
And that brings to mind my grandmother’s favorite saying, “An ounce of prevention is worth a pound of cure.”
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/12/20211217-DJI_0098.jpg?fit=1200%2C799&ssl=17991200adminadmin2021-12-17 20:42:492021-12-19 11:24:48White Oak Bayou Gets A Makeover…Again
Harris County Commissioners Court considered a motion today by the County Administrator to change the prioritization of flood-bond projects for the fourth time. By a 3-2 party-line vote, they approved a proposal that could soon lead to depriving outlying neighborhoods of flood bond funding. The vote today was preliminary. Before they take a final vote, they will submit the proposal to the Community Flood Resilience Task Force (CFRTF) for input, then take a final vote in 60 days. Based on past experience, the CFRTF will likely rubber stamp the three recommendations in the proposal:
Exclusion of partner funding
Inclusion of street flooding in 500 year floodplain
Counting people not structures when measuring benefits
Exclusion of Partner Funding
The exclusion of partner funding will mean that 90% match grants from the US Department of Housing and Urban Development (HUD) will no longer be available to anyone. Inner city neighborhoods will use flood-bond money to complete their projects instead of HUD money. And more affluent, outlying neighborhoods do not qualify for HUD grants.
County Judge Lina Hidalgo, Precinct 1 Commissioner Rodney Ellis, and Precinct 2 Commissioner Adrian Garcia all admitted during debate that there wasn’t enough money to complete all the bond projects. But they voted to consider the allocation changes regardless.
Precinct 4 Commissioner Jack Cagle and Precinct 3 Commissioner Tom Ramsey also agreed there wasn’t enough money to complete all bond projects. However, they voted against the proposal.
The 3-2 vote will send the proposal to the CFRTF for input. To date, the CFRTF has rubber stamped everything proposed by Democrats that benefits low-to-moderate income (LMI), inner-city neighborhoods at the expensive of outlying neighborhoods.
That means construction funds may not be available for outlying projects by the time inner city neighborhoods complete theirs.
Those who compiled the list of bond projects were counting on approximately $2.5 billion in partner funding. The Flood Control District has already secured more than a billion just three years into a ten year bond. But this move could now jeopardize a large portion of the remaining partner funding.
Inclusion of Street Flooding
Not one project in the flood bond addressed street flooding. That is not within HCFCD’s scope of responsibility.
Regardless, Commissioner Garcia said, “People don’t care where they flood from. They just want it fixed.” He never addressed the budget issue or who was responsible for cleaning out those roadside ditches – Garcia, Ellis, Turner and other City mayors!
Expanding the scope of the bond and eliminating partner funding will mean even fewer dollars left over to address flooding in outlying neighborhoods.
I have photographed hundreds of clogged roadside ditches like these in watersheds inside Beltway 8. Dems now want to use what’s left of your flood bond money to clean them out even though the flood bond never mentioned them.
Counting People Not Structures
Typically, the objective of flood-mitigation projects is to remove structures, not people, from a flood plain. By counting people, not structures, in an evaluation matrix, you push funding toward more densely populated neighborhoods. Normally, helping more people is good. But what if the density is vertical, not horizontal?
Let me give you an example. Consider an apartment building with a hundred residents. But none lives on the ground floor.
Now consider 25 single family homes each with three people. All live on the ground floor.
Project A could take a 100 people out of the flood plain whose apartments would not flood. Project B would take 75 people out of the floodplain and prevent damage to 25 structures that would flood. Should A or B get the flood-mitigation project?
This provision would also drive funding away from outlying neighborhoods which generally have fewer apartments.
The People Spoke and Are Being Ignored
The People – with a Capital P – voted on the flood-bond and approved it overwhelmingly. Now its being repeatedly changed by a few individuals to push ever more funding to inner-city neighborhoods which already get the lion’s share. These latest moves could deprive outlying neighborhoods of construction dollars needed to complete projects.
Seems to me that the three Dems and their proxies are depriving half the county of their votes and taxes.
The two Republicans on Commissioners Court, Precinct 4 Commissioner Jack Cagle and Precinct 3 Commission Tom Ramsey, argued against the changes.
Commissioner Cagle argued that “We must do what we say. We must work on projects in the bond.” He went on, “Changing the projects included in the 2018 flood bond is a bad idea. The promises we made to voters in 2018 are sacred. While I support the concept of asking to finance more flood mitigation projects in the future, the public has to know that we can be trusted to keep our word.”
