Northpark Drive Expansion work

First Concrete Poured for Northpark Drive Expansion

Earlier this week, contractors poured the first concrete for Northpark Drive expansion. It was for the first of several new outbound lanes at US59.

Looking north across Northpark. US59 on left. Note fresh concrete for first of new through- and turn lanes. 3/15/24.

Crews are doing both surface and subgrade work, moving back east towards Chick-Fil-A.

Stormwater Retention Basin Progress

Elsewhere along Northpark, excavation work continued on the south pond. The twin ponds will double as decorative ponds and stormwater detention basins to handle extra runoff from the wider roadway.

Looking N across south retention pond on Friday afternoon 3/15/24.

Also, in the south pond, Texas Wall & Landscape is continuing work on the retaining walls.

Setting forms for additional concrete in second retaining wall in South Pond
Crews were also bringing in fill to place behind the recently completed large retaining wall on the north pond.

What to Expect Next

According to the Lake Houston Redevelopment Authority website, crews will continue to work on drainage down the middle of Northpark and along the north side of the road, expecially between 59 and 494.

Looking E at construction of drainage and new outbound lanes along Northpark.

Entergy Power Lines Still Not Moved

Farther east, you can see that Entergy power lines still have not moved. The photo below shows where the bridge over the railroad tracks will go. In the bottom right corner, the roadway will expand to 10 lanes. Six will bridge over the tracks. And four (two on each side) will carry surface traffic turning north and south onto Loop 494.

However, Entergy’s power lines are in the way of the extra lanes.

Looking E along Northpark from over UP railroad tracks.

The big question at this point is when Entergy will move its power lines. It also has not yet begun moving its transformer near the Exxon Station at 59. Entergy ignored a City of Houston deadline to complete moving its lines by March 8. After another 8 days, the company has not yet even begun the work. Nor have they offered the public an explanation why.

Unfortunately, weather forecasters predict this hurricane season will be especially active. And one of the main purposes of this project is to provide an all-weather evacuation route for 78,000 Kingwood residents.

For More Information

For more information about the project including Phase I, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 3/8/24

2391 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.