Tag Archive for: glo

GLO Releases Status of Disaster-Relief, Flood-Mitigation Applications

2/28/25 – Today, the Texas General Land Office (GLO) released the status of Community Development Block Grant (CDBG) disaster-relief and flood-mitigation applications from Harris County’s Flood Control District and Housing & Community Development Department.

The grant applications cover almost $1.1 billion dollars in aid for Harris County relating to Hurricane Harvey alone, which the GLO manages for the U.S. Department of Housing and Urban Development.

Today’s updates cover the status of more than 60 projects. A little more than half have already been approved. Twenty-one are still in review. And eight still have not been submitted yet.

Separately, yesterday Harris County Commissioners adopted three resolutions to limit financial exposure during the Federal grant funding freeze.

Let’s look at the disaster-relief and flood-mitigation applications first, then the issue of financial exposure.

HCFCD Disaster Relief Projects

Of the 11 disaster relief projects published by Flood Control, the GLO has already approved 10. Flood Control has not yet submitted the application for the Genoa Red Bluff Regional Stormwater Detention Basin.

All projects in this list total approximately $269 million.

Provided by GLO on 2/28/25

For descriptions of each project above, click here.

HCFCD Flood-Mitigation Projects

HCFCD is submitting 18 projects in the flood-mitigation category. Of those, the GLO has started reviewing 16. HCFCD has yet to submit two.

The 16 projects submitted to date total approximately $510 million out of $541,847,826 allocated for this category.

Only one project below – Taylor Gully/Woodridge – is in the Kingwood Area.

Provided by GLO on 2/28/25.

For descriptions of each project, click here.

For a printable PDF of these two lists, click here.

Housing and Community Development Mitigation and Planning

Harris County’s Housing & Community Development Department also has projects in two categories: mitigation and planning.

Mitigation includes nine projects totaling approximately $150 million. GLO has already approved all except for two still in review.

HC H&CD has already issued notices of intent to release funds for approved projects above.

Housing & Community Development has also requested money for 23 planning studies. The 18 approved or still in review total $10.775 million.

For a printable PDF of these two lists, click here.

County Making Contingency Plans for Federal Grant Funding Freeze

A large portion of the Special Harris County Commissioners Court Meeting yesterday concerned planning for uncertainties regarding the federal grant funding freeze. Specifically on the agenda:

  • Item 11 tried to limit the County’s financial exposure in case projects were started, but promised funding did not come through on the back end.
  • Item 164 requested HCFCD to provide an update on every 2018 flood-bond project (completed, in progress, and not yet started). Commissioners requested dollars expended to date by life cycle stages, locations and subprojects. They also requested a listing of how all projects scored and ranked on the County’s Equity Prioritization Framework.

Those two items alone consumed two hours.

Re: Item 11, Commissioners adopted three motions unanimously:

  • Motion 1 directed OMB to maintain a maximum monthly average of $100 million in outstanding receivables relating to federal grants and to update commissioners court monthly on balances.
  • Motion 2 directed OCA, OMB, the County’s Strategic Planning Committee, and impacted departments to make recommendations for dealing with at-risk, federally funded programs.
  • Motion 3 allowed payment of grant-funded invoices if federal funding is available.

The motions govern management of invoice payments related to grants and establish protocols for prioritizing grant programs.

Rationale Behind Motions in Item 11

Watch the discussion of Item 11 in this video of yesterday’s Special Commissioners Court Meeting. Make sure you click on the segment labeled “Departments 2 of 2.” The discussion starts at 11:02 A.M.

The commissioners want to prevent a significant impact on cash flow and future budget cycles. Their plan includes setting aside general funds and cooperating with the Strategic Planning Committee to identify priority grants.

Additionally, there are strategies to identify at-risk grants, limit financial exposure, and ensure that ongoing expenditures are more closely aligned with the likelihood of reimbursement.

Motion 3 would only allow payment of project/program related invoices if reimbursement seems likely.

The measures apply to all federal grants, not just those listed above. For instance, ARPA funding expires next year and will affect many county employees.

The county averages about $70 million in liabilities every month related to payment of grant invoices (for which the Federal government later reimburses the county). The $100 million limit in Motion 1 reflects an amount that the county cannot afford if the Feds withhold payment.

For the time being, everyone is proceeding as though the funding appropriated by Congress will come through.

Most of those I interviewed for this article believe the President does not have the authority to override laws passed by Congress with executive orders. However, Department of Government Efficiency (DOGE) budget cuts could have the impact of hamstringing other departments, such as HUD.

For instance, I talked to two government officials on the condition of anonymity who discussed rumors of staffing cuts greater than 80% at HUD. That could affect reimbursement for tens of billion of dollars in CDBG funds nationwide, because the Department might not have the personnel to process reimbursements.

That could affect most of the disaster-relief and flood-mitigation applications above. But more on that at a future date when and if the rumors become real.

Posted by Bob Rehak on 2/28/25

2740 Days since Hurricane Harvey

GLO, HUD Funding Approved for 7 HCFCD Projects So Far

11/20/2024 – The Texas General Land Office (GLO) confirmed funding approval from the U.S. Department of Housing and Urban Development (HUD) for seven Harris County Flood Control District (HCFCD) projects.

In June of last year, HCFCD submitted two projects lists to GLO for $825 million in HUD Community Development Block Grant disaster relief (CDBG-DR) funding and flood mitigation (CDBG-MIT) funding.