Top 4 LMI Watersheds Receive 53% of All Funding since 2000
However, when you look at spending to date and the ever-changing “equity” guidelines, we’re far from approaching anything that resembles equity. And we’re getting farther from it with each round of changes to the so-called “equity” guidelines.
Four LMI watersheds out of 23 (Greens, Sims, Brays and White Oak) have received 53% of ALL funding since 2000, yet their representatives complain about historical prejudice and demand more.
Analysis of HCFCD Spending Data from 1/1/2000 through Q3 2021 obtained via FOIA request
For the record, that’s $1.6 billion out of $3.1 billion during the period of comparison.
Top LMI Watersheds Get More than Twice as Much as Top NON-LMI Watersheds
Comparing those 4 LMI watersheds with the most dollars to the four NON-LMI watersheds with the most, we can see that LMI watersheds have received more than two dollars for every dollar received by a non-LMI watershed.
Pie represents total dollars spent among top four LMI and NON-LMI watersheds. An LMI watershed is one where more than half the residents earn below the average annual income for the region.
The four LMI watersheds receiving the most money included Brays, Greens, Sims, and White Oak Bayous.
The four NON-LMI watersheds receiving the most included Cypress Creek, Addicks, San Jacinto and Buffalo.
All dollars include HCFCD and partner spending from 1/1/2000 through Sept. 30, 2021.
Bottom 4 LMI Watersheds Get 3X More than Bottom 4 NON-LMI
At the opposite end of the spectrum, the four LMI watersheds receiving the least money have received 3X more dollars than the four lowest NON-LMI watersheds since 2000.
Comparison of total dollars spent in the four lowest LMI and NON-LMI watersheds since 2000 through the end of Q3 2021.
There are only 8 LMI watersheds hence the comparison of groups of four.
The four LMI receiving the least dollars since 2000 include Halls, Hunting, Goose Creek/Spring Gully, and Vince.
The four NON-LMI watersheds receiving the least include Luce, Galveston, Jackson and Carpenters.
But what about those other NON-LMI watersheds in the middle of the spending pack? Simple. Altogether, the scale is already so tilted, they can’t tilt the balance back much. See comparison below of ALL LMI and NON-LMI watersheds.
LMI vs. Non-LMI flood-mitigation funding through Q3 2021 for ALL watersheds. Note Non-LMI watersheds outnumber LMI watersheds almost 2:1, yet have gotten only a little more than a third of total funding.
Partner Funding Also Favors LMI Watersheds, Not Affluent Ones
Anyone who doubts the percentages above can check my calculations. Here’s the raw spending data for each watershed with percentages of low-to-moderate income residents – including pre- and post-Harvey spending.
I’ve also included partnership funding since 2000 for each watershed. Because the dollars involved vary widely and because Non-LMI watersheds outnumber LMI watersheds 2:1, the fairest way to compare partner funding is by looking at it as a percentage of total funding for each watershed since 2000.
Watersheds with a high percentage of LMI residents are not disadvantaged in total spending or partner funding. LMI watersheds are those with a percent of LMI residents above 50%.
During that period, 26% of all flood mitigation funding in Harris County has come from partners, such as FEMA, HUD, the Army Corps, TWDB or cities. However, LMI watersheds have attracted a higher percentage of partner spending: 30%.
While that’s not a huge advantage, it shows conclusively that LMI watersheds, as a rule, are not disadvantaged when it comes to partnership funding.
The correlation between total dollars and partnership dollars spent in all watersheds is not a perfect (1.0), but very high at .79.
In fact, the two highest partner percentages both belong to LMI watersheds (Sims at 55% of the watershed total and White Oak at 33%). The two lowest partner percentages belong to two of the most affluent watersheds (Willow Creek at 6% and and Barker at 3%).
This debunks another myth frequently heard in commissioners court, i.e., that partner dollars always go to the watersheds with the highest home values.
Conclusion: Organize, Protest
Outlying communities must organize and protest en masse before commissioners take a final vote on shifting even more dollars to LMI communities based on bad information. If they change the deal on this flood bond, they’ll do it again on the next.
Fool me once, shame on you. Fool me twice, shame on me.
Posted by Bob Rehak on 12/14/2020
1568 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2021/12/Screen-Shot-2021-12-14-at-8.56.24-PM.png?fit=1616%2C854&ssl=18541616adminadmin2021-12-14 22:23:322021-12-15 09:44:23Move by Dems Could Mean Flood-Bond Projects in Outlying Neighborhoods Never Get Built