UPRR Almost Finished, Northpark to Reopen This Afternoon
3/7/25 Updated at 2:30 PM– The UnionPacific Railroad (UPRR) has almost finished with Northpark work that caused a three day closure of one of two major traffic arteries out of Kingwood. UPRR hopes to reopen Northpark this afternoon. They say it should be open for evening rush hour.
Reasons for Closure
UPRR installed a single 55,000 pound, 200-foot-long, welded section of track across the area where ten lanes of traffic will soon go. The single section was necessary to stabilize the track against traffic that will drive over it and utilities that will bore under it.
The bridge that will carry six lanes of traffic over the tracks and Loop 494 eliminating backups in the case of evacuation. But the bridge also will create a conflict for utilities that run wires overhead in that area.
The pictures below tell the story of what happened since my last update yesterday at noon.
By 4 PM Thursday
By 4 PM Thursday, Day 2 of the 3-day closure, UPRR crews were preparing the areas next to the tracks where asphalt will go.



That means Loop 494 expansion through that area can now re-commence.
At 10 AM Friday
This morning, Friday 3/7/25, the Northpark railroad crossing was a beehive of activity. Crews poured asphalt over the gravel next to the track so that traffic could move smoothly over them.



While I was there, they did not actually place any of the concrete panels. However, asphalt kept arriving.


Reports of Train Moving Through Intersection Yesterday
Numerous people reported a train moving through the Northpark intersection yesterday. Those reports were true. But according to the railroad, the train was moving “really, really slow.”
UPRR has not yet fully stabilized the new section of track per their standards, but they are working on that now.
Reopening and Next Steps
UPRR will reopen the roadway late this afternoon, probably about 5 PM. Variables affecting that goal include the asphalt transition between the newly installed concrete panels and the adjacent roadway.
That asphalt arrived late this morning. And once placed, it must cool. But the roadway should open by rush hour this afternoon, according to UPRR.
The concrete panels needed for the future feeder road crossings and the two 10’ multi-use pathways still need to be installed. UPRR is still working on that.


UPRR also intends to place concrete panels between the tracks north (left) of the intersection above. Note the panels stacked by the white pickup in the lower left of the photo above. It is unclear whether they intend to try to do that before the re-opening.
No new signal work will be done at this time. The existing gate arms and signals will continue to operate when the roadway opens later today.
Other Northpark Work
Separately, the Lake Houston Redevelopment Authority used the opportunity created by the railroad work to run drainage underneath Northpark in two areas. The Harper Brothers crews are also nearly finished with those, too. So that work should not impede the re-opening of Northpark.


Posted by Bob Rehak on 3/7/25
2747 Days since Hurricane Harvey