flood bond update

Flood-Bond Update through End of November 2021

At the last meeting of Harris County Commissioners Court, Harris County Flood Control District (HCFCD) released a flood-bond update that shows spending through the end of November 2021. It provides a quick and easy way to see what your money is being spent on and where it is going. This differs from data reported recently from my FOIA Request. That data goes back to 2000 and looks at data pre- and post-Harvey, not just the start of the flood bond.

November Highlights

Below, some of the highlights from the November spending update:

  • Professional services invoices paid to date total $296 million. In November, payments totaled $338 thousand. Three quarters of that amount went to minority- or women-owned businesses.
  • HCFCD has awarded $354 million in construction contracts. Five more were awarded last month totaling $335 thousand.
  • Total spending since the approval of the flood bond through the end of November totaled $885 million. Of that, $447 million came directly from bond funds. Another $321 million came from grants. Other local funds totaled $117 million.
  • Three years into a ten year bond program, we’ve expended 17.9% of the anticipated total.
  • Home buyouts continue to drag out. HCFCD has completed 676, but 613 remain in the pipeline.

GANNT Charts Show Progress in All Watersheds

The San Jacinto River Basin has 10 active projects in various stages of development. Cypress Creek has 10. And Spring Creek has 4. To see what stage they are at, see the GANNT Charts on Pages 4 through 9.

Brays Leads Dollar Derby By Wide Margin

Brays Bayou still leads the dollar derby by a factor of two compared to the next three contenders. Brays has received $162 million flood-bond dollars to date. Cypress Creek, Addicks, and Greens Bayou have each received approximately half that. Then there are all others.

Where your flood-bond dollars have gone through the end of Nov 21..

This report PDF also contains maps that show:

  • Dollars spent in each watershed through the end of November.
  • Dollars funded in each watershed through the end of November.
  • Active maintenance projects and their values in December.
  • Active capital projects and their values in December.

The visual nature of this report makes it easy to see where your money is going at a glance.

Posted by Bob Rehak on 12/20/2021