Northpark Expansion Still Making Progress Despite Holidays
12/10/24 – Halfway between Christmas and New Year’s, Harper Brothers Construction is still making progress on Northpark Expansion. The pace appears to have slowed somewhat. But that’s because of the current focus on subsurface drainage. Installing reinforced concrete box culverts takes significantly longer than work above ground.
It appears that all of the old westbound road bed between Caliber Collision and the railroad tracks has been removed except for driveways.
Meanwhile, farther east, I spotted more concrete being poured in the middle in preparation for additional demolition of westbound lanes.
Pictures Taken 12/10/24
The area above is where surface turn lanes will diverge from westbound traffic headed over an as-yet-unbuilt bridge over the railroad tracks.
Up Next
In other news, according to the Lake Houston Redevelopment Authority website:
- Waterline crews will continue transferring water services from the Porter SUD to the City of Houston waterline.
- Dirt crews will backfill new paving on Loop 494 and excavate for the asphalt transition on each end to tie into the new concrete paving
- Next week, project managers have scheduled a traffic switch on LP 494. They will move all traffic onto the new concrete paving, and close off the existing LP 494.
- Another traffic switch during the week of 12/16 will occur just east of Kings Mill to the east end of the project. Traffic will detour into the middle closing off the existing eastbound lanes.
To see what happens when, consult the Lake Houston Redevelopment Authority project pages or the schedule below.
For More Information
To learn more about the project history, consult these ReduceFlooding.com posts:
- 24/11/15 Focus of Northpark Expansion Work Moving Toward Loop 494
- 24/10/26 Say Goodbye to the Old Northpark Drive
- 24/10/23 Northpark Crossover at Russell Palmer Closed through Sunday Night
- 24/10/11 Northpark Expansion Shifting into Higher Gear
- 24/10/04 More Northpark Concrete Poured Today; Expansion Update
- 24/10/02 Lane Closure for Upcoming Concrete Pour
- 24/09/16 Pictures of First Concrete Pour
- 24/09/13 Northpark Crews Begin Pouring Concrete Monday, Road Narrowed
- 24/08/18 Northpark Drive Construction Sequence Changing
- 24/08/08 Northpark Drive Expansion Project Overcoming Hurdles
- 24/06/21 Northpark Expansion Obstacles Finally Being Addressed
- 24/04/21 Northpark Floods at Russell-Palmer Road
- 24/04/19 Entergy Makes Some Progress on Northpark but Significant Issues Remain
- 24/04/07 Northpark Entergy Saga: New Power Poles Slowly Going Up
- 24/04/02 New Entergy Power Poles Finally Arrive on Northpark
- 24/03/29 Northpark Expansion Update; Still No Sign of Entergy
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/08 TXDoT, LHRA Engage Kingwood at Northpark Phase II Meeting
- 24/03/05 Details of Phase II Meeting
- 24/02/27 February ’24 Northpark Expansion Update Including Lane Closures
- 24.02/24 Save the Dates: Public Input Meetings for Diversion Ditch, Northpark Expansion Phase II
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/10 Entergy in City’s Crosshairs, Lane Closures Announced
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/12/03 Northpark Expansion Presses Forward While Fighting Entergy Obstacle
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/26 Project moving forward on multiple fronts
- 23/10/12 Transplanting first tree
- 23/10/02 Clearing of south-side entry for second pond
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
The next meeting of the Lake Houston Redevelopment Authority Board will be Thursday morning at 8am at the Kingwood Community Center.
Posted by Bob Rehak on 12/10/24
2660 Days since Hurricane Harvey