Since then, HCFCD has worked with GLO to finalize the HUD applications. HCFCD presented an update to Commissioner’s Court in early October, 2024. Today, GLO provided an update to the update.

CDBG-DR Projects

According to an email from GLO spokesperson Brittany Eck received today, seven DR projects have received funding approvals to date. They include:

Eck also said that five more CDBG-DR projects are under final quality-control review. “We are making sure the project submissions are complete and meet all federal eligibility requirements so that there are not issues or concerns down the road.”

Disaster Relief projects have the tightest deadlines. So, all parties focused on those first.

CDBG-MIT Funding Still Under Review

“Seventeen CDBG-mitigation projects are still in various stages of preliminary review,” said Eck.

“We are working back and forth on requests for more information required by HUD on many of the projects,” said Eck. “We continue to work very closely with the HCFCD team to make sure they have all available resources needed to complete the applications. Overall our team is very pleased with the progress being made and the relationship continues to be strong.”

Only two mitigation projects have not yet been submitted for preliminary review.

  • Kickerillo-Mischer Preserve Channel Rehabilitation (100-00-00-X115)
  • Channel Conveyance Improvements (C147-00-00-E002) in the Sims Bayou Watershed.

Tremendous Progress

“HCFCD has made tremendous progress on these funds,” said Eck. “However, the rate of approval may not yet demonstrate the progress being made behind the scenes.”

She added, “This process, especially considering the amount funds being administered is an extremely lengthy federal process. Additionally HCFCD has needed to combine projects due to functionality and the GLO is working closely with them to ensure eligibility in the most efficient timeframe imaginable.”

Kingwood Projects Not Mentioned in This Update

Eck did not comment on the status of two Kingwood projects. I can only assume they are still under review. She did not mention any that had been eliminated.

The two Kingwood projects:

Woodridge Village detention basin photographed on 10/25/24. Project paused pending outcome of HUD financing approval.

In its October update to Commissioners Court, HCFCD said the Woodridge Stormwater Detention Basins were originally below the funding line for CDBG-DR.

“The original engineering analysis indicated that only Woodridge Basin Compartment 1 was needed for the Taylor Gully mitigation,” said the update. “As the analysis has progressed it indicates that Compartment 2 (or a portion of it) may also be needed. Due to other projects potentially reducing in budget from the initial estimates, there may be funding available to include the Woodridge basin in the Taylor Gully project.”

That word “may” in the last sentence worries me.

HCFCD did not propose the Kingwood Diversion Ditch project for HUD consideration. HCFCD called the diversion ditch one of the two most important projects in Kingwood. That funding will have to come from somewhere else.

Posted by Bob Rehak on 11/20/24

2640 Days since Hurricane Harvey

GLO Posts Six State Action-Plan Amendments for Public Comment

9/3/2024 – Today, the Texas General Land Office (GLO) posted six state action-plan amendments for public comment. The amendments reallocate remaining money from federal grants for disasters between 2008 and 2019.

Includes Disaster Recovery Reallocation Program

Each of the six amendments includes a new Disaster Recovery Reallocation Program (DRRP). The DRRP will let the GLO utilize de-obligated and un-utilized funds remaining within the action plan for each disaster.

The $135 million being reallocated pales in comparison to the billions of dollars in unmet needs around the state. Better matching remaining dollars with remaining needs will help create a more resilient Texas. And simplifying the application process will help use up available money before federal deadlines expire.

Action-Plan Amendments, Deadlines, Major Changes

The GLO provided this summary of the deadlines for public comment on each amendment:

  • Hurricanes Ike and Dolly Amendment 7
    • Federally required public comment period of 7 days will end at 5:00 PM on September 11, 2024.
  • 2015 Floods and Storms Amendment 6
    • Federally required public comment period of 14 days will end at 5:00 PM on September 18, 2024.
  • 2016 Floods and Storms Amendment 8
    • Federally required public comment period of 14 days will end at 5:00 PM on September 18, 2024.
  • Hurricane Harvey $5.6 Billion Amendment 16
    • Federally required public comment period of 30 days will end at 5:00 PM on October 4, 2024.
    • Includes updates to the Harris County Homeowner Assistance, Residential Buyout, Affordable Rental and Single Family New Construction Programs.
    • Includes updates to the City of Houston Single Family Development and Buyout Programs.
  • 2018 South Texas Floods Amendment 2
    • Federally required public comment period of 30 days will end at 5:00 PM on October 4, 2024.
    • Includes updates to the Specific Conditions Report in Appendix H.
  • 2019 Disasters Amendment 3
    • Federally required public comment period of 30 days will end at 5:00 PM on October 4, 2024.
    • Includes updates to the Specific Conditions Report in Appendix G.
Cover of Amendment 16 to Harvey Action Plan

The six action-plan amendments are available for review at https://recovery.texas.gov/public-notices.

Submit all comments to cdr@recovery.texas.gov by 5:00 p.m. on their respective ending dates.  

$135 Million Reallocated

The Hurricane Ike action plan amendment creates the DRRP. It will utilize remaining program funds from current disaster recovery grants from 2008 to 2019, with the exception of the 2011 Wildfires grant.

DRRP will expedite the expenditure of funds to comply with HUD’s timely expenditure requirements through a call for projects across multiple grants.

Ike Action Plan Amendment, page 2.

Each project will undergo eligibility analysis based on the grant that used to fund it.

