Paving of Northpark Drive to begin Monday

Northpark Crews Begin Pouring Concrete Monday, Road Narrowed

Northpark Drive construction crews have finished placing rebar in a 1000 foot long stretch on both sides of the entrance to Kings Mill. They will begin pouring concrete there on Monday, 9/16/24 at 3 AM. Concrete trucks will enter and leave the construction zone approximately every six minutes.

Because workers will spread the concrete next to the inbound lanes, traffic will be reduced to one lane until approximately 1 PM. However, both inbound lanes should open for the evening rush hour.

Rebar and forms ready for pour at 3AM Monday. Traffic on right will narrow to one lane to protect workers spreading the concrete.
Looking west from Kings Mill Entrance at rebar ready for concrete.

At this time, the construction team has scheduled additional concrete pours for 9/20, 9/27, and 10/1; times and dates subject to change.

Project managers evaluated all-night and all-weekend scenarios for pouring the concrete, but encountered legal restrictions having to do with worker safety and/or cost.

Back-and-Forth Paving Plan

The general plan is for crews to pour one side of one stretch of the road while prepping the other. After they finish the new middle lanes, the old outer lanes will be demolished one side at a time. They will reroute traffic to the middle lanes will reconstructing the old lanes.

At this point, neither inbound nor outbound traffic will be shut down completely, though it will narrow to one lane on the side where concrete is being poured.

Looking east at entire stretch of rebar on right. The next pour will be on other side of road.

More Visible Progress

Ralph De Leon, the project manager, emphasized that most of the wrinkles that the project experienced in the last year have been ironed out at this point. However, one small snag remains re: a switch of fire hydrants and buildings with commercial sprinkler systems on the north side of Northpark.

Several companies and a church are migrating to the City of Houston water system, and it’s apparently taking longer than expected for the City’s billing and meter installation department to catch up with the new infrastructure installation. Worst case: some businesses may get free water for a month or so.

De Leon asked for patience. “People don’t see all the work that’s going on underground, but that’s the real heavy part of the lift,” he said. “People will begin to see a lot more progress on Monday. The above-ground ‘flat work’ that everyone sees goes much faster.”

Major Steps After This

The area between the Diversion Ditch and Russell Palmer Road will be paved as part of Phase II, which includes everything up to and a little bit past Woodland Hills Drive.

Paving crews will next complete the new lanes between Russell Palmer and 494.

Looking NE across 494 and Northpark (right). First junction box has just been buried in lower left. Drainage team must next bore under 494 and railroad tracks.

Next, paving crews will turn their attention to 494.

Loop 494 will get the same alternate side of the road treatment in sections until finished.

Finally, crews will begin work west to US59.

NW corner of Northpark and Loop 494, looking west toward 59

The entry ponds will likely be among the last things completed.

In my last post, I alluded to a total shutdown of Northpark while UnionPacific installed new beds and track across the road. Originally scheduled for sometime in October or November, that will now happen in January or February.

It’s too early to tell when bridge construction over 494 will commence.

For More Information

For schematic diagrams of the paving plan, click here.

As paving moves east to west, crossovers will need to close temporarily. To see the schedule, click here.

For a three-week look-ahead schedule, visit the Lake Houston Redevelopment Authority website.

Also, see these posts on ReduceFlooding for a history of the project:

Posted by Bob Rehak on 9/13/24

2572 Days since Hurricane Harvey