Northpark Drive Expansion Update: Life in the Slow Lane
2/9/25 – Northpark Drive expansion has become a bewildering maze of lane switches and traffic barriers where SUVs tango daily with excavators and dump trucks. All of that makes for life in the slow lane … which can actually be a good thing given the potential for accidents.
Since my last construction update, contractors have removed the old:
- Eastbound pavement between Kings Mill and Russell Palmer Road
- Loop 494 Northbound pavement on both sides of Northpark
They have also substantially completed the installation of storm sewers underneath the westbound surface turn lanes that will parallel the bridge over the UnionPacific Railroad Tracks and Loop 494. However, crews still need to install many laterals.
Pictures Taken 2/9/25
I took all pictures below on 2/9/25. They show the status of construction. If traffic looks light in these photos, it’s likely because I took them during the pregame show for the Super Bowl.

Before contractors pour new concrete, they will have to install drainage, compact the dirt, prepare the base, and place rebar. All of that could take another month or more.
As soon as they finish the drainage on eastbound Northpark between Italiano’s and Russell Palmer the same crew will rotate to the northeast side of the Loop 494/Northpark intersection then the southeast side. Again, once the drainage is complete, they will begin to prepare the sub-grade, then rebar, then concrete paving.




The southbound lanes of Loop 494 south of Northpark are complete! So are the driveways!



The lookahead schedule posted on the Lake Houston Redevelopment Authority website shows major efforts for the next three weeks include installation of:
- Fire lines, water lines, water meters
- Box culverts and laterals
- Sub grade and fine grade prep
In other words, no big concrete pours for a while.
For More Information
See the Lake Houston Redevelopment Authority project web pages. For a history of the project, see these select posts on ReduceFlooding.
- 25.01.23 More of Old Northpark Drive Disappears
- 25.01.07 Northpark Construction: From Mistletoe to Milestones
- 24.12.18 Northpark-Loop-494 Lane Switches Happen Tonight
- 24.12.14 Major Changes Coming Soon at Both Ends of Northpark
- 24/11/15 Focus of Northpark Expansion Work Moving Toward Loop 494
- 24/10/26 Say Goodbye to the Old Northpark Drive
- 24/10/23 Northpark Crossover at Russell Palmer Closed through Sunday Night
- 24/10/11 Northpark Expansion Shifting into Higher Gear
- 24/09/16 Pictures of First Concrete Pour
- 24/08/18 Northpark Drive Construction Sequence Changing
- 24/08/08 Northpark Drive Expansion Project Overcoming Hurdles
- 24/04/19 Entergy Makes Some Progress on Northpark but Significant Issues Remain
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/05 Details of Phase II Meeting
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/12 Transplanting first tree
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
Posted by Bob Rehak on 1/30/25
2711 Days since Hurricane Harvey