As funds continue to be identified through the de-obligation process, they will be added to the DRRP
program. All remaining funds will be reallocated to this program for each grant.

The amounts going into the DRRP “pot” total $135 million. That includes:

Together, they total $135,000,000. 

Consult Individual Plans for More Details

Based on the Dolly/Ike amendment, GLO will do a single call for projects statewide. Each agency that responds can submit up to two applications, and they will score them based on the published criteria.  

Those criteria total more than 800 pages. Criteria for each of the six amendments are hyperlinked with the amounts above.

While that’s a daunting number of pages to read, GLO provides tables that show where money is going from and to, plus rules that will govern grant awards.

The GLO will perform the eligibility analysis to make applications easier. “We want this to be as simple as possible for applicants, so they will only have to submit one application and have all of the difficult analysis of eligibility and funding streams on our end,” said Brittany Eck, a GLO spokesperson.

If nothing else, these amendments dramatize how complex the flood mitigation process is. Today is 2562 days since Hurricane Harvey. But Hurricane Ike struck Houston on September 11, 2008. That’s 5836 days ago!

How to Submit Public Comments

Submit all comments to cdr@recovery.texas.gov by 5:00 p.m. on their respective ending dates to be considered. GLO requests that you please include the name and number of the action-plan amendments that you’re commenting on in the subject line. 

Posted by Bob Rehak on 9/3/24

2562 Days since Hurricane Harvey

GLO Rebuilds Its 2000th Home in Houston, Harris County

Today, Texas Land Commissioner Dawn Buckingham, M.D., announced the Texas General Land Office (GLO) has rebuilt its 2000th home – in Houston and Harris County alone – since Hurricane Harvey. Many more projects are under construction or in the approval process here and in other counties throughout Texas..

Dawn Buckingham MD, GLO Commissioner congratulates the homeowners (center) as she turns over the key. Builder is on left.

GLO rebuilt the home through its Homeowner Assistance Programs (HAP) as part of ongoing recovery efforts. One of the GLO’s missions is to restore and rebuild communities across Texas after natural disasters. Just last year, GLO celebrated the rebuilding of 1000 homes in Houston/Harris County.

Rebuilding Lives, Not Just Homes

The GLO certainly isn’t resting on its laurels. Buckingham said, “This milestone represents more than just a number. It reflects the dedication and hard work of the GLO’s disaster recovery team and our commitment to helping Texas families rebuild their lives after the devastation of Hurricane Harvey and other disasters. 

Buckingham (Left) and Mike Nichols (Right), new director of Houston Housing and Community Development, tour new home with ecstatic owners, Argelis and James Sapio (Center).

Hurricane Harvey Homeowner Assistance Program

The GLO’s Homeowner Assistance Program is funded by $2 billion in Community Development Block Grants for Disaster Recovery (CDBG-DR) from the U.S. Department of Housing and Urban Development (HUD). The program helps homeowners repair, rebuild, and, in some cases, elevate their homes to mitigate future flood risks. 

Army Vet and Teacher

The homeowners, James and Argelis Sapio, have been married 47 years and lived in the same house for 27 of those. A U.S. Army veteran, James served in war zones around the world starting in Vietnam and ending in Eastern Europe. Argelis, taught at a neighborhood elementary school

They loved their home and the location. But it flooded repeatedly with increasing frequency. Over time, the flooding got worse as neighbors built their lots up. Reportedly illegal dumping also complicated flooding issues when it backed water up in ditches. The final straw was Hurricane Harvey. A foot of floodwater invaded the Sapio’s home.

They persisted through a daunting application for aid that the GLO, HUD and City are trying to streamline. Four months ago, construction of a new home started on their old lot. The elevated design should make them safe from flooding. It includes ramps to make access easier.

The 2000th home. Note elevation and ramp.

Said Argelis (with a smile), “Now the only thing we have to worry about is elevating our cars.”

Construction took four months. During that time, the couple lived in motels. They were so eager to move in, they weren’t going to wait for the movers. Argelis said they were going to bring a mattress in tonight and sleep on the floor if they had to.

Ongoing Commitment to Disaster Recovery

Altogether, the GLO has rebuilt more than 8,000 homes in 49 counties designated eligible by the U.S. Department of Housing and Urban Development (HUD). 

Commissioner Buckingham reaffirmed the agency’s ongoing dedication to disaster recovery and preparedness as the GLO celebrates this achievement. “The GLO remains steadfast in supporting Texans as they rebuild and recover,” said Buckingham. “Together, we will continue to work towards a more resilient Texas.”

For a one-minute YouTube video of the ceremony and tour of the house, click here.

Posted by Bob Rehak on 8/7/24

2535 Days since Hurricane Harvey

GLO Approves $66.4 Million in Regional Mitigation Projects

7/18/2024 –  Today, Texas Land Commissioner Dawn Buckingham, M.D., announced the Texas General Land Office (GLO) approved another $66,402,284 in regional mitigation projects.

The money will go toward projects that improve roads, water detention, drainage and sewer systems. The projects are within the cities of Baytown, Brenham, Centerville, Charlotte, Corpus Christi, Houston, Jasper, Plantersville, Seadrift and Waelder.

However, money will also go toward projects in Fort Bend, Grimes, Harris and Matagorda counties.

Projects Prioritized Locally

“Through the Regional Mitigation Program, the GLO enabled local prioritization. That will have a tremendous impact across multiple regions,” according to GLO spokesperson Brittany Eck.

