Northpark, Loop 494 Lane Switches Happen Tonight
12/19/24 – Northpark and Loop 494 lane switches happen tonight to accommodate new construction. Two large lane switches will begin at 9PM.
One will be on the eastbound lanes between Kings Mill and the eastern end of the project at the Kingwood Diversion Ditch. The second will be on Loop 494 about a block north and south of the Northpark intersection.
In both areas, Harper Brothers Construction will switch traffic to new or temporary lanes to accommodate demolition of the old lanes, installation of drainage, and reconstruction of new lanes.
The project has two overall goals: accommodate increased traffic and create an all-weather evacuation route for 78,000 Kingwood residents when floods cut off other exits.
Eastbound NorthPark Drive Traffic Switch
Lake Houston Redevelopment Authority’s (LHRA’s) contractor, Harper Brothers Construction will shift east bound NorthPark Drive traffic from the existing eastbound lanes to the newly constructed center lanes. The shift of eastbound traffic to the center lanes will occur between Kings Mill Park Drive and the Kingwood diversion ditch, approximately 0.3 miles east of Russell Palmer Road.
No new changes to the westbound traffic will occur during this phase. The contractor will be installing new storm sewer pipes and inlets along the south side of NorthPark Drive along with new concrete roadway.
This shift is planned to last approximately 6 months.
For a printable map of the lane changes, see this PDF.
The pictures below may help you visualize the changes coming tonight.
Loop 494 Traffic Switch:
Harper Brothers will also shift traffic from the east side of Loop 494 to the newly constructed concrete pavement on the west side. This shift of traffic to the newly constructed concrete lanes will occur between Northpines Drive and the east entrance to Kroger, approximately 0.2 Miles north of Northpark Drive.
This shift will last approximately four months while the contractor installs new storm sewer pipes and inlets along the east side of Loop 494, and new concrete roadway.
Here’s a second high-resolution, printable map of the lane changes on 494. See this PDF.
This photo may help you visualize the changes.
One thing to note re: Loop 494. Southbound traffic turning west onto Northpark will have a dedicated right-hand turn lane separate from the southbound lanes. That was not there before.
I would definitely avoid these areas tonight as contractors erect new traffic barriers. And use extra caution in coming days as drivers get used to the changes.
For More Information
The Lake Houston Redevelopment Authority offers a 3-week look-ahead schedule here.
For a history of the project, see these select ReduceFlooding posts.
- 24.12.14 Major Changes Coming Soon at Both Ends of Northpark
- 24/11/15 Focus of Northpark Expansion Work Moving Toward Loop 494
- 24/10/26 Say Goodbye to the Old Northpark Drive
- 24/10/23 Northpark Crossover at Russell Palmer Closed through Sunday Night
- 24/10/11 Northpark Expansion Shifting into Higher Gear
- 24/09/16 Pictures of First Concrete Pour
- 24/08/18 Northpark Drive Construction Sequence Changing
- 24/08/08 Northpark Drive Expansion Project Overcoming Hurdles
- 24/04/19 Entergy Makes Some Progress on Northpark but Significant Issues Remain
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/05 Details of Phase II Meeting
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/12 Transplanting first tree
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
Posted by Bob Rehak on 12/19/24 at 2PM
2669 Days since Hurricane Harvey