Northpark Drive Expansion Begins in Earnest
Note: This story was updated on 7/26/23 to include more information about phasing of the Northpark Drive expansion project.
After what turned out to be a ceremonial groundbreaking on 4/13/23, the Northpark Drive expansion project appears to have started in earnest on 7/25/2023. Northpark is a vital evacuation route for tens of thousands of Kingwood and Porter residents during floods.
Cones and Culvert Line Northpark Center Ditch
Traffic cones line the center ditch between Russell-Palmer and the Kingwood Diversion Ditch.

Contractors have also stacked what looks like six-foot reinforced-concrete pipe on the edge of the Northpark Drive ditch where it enters the Kingwood Diversion Ditch.

They have also begun excavating the Northpark center ditch.

Project Partners
Project partners include:
- Lake Houston Redevelopment Authority
- City of Houston District E
- Montgomery County Precinct 4
- Texas Dept. of Transportation
- Harris County Flood Control
Plan Vs. Execution
In general, the project partners plan to widen Northpark by a lane in each direction (toward the middle). But instead of taking land and parking from merchants, the project partners plan to replace the center ditch with culvert then pave over it.
Early plans indicated that the area between US59 and Russell-Palmer would be Phase One and that Russell-Palmer to the Diversion Ditch and eventually beyond Woodland Hills would follow.
However, Ralph Deleon, a TIRZ engineer/project manager indicated that contractors are taking pieces of the phases out of order. Why? Contractors are ready to go. But not all the right-of-way and utility issues have been resolved.
So they’re approaching drainage first and starting at the downstream end – a best practice. In coming days, we should see additional activity on other portions of Northpark Drive. But Deleon emphasized that the public should have two lanes of traffic in both directions at all times.
The Lake Houston Redevelopment Authority (TIRZ 10) website contains a number of videos and construction docs that detail the ultimate vision for the project as well as next steps.
Will Culvert Convey as Much as Ditch?
The first thing that popped into my mind when I looked at the size of the culvert and the size of the ditch was that the culvert could not possibly convey all the water that the ditch used to.

Then I read this letter from Harris County Flood Control to the engineering company. It states, “The proposed improvement includes enlarging the proposed storm sewer system to provide inline detention and modeling the restrictors needed to meet allowable outflow requirements for both outfalls.”
The pipes shown above would definitely act as restrictors. I sure hope they don’t back water up into the street.
Having worked near Northpark for 22 years, I’ve seen the ditch overflow on multiple occasions. I’ve seen cars plunge to the bottom, emergency rescues, and stalled vehicles.
Here is the engineering company’s drainage impact analysis. And this presentation provides a project overview for the pre–bid conference for the western portion of the project. It shows a 32-month construction schedule for the western portion alone – even with a six day work week.
More Info to Follow
The TIRZ docs for the eastern portion of the project (Russell-Palmer to Diversion Ditch, Woodland Hills and beyond) are less comprehensive.
I’m meeting with the engineers and contractors tomorrow to learn more. Check back for more news and analysis.
Posted by Bob Rehak on 7/25/2023 and updated on 7/26/23