“The GLO works with Texas communities to strengthen and build infrastructure, so we can help protect and improve lives for local residents,” said Commissioner Buckingham.

“Many of these communities were recently impacted by Hurricane Beryl’s devastating winds and flood waters,” continued Buckingham.

“Getting and using federal grant funds can be very complicated. But the GLO works side by side with local leaders to push past the federal paperwork and get funds moving forward.”

Making Communities More Resilient

Buckingham emphasized that the funds should make Texas communities “more resilient against future disasters.”

The table below shows the list of approved grants.

Fix 7.18 Table Update

For more detailed project descriptions, please click here.

The one project in Houston: a $10.8 million stormwater detention basin in Sunnyside, a small community near West U.

Money Prioritized by Councils of Governments

These funds come from $1,166,997,000 in Community Development Block Grant Mitigation (CDBG-MIT) funds from the U.S. Department of Housing and Urban Development. HUD designated the money local councils of governments (COGs) through the GLO.

The projects themselves do not have regional benefits. The term “regional mitigation projects” applies more to the type of organizations that sponsor the projects.

The Houston-Galveston Area Council (HGAC) is one such group. Each Council of Government with HUD-designated eligible counties developed a method of distribution (MOD) for allocation of funds to units of local governments. Each COG developed their MOD through extensive public participation.

HUD defines mitigation as activities that increase resilience to disasters and reduce or eliminate the long-term risk of loss of life, injury, damage to and loss of property, and suffering and hardship, by lessening the impact of future disasters.

HUD requires that at least 50% of total funds must be used for activities benefiting low-to moderate-income (LMI) persons. For more information, please visit recovery.texas.gov/mitigation.\

Posted by Bob Rehak on 7/18/2024 based on a press release from the GLO

2515 Days since Hurricane Harvey

Area Leaders Meet with GLO Commissioner Buckingham

Harris County and the Houston area are receiving $863 million from the U.S. Department of Housing and Urban Development (HUD) via the Texas General Land Office (GLO) for disaster relief and flood mitigation. So, on Thursday, April 25, 2024, GLO Commissioner Dr. Dawn Buckingham met with a group of Lake-Houston-Area leaders to discuss the area’s flood mitigation needs.

The meeting, arranged by State Representative Charles Cunningham, also included Director Tina Petersen of the Harris County Flood Control District (HCFCD); Director Thao Costis of Harris County Community Services (CSD); Humble Mayor Norman Funderburk; and Dustin Hodges, Chief of Staff for City of Houston Council Member Fred Flickinger.

(L to R) Dustin Hodges; Tina Petersen; Thao Costis; Dr. Dawn Buckingham; Rep. Charles Cunningham; Norman Funderburk; Alice Rekeweg;  Scott Elmer, HCFCD; and Kathleen Jordan.

Projects Vie for Funding

As reported on 4/23, Buckingham was in Houston to discuss Disaster Relief and Mitigation projects totaling $863 million. But there are more deserving projects than money to fund them all. So Buckingham, her team, HCFCD and CSD met with area leaders to discuss needs.

The GLO administers the distribution of HUD funds in Texas. Among Lake Houston Area projects discussed for funding were:

  • Taylor Gully Channel Improvements ($25.5 Million)
  • Woodridge Stormwater Detention Basin – Compartment 1 ($13.3 Million)
  • Woodridge Stormwater Detention Basin – Compartment 2 ($17.5 Million)
  • Mercer Park Drainage Improvements ($5.3 Million)
  • Mercer Detention Basin ($15.4 Million)
  • Mercer Botanic Garden Restroom Improvements (0.6 Million)
  • New Humble Fire Station ($4.5 Million)

No commitments were made at the meeting, but the mood was positive and everyone left smiling.

Buckingham is still collecting information. She listened attentively, asked probing questions and left with a better understanding of the area’s needs.

Splitting the Woodridge Basin into two phases helps ensure that at least one compartment will get funded and provide enough mitigation to let the Taylor Gully Channel Improvements move forward.

Other Topics

Several other topics came up toward the end of the hour-long meeting. They included sedimentation, dredging, and the need for sand to nourish beaches along the Texas coast. The GLO needs sand to replace eroding beaches…and this area needs to remove sand collecting in streams and Lake Houston.

That raised the tantalizing possibility of collaboration for mutual benefit and solving two problems at once.

More news to follow.

Posted by Bob Rehak on 4/26/24

2432 Days since Hurricane Harvey

GLO Reviewing HUD Applications for Harris County Projects Totaling Half Billion Dollars

The Texas General Land Office (GLO) is currently conducting a final review on more than $498 million in grant applications from Harris County Flood Control District (HCFCD) and Harris County Community Services Department (CSD). That’s out of a total allocation of $1,072,033,863 allocated to Harris County. And that means projects for almost half the Harvey money allocated to Harris County will soon go to Washington for a final review by HUD.

Additional applications for the rest of the money will soon follow the projects listed below. They will be submitted “on a rolling basis,” according to Brittany Eck, a GLO spokesperson.

The GLO administers all HUD funds in the state of Texas.

GLO Working Side by Side with Harris County

GLO has a “Strike Team” embedded at HCFCD headquarters, working side by side with both CSD and HCFCD to eliminate any delays on the HUD applications. The billion dollars allocated to the county falls into several different programs, each with different deadlines and complex rules.

