Northpark Making Good Progress Despite a Few Hiccups
4/25/26 – Since I last posted about the Northpark Drive Expansion Project in Kingwood eleven days ago, contractors have continued to push forward parts of the project that they have control over. Those include the eastern bridge abutment and excavation of the detention basins at the US59 entrance.
They have also virtually completed everything east of the abutment all the way to the eastern terminus of the project near the Kingwood Diversion Ditch. Here’s an update on what is and isn’t complete in Phase I.
Eastern Part of Project Virtually Done
The entire project from US59 to the eastern terminus is about a mile. Eight-tenths of that mile is virtually complete – everything between Parkwood Baptist Church between Russell Palmer Road and the Kingwood Diversion Ditch down to the start of the eastern bridge abutment in front of the Quick Quack Car Wash.
In this segment of the project, I observed:
- Medians that need to be planted with grass in some areas
- One lane of traffic on each side of the median still blocked off for contractors to work on the medians
- Traffic cones still blocking off turn lanes where new traffic control lights have not yet been activated
- A few gaps in sidewalks caused by utility conflicts.
Other than that, it’s clear sailing in wider lanes than existed before the project. See the pictures below all taken during the afternoon of August 24, 2026. The sequence goes from east to west beginning near Russell Palmer Road.







Bridge Construction
Things get a little hairier in the last 2/10s of a mile. The east abutment is coming along well. It appears to have reached its full height or close to it. Yesterday, contractors appeared to be spreading and compacting the last layer or two of dirt.

Contractors are scheduled to pour the bridge abutment cap concrete next week weather permitting. They will also begin paving up to the ramp.
Railroad Crossing
So far, that’s all great news. But Northpark contractors still have some hiccups to contend with at the UnionPacific Railroad crossing near Loop 494.
On the south side of Northpark, two utility poles still block completion of the new surface lanes.


The last foot or so of pavement before and after the tracks will be completed when all new surface lanes, crossing signals and gates are in place and operational. In the meantime…
Zig Zag Continues
Traffic near Loop 494 continues to curve in and out around a) the eastern bridge abutment and b) where the western bridge abutment will eventually go between Whataburger and PNC Bank.


Entry-Pond Excavation
Meanwhile, the two entry ponds at US59 have almost reached full depth.


Contractors will apply cement and line both ponds at the same time to save money. That should happen around mid-May, 2026.
Street Illumination and Hydro-Mulch for Ditch One
The street light crew is continuing installation of street light foundations and light poles throughout the project.
Ditch 1 reestablishment has been completed.

Contractors will seed the slopes with hydro-mulch during the week of 5/4/26, weather permitting.
For More Information
See the Lake Houston Redevelopment Authority/TIRZ 10 web pages associated with this project for plans, videos and construction timelines. They also include a new 3-week lookahead schedule.
You can also search this website for “Northpark” for links to close to a hundred posts about the progress of the project.
This will be the first all-weather evacuation route from Kingwood. Phase I should be complete by mid-year next year.
Posted by Bob Rehak on 4/25/2026
3161 Days since Hurricane Harvey










