Contractors Clearing South Side of Northpark Entry at US59

October 2, 2023 – Contractors finished clearing the north side of Kingwood’s Northpark entry last week. Now they have shifted their focus to the south side to make room for two stormwater retention basins that will double as decorative lakes.

TxDoT requires the basins to catch extra runoff caused by widening of the road.

Photos Show Progress of Northpark Entry Construction

The focus of the project’s landscape architects now is saving as many trees as possible. I took the photos below with one exception on 9/30/23.

Looking west. Trees remaining on the south (left) side of Northpark have been marked for transplantation. Excavation of pond on north (right) side should begin in mid-October.

In the photo below, note the rings around the remaining trees on the south side.

Those rings help retain water and nutrients being given to the trees to enhance their chances of surviving transplantation.
Looking E. Note how row of trees on the left screen the entry from the busy shopping center behind them. Also notice how the right side does not have a similar row of trees.

Landscape architects will relocate most of the remaining trees on the right/south side of Northpark to create a backdrop for the new pond. Some trees will remain in front of the pond. See the latest plan below.

Northpark entry plan

Handling Overflow from Ponds during Heavy Rains

To avoid flooding the Northpark entry area, contractors will channel overflow from the ponds west to Bens Branch and the Kingwood Diversion Ditch.

Looking east. Note clearing on the left/north side of Northpark to lay the new stormwater line that will carry overflow from the ponds to the east.
Looking west toward 59. The stormwater line will go behind Public Storage (upper left) and carry water toward the Kingwood Diversion Ditch and Bens Branch.
Northpark Drive expansion;
Route for excess water. Circle shows location of photo above this one.

Status from Diversion Ditch to 494

Looking east from Russell-Palmer to Kingwood Diversion Ditch. Virtually all of the ditch has been replaced by box culvert.
A coffer dam remains around an out-of-place water line that needs to be lowered.

Re-engineering of the water line has begun in concert with the City of Houston.

Farther east where culverts have already been placed, you can start to see how Northpark will be widened inward toward the center to create two extra lanes of traffic.
Looking west from Russell-Palmer, contractors are still waiting for Centerpoint to move a gas line out of the median to the side of the road.

Until Centerpoint moves that gas line, contractors will focus on other parts of the project, such as the entry.

Saving Money While Saving Trees

At their monthly meeting last Thursday, Lake Houston Redevelopment Authority/TIRZ board members discussed the escalating cost of relocating trees. Costs increased as trees grew between the original estimate and today.

After the meeting, Ralph De Leon, the project manager, met with contractors, the landscape architect and project designer. They developed a new plan to help hold down costs.

Previously, some trees were to be moved twice, first to a temporary holding location on the north side of Northpark and then back to their final spot on the south side. Why? Contractors needed to build up land behind the pond on the south side of Northpark before transplanting the trees.

The new plan calls for building up the land before moving ANY trees. That will eliminate the cost of the double move. It will also reduce traffic disruption. Tree moving equipment will no longer have to cross Northpark.

Main Goals of Northpark Project

Overall, the main goals of the Northpark project include:

  • Widening the road to reduce delays caused by increased traffic
  • Building a bridge over the UP railroad tracks to eliminate traffic blockages
  • Creating a reliable, all-weather evacuation route for Kingwood

For More Information

For previous posts about Northpark construction, see the following:

Also visit the Lake Houston Redevelopment Authority/TIRZ 10 Project pages at https://lakehoustonra.com.

Posted by Bob Rehak on 10/2/23