“We are currently in the ‘Eligibility Phase,’ which is the most critical, but also the most time consuming. During this phase we must ensure that the projects proposed sync with HUD regulations in terms of LMI beneficiaries, environmental impacts and more,” said Eck. 

No Performance Benchmarks Missed So Far

“It is important to note that Harris County has not missed a performance benchmark yet on the HUD applications. The GLO is working with Harris County to ensure all administrative paperwork is completed in accordance with federal regulations. This protects both Harris County and the State of Texas from incurring costly ‘findings’ during the post-project audit process.”

A finding during a post-project audit could potentially cause HUD to claw back part of its grant money. So it’s vitally important to ensure all regulations are followed to the letter.

Three Main Batches of Money

The three main pots of money include:

  • Harris County CSD – $208,152,174 in CDBG-MIT funds
  • HCFCD – $322,033,863 in CDBG-DR funds
  • HCFCD – $541,847,826 in CDBG-MIT funds

That brings the total of original allocations to $1,072,033,863.

Since this involves the government, it also includes acronyms. So let me explain some of the terms.

CDBG stands for Community Development Block Grants. These grants provide communities with resources to address a wide range of development needs, providing projects meet one or more of HUD’s three defined national objectives. Namely, a CDBG project must:

  • Benefit to low- and moderate- income (LMI) persons
  • Aid in the prevention or elimination of slums or blight and/or
  • Meet an urgent need (UN), especially one impacting public health and safety.

But what about the rest of those acronyms?

  • DR stands for Disaster Relief
  • MIT stands for Mitigation.

What’s the difference? According to HUD, CDBG-DR grants provide housing, infrastructure, and economic revitalization assistance to impacted areas. The CDBG-Mitigation (CDBG-MIT) program provides additional funding to lessen the impact of future disasters.

To learn more about HUD applications for the specific Harris County projects, see below.


Harris County CDBG-MIT

Harris County Community Services Department was allocated $208,152,174 in CDBG-MIT funds for infrastructure, planning, and project delivery.

The contract was executed on 08/31/2022. All projects in this batch of funding must close out by 8/31/27.

The $208 million breaks down into three subcategories.

  • Infrastructure programs – $154 million
  • Planning programs – $37.5 million
  • Project delivery – $16.7 million
Infrastructure Programs

Of 11 projects initially proposed in this category, the three largest in terms of dollar amounts – totaling $75M of the $154M – have been submitted for preliminary review.

$37,500,000.00Pine Trails Subdivision Drainage Improvements
Involves upgrading approximately 63,650 LF of drainage systems and developing two (2) detention ponds in Harris County Precinct No. 2. 
66.97% LMI
$20,545,326.00Ralston Acres Subdivision Drainage Improvements
Involves upgrading approximately 15,250 LF of drainage systems and developing two (2) detention ponds in Harris County Precinct No. 1 and Ralston Acres Subdivision.  
Income Surveys TBD
$16,954,674.00 North Forest Subdivision Drainage Improvements
Involves upgrading approximately 19,700 LF of drainage systems and developing one (1) detention pond in Harris County Precinct No. 1 and the North Forest Subdivision.  
Income Surveys TBD
As of 3/19/24

Planning Programs 

Four projects – costing a total of $16.5M out of the $37.5 million – have been submitted for preliminary review out of the 23 proposed planning projects.

$500,000.00 Harris County Multi-Jurisdictional Hazard Mitigation Plan
The Harris County Office of Homeland Security & Emergency Management is seeking to update the Harris County Hazard Mitigation Plan. The plan will develop strategies and action items to minimize vulnerabilities and damages and include 37 participating jurisdictions.
$12,500,000.00Drainage Master Plan for Unincorporated Harris County
The planning project will evaluate drainage infrastructure capacity status and deficiencies in Harris County’s unincorporated areas. It will also guide the identification and implementation of mitigation alternatives to reduce flood risk.
$500,000.00Halls Bayou Watershed Flood Risk Analysis Study
The scope of the Halls Bayou watershed study is to analyze the best available data incorporating the Halls Bayou watershed flood risk reduction-related project and to evaluate existing program benefits using the new Atlas 14 precipitation data to identify additional potential flood reduction needs within the watershed.
$3,000,000.00The Evacuation Routes Study
The Evacuation Routes Study aims to enhance transportation resilience in road-flooding-prone areas of Unincorporated Harris County.
As of 3/19/24

Project Delivery: 

$16,652,174 of the $208,152,174 County allocation will be used to administer the funds for projects.


HCFCD Disaster Relief

HCFCD was allocated $322,033,863 in CDBG-DR funds for infrastructure projects.

HCFCD submitted 13 projects costing a total of $317,494,724.78 for CDBG-DR grants and is putting up local funds in the amount of $45,899,821 for those same projects. All of the applications have been officially submitted and are being reviewed for HUD eligibility completeness by the GLO.

The HCFCD/CDBG-DR contract was executed on 11/27/2023 and must be closed out by 3/31/2026. The 13 projects include:

$20,361,143.56Arbor Oaks Stormwater Detention Basin
To construct one 431-acre-feet stormwater detention basin within the White Oak Bayou watershed. 
60.55% LMI
$20,247,760.00Isom Stormwater Detention Basin
To construct one 550-acre-feet regional stormwater detention basin within Halls Bayou. 
74.23% LMI
$8,692,644.00Lauder Stormwater Detention Basin
To construct one 341.47-acre-feet stormwater detention basin within Greens Bayou. 
78.10% LMI
$20,361,143.56Brookglen Stormwater Detention Basin
To construct one 33.45 acre-feet stormwater detention basin within Armand Bayou Watershed. 
52.54% LMI
$25,390,047.00Kluge Stormwater Detention Basin – Phase 3
To construct one 350 acre-feet stormwater detention basin within Little Cypress Creek watershed. 
14.25% LMI but qualifies under Urgent Need
$77,899,107.00Greens Bayou Mid-Reach Channel Conveyance Improvements
To rehabilitate 19,008 LF of channel conveyance along Greens Bayou. 
78.61% LMI
$18,878,499.00Cypress Creek Channel Rehabilitation, Main Stem, Batch 5
To rehabilitate 7,500 LF of channel conveyance along Cypress Creek. 
49.18% LMI, but qualifies under Urgent Need
$36,710,019.00Dinner Creek Stormwater Detention Basin ‐ Phase 1
To construct two (2) detention basins, northwest and southeast of Dinner Creek. 
52.36% LMI
$7,642,742.00Barker Reservoir Channel Rehabilitation, Repair Package 2
To rehabilitate 18,528 LF of channel conveyance at 19 different sites along Barker Reservoir. 
21.64% LMI but qualifies under Urgent Need
$9,742,750.00Stormwater Detention Basin along Jackson Bayou
To rehabilitate 2,025 LF of channel conveyance and construct one (1) 15 acre-feet stormwater detention basin within Jackson Bayou. 
60.78% LMI
$23,496,000.00Addicks Reservoir Channel Rehabilitation & Restoration, Repair Package 3
To rehabilitate 49,296 LF of channel conveyance at 49 sites along the Addicks Reservoir. 
37.04% LMI but qualifies under Urgent Need
$23,844,000.00East TC Jester Detention Basin – Compartment 1B
To construct one 725 acre-feet stormwater detention basin within the Cypress Creek watershed. 
36.14% but qualifies under Urgent Need
$12,293,732.00Keegans Bayou Stormwater Detention Basin Near Old Richmond Road – Phase 1
To construct one stormwater detention basin within the Brays Bayou watershed. 
56.71% LMI
As of 3/19/24

HCFCD CDBG-MIT

Harris County Flood Control District was allocated $541,847,826.00 in CDBG-MIT funds for infrastructure hazard mitigation projects.

Five projects – totaling $73 million – have been submitted for preliminary HUD eligibility completeness review out of the 19 mitigation projects originally proposed.

Overall Contract Status: Contract executed 11/07/2023

Projected Closeout: March 31, 2028

$3,235,715.00Halls Bayou Channel Conveyance Improvements Downstream of Hopper (HALLS HOPPER)
Includes widening approximately 4,525 LF of the existing channel along the left (east) bank from downstream of Hopper Road to just upstream of Pinewood Village Park. 
70.03% LMI
$10,427,946.00Hahl North Stormwater Detention Basin (Hahl North)
Includes construction of one 220 acres-feet of stormwater detention basin adjacent to Halls Bayou and the widening of approximately 2,100 LF of the existing channel along Halls Bayou. 
73.65% LMI
$17,300,036.00West TC Jester Stormwater Detention Basin
Will create one 414 acre-feet stormwater detention basin in the Cypress Creek watershed. 
36.13% LMI but qualifies under Urgent Need
$11,987,888.00Taylor Gully Channel Conveyance Improvements
Includes approximately 13,118 LF of stormwater drainage channel improvements in the affected stretch of channel.
20.92% LMI but qualifies under Urgent Need
$30,007,445.00Boudreaux Stormwater Detention Basin – Phase 1
Will build one 458 acre-feet stormwater detention basin west of Holderrieth Road along Willow Creek. 
33.59% LMI but qualifies under Urgent Need
Altogether, the HUD applications must benefit at least 50% LMI individuals according to HUD regulations governing these funds.
Taylor Gully Looking S from county line
Taylor Gully looking S from the Montgomery County Line. Up to 600 homes flooded twice here in 2019, after Perry Homes clearcut 270 acres without installing the required detention basin capacity. One of the HUD applications seeks to improve the channel.

Even though some projects drop below the 50% threshold, as a group they meet the requirement. Those that fall below the threshold also qualify under HUD’s Urgent Need mandate.

Extensions Requested, But Not Yet Confirmed

GLO has requested extensions for all these projects. While HUD reportedly seems favorable, written confirmation has not yet been received. That places a premium on HUD applications that can be executed quickly.

Posted by Bob Rehak on 3/19/24 based on information provided by the Texas GLO

2394 Days since Hurricane Harvey

GLO Announces Bolivar Beach Restoration Project to Protect Highway

On 12/13/23, Texas General Land Office (GLO) Commissioner Dawn Buckingham, M.D. announced the approval of Coastal Erosion Planning & Response Act (CEPRA) funding for a Bolivar Peninsula Beach and Dune Restoration project.

The beach-restoration project seeks to:

  • Restore additional essential beach and dune systems
  • Provide crucial protection for Highway 87, Bolivar Peninsula’s only hurricane evacuation route

According to the GLO, the CEPRA funds – initially aimed at an engineering study – will provide both economic and coastal resilience benefits.

Part of SH 87 Already Washed Away

Highway 87 once had a stretch between Sea Rim State Park and High Island that washed out repeatedly over the decades. TXDoT closed it permanently in 1990. Today, eastbound SH 87 stops at High Island. Evacuees must then turn north on SH 124 toward I-10.

The stretch being protected provides the only remaining land-based evacuation route for the 2,800 residents of the Bolivar Peninsula. Seventeen people died there on September 13, 2008, during Hurricane Ike.

The scope of this project: to develop focused beach nourishment engineering design specifications for a U.S. Army Corps permit. Beach nourishment will alleviate tidal impacts threatening SH 87’s eastern terminus on Bolivar Peninsula near High Island.

Satellite Image Sequence Shows Severity of Shoreline Erosion

This series of Google Earth images shows how shoreline erosion now has waves lapping at the shoulder of the highway in this area.

State Highway 87 near High Island in 1974. Note dunes between highway and broad beach.
Same area immediately after Ike. Note erosion of beach and deposition inland from SH87.
Same area in 2023. Note continued erosion of beach toward highway.
Enlargement of nearby stretch shows high tide lapping at riprap which maintenance crews are replenishing (2023).

The beach nourishment engineering design specifications under this project are focused on an approximately four miles of the Bolivar Gulf-facing shoreline beginning at the Galveston-Chambers County line and extending west toward Gilchrist. This is where tides come closest to Hwy. 87 on a recurring basis.

Improving Resilience

“Ultimate benefits from this beach nourishment design work would include protection of the peninsula’s only hurricane evacuation route,” said a GLO spokesperson.

The CEPRA Program helps communities across the Texas coast implement erosion response projects and related studies to understand and reduce coastal erosion as it threatens public beaches, natural resources, coastal development, public infrastructure, and public and private property. 

The Bolivar Peninsula Special Utility District, Bolivar Peninsula Chamber of Commerce, Galveston County Road Administrator Lee Crowder, Galveston County Judge Mark Henry, and Galveston County Precinct 2 Commissioner Joe Giusti played pivotal roles in securing this funding.

Nature-Based Solutions Help Protect People and Wildlife

Commissioner Buckingham said, “As a Texan who grew up near the coast and lived on Galveston Island for more than a decade, preserving our state’s precious shorelines and their communities is a top priority.”

FEMA has found that such nature-based solutions increase quality of life for both humans and wildlife. And make no mistake. This is an important wintering and nesting area for many species of wildfowl that depend on the wetlands in this area.

Snow geese flocking near High Island in December 2008, shortly after Ike.

Posted by Bob Rehak on 1/1/24

2316 Days since Hurricane Harvey

HCFCD Grappling with Inflation’s Impact on Flood-Bond Purchasing Power

Inflation has reduced the 2018 Flood Bond’s purchasing power. The general rate of inflation during the last five years adds up to 20%. That could potentially eliminate one fifth of the projects in the flood bond.

It’s a serious concern for the people whose mitigation projects have been put at the end of the line by the County’s Equity Prioritization Framework. Some residents may never see any benefit from their tax dollars, which are going to other areas.

Here’s how Harris County Flood Control District (HCFCD) will look at projects that now have an uncertain future.

Local Costs Consistent with General Rate of Inflation

In a presentation to the Harris County Community Flood Resilience Task Force, Jesal Shah PE, the new Chief Project Delivery Officer for HCFCD, discussed the issue of inflation. Shah, a Houston native, has been in his job since May, 2023. He previously led flood-risk reduction planning, design, engineering, and construction efforts for the government of British Columbia.

Shah cited 15-20% increases in construction, material, and right-of-way acquisition costs for Harris County flood-mitigation projects.

This and other screen captures below are from Shah’s presentation to Flood Task Force on 12/14/23.

Summary of 2018 Flood-Bond Funding To Date

The 2018 flood bond contained $2.5 billion in funding for approximately $5 billion worth of projects. Partnership funding, i.e., grants, were supposed to make up the difference.

And at this point, all of the partnership funding has been secured thanks to an infusion of $825 million in Community Development Block Grant funding from the U.S. Department of Housing and Urban Development (HUD) and the Texas General Land Office (GLO).

“Anticipated” should now be removed from this slide.

That’s very good news.

63% of Bonds Sold Already

Shah says that the County has sold $1.575 billion worth of bonds to date, almost two thirds of the original $2.5 billion.

Of the two thirds, about half the money has been spent or “encumbered.” Encumbered means the money is committed to projects and difficult to move. For instance, a project may be in construction, but not yet completed.

The other half has been committed to projects, but not yet encumbered. For instance, bonds may have been sold, but the construction job may not have been awarded yet.

See below.

Securing the partner funding is huge good news. But the impact of inflation is worrisome. To help deal with that, the County is re-evaluating all projects associated with the flood bond.

How Projects are Being Re-evaluated

Shah cited three types of projects listed in the original bond. Those with:

  • Well defined scope and accurate estimates.
  • Clear scope but inaccurate estimates. For instance, the Lauder basin has almost tripled its original cost estimate.
  • Vague scope and unreliable estimates.

See examples below.

To complicate matters, some backstop funding from the Flood Resilience Trust is no longer available because of new “guidance” from Commissioners Court. That will eliminate $343 million in funding flexibility.

And keep this in mind. The bond program is far from complete. We could easily see another 15-20% of inflation before its over. So what to do?

Sharpening the Pencil

Shah’s team is dividing the remaining bond projects into two piles.

  • Those with clear scope and funding will be completed.
  • Those without clear scope or funding will be re-evaluated.

Shah hopes to present an updated project list to Commissioners Court sometime during the second quarter of 2024.

Shah has already taken a first pass at re-evaluating the bond’s project list. Of the 181 projects identified in the bond:

  • 30 have already been completed or eliminated.
  • 63 will continue moving forward.
  • 88 (almost half) will need more funding or more clarity (i.e., more engineering studies/tighter estimates) to move forward.

The slide below shows the guiding principles for evaluating the 88 projects that need more funding or clarity.

Lack of Balance Could Jeopardize Future Bond Offerings

One possible way to mitigate the toll of inflation involves phasing projects in areas that have already received large amounts of funding so that projects in areas that received little funding could move forward.

For instance, in a project that involves multiple stormwater detention basins, one or more of the basins could be delayed until the next bond. Meanwhile, delaying that basin could free up money for a basin in a different watershed.

However, during Q&A, Shah said he has no plans to phase projects.

A lack of equitable distribution could jeopardize future bond offerings.

And many areas have received little funding from this bond.

More than a 100 to 1 difference exists between projects on the left and right.

In the future, voters who saw no benefit from the 2018 flood bond might, once again, feel victimized by bait-and-switch tactics.

Selling future bonds will require restoring faith in the fairness of government. And that will require spreading bond funds around so that everyone – in all parts of the county – sees some benefit from them. That’s my humble opinion.

When HCFCD presents its updated project list to Commissioners Court in the second quarter of 2024, it will be interesting to see whether Commissioners and the County Judge agree with it.

John Whitmire’s landslide election in the Houston Mayor’s race may send a message to them. Whitmire is a Democrat who campaigned across the aisle and received heavy Republican support.

Posted by Bob Rehak on 12/16/2023

2300 Days since Hurricane Harvey

Woodridge Village Excavation and Removal Contract Ends

(Note: Within an hour of posting this, I received additional information from a source familiar with Federal grants and have updated the section on Funding below.) Harris County Flood Control District (HCFCD) and Sprint Sand & Clay have ended their Woodridge Village excavation and removal (E&R) contract. As of Friday afternoon, 11/24/23, Sprint had removed all of its equipment from the worksite, including the construction trailer at the entrance. See photos below.

Empty entrance on Woodland Hills where construction trailer once stood.
Looking NE at extent of excavation for new detention basin.
Same basin, but looking in opposite direction toward SW.

This will pause construction of additional stormwater detention capacity on Woodridge Village property.

Why did the contract end?

Funding Played Role in E&R Contract Termination

The new stormwater detention basin on HCFCD’s Woodridge Village property was part of a much larger project involving improvements to Taylor Gully. The combined Taylor Gully/Woodridge Village project involved funding from multiple sources:

  • U.S. Representative Dan Crenshaw secured federal funding for Taylor Gully improvements in March 2022.
  • The Texas Water Development Board approved additional state funding in May.
  • Last summer, HCFCD also recommended the Taylor Gully/Woodridge project(s) for GLO/U.S. Department of Housing and Urban Development (HUD) CDBG-MIT funding.

The last comes with a firm, tight deadline for spending the money – Jan. 12, 2027 – three years away. It also comes with other “process” restrictions dictated by the CDBG-MIT funding.

Harris County requested a deadline extension. But because of the holiday, it is not clear whether HUD granted it.

Also, since originally posting this, an expert in Federal grants wrote to say, “The excavation and removal at Woodridge had to stop because Federal funds require a process to be followed. The excavation project that will be funded by CDBG mitigation funds has to follow NEPA (the National Environmental Policy Act). It does not allow any activity until NEPA has been cleared. Once the site was officially approved for CDBG mitigation funds, everything had to stop. The agreement with GLO was executed a week or two ago.”

“A similar thing happened to the Sprint excavation and removal at the Dinner Creek Basin,” he added. “It’s one of those sad facts about federal grants. You have to follow their process and everything is done in a linear fashion.”

Flexible E&R Contracts Allow Early Termination

HCFCD’s excavation and removal contracts are very flexible. They let HCFCD get a head start on construction as it worked out financing, design and other project details.

The terms of Sprint’s E&R contract let Sprint excavate up to 500,000 cubic yards of material and sell the dirt on the private market to make a profit. Sprint was meeting its 5,000 cubic-yard/month minimum. They averaged 6,000 to 7,000 cubic yards per month during the last two years.

By the end of October, the company excavated 156,478 cubic yards – about a third of the maximum. However, the additional two-thirds at the current rate would have missed the HUD deadline by at least two years.

If there’s good news here, it’s that:

  • The amount excavated to date already puts the site very close to meeting Atlas-14 requirements. The “head start” worked.
  • Once construction resumes, it could sharply accelerate.

Final HCFCD Recommendations Not Yet Revealed

In December 2022, engineers presented their preliminary plans to the Kingwood community and sought public input on four alternatives. Their recommended alternative included:

  • Expanding a portion of Taylor Gully and lining it with concrete.
  • Building yet another 412 acre-foot stormwater detention basin on Woodridge Village.
  • Replacing the culverts at Rustling Elms with a clear-span bridge.

HCFCD has not yet revealed final construction plans to the community. But it appears that the pot is starting to boil. Stay tuned. More news will follow soon.

Posted by Bob Rehak on 11/26/23

2280 Days since Hurricane Harvey