10/12/26 – Harris County Flood Control District (HCFCD) has 44 items on the 10/15/26 Commissioners Court Agenda. Among them, a request to approve a $5 million grant from the Texas Water Development Board (TWDB) for drainage improvements to the Kingwood Diversion Ditch. See Item 432.
TWDB authorized the grant to HCFCD in January this year. State Rep. Charles Cunningham obtained it during the 89th Legislative Regular Session. By itself, the $5 million won’t come close to funding the entire Diversion Ditch Project. But it will play an important part in the larger funding picture.
On 3/26/26, former HCFCD Executive Director Dr. Tina Petersen, told the San Jacinto River Authority Board that the entire project will cost approximately $43 million and is fully funded through construction. At the time, Petersen estimated that construction would start in April 2027 and finish before the end of 2027.
Scope, Location Funding of Project
The scope includes four bridge replacements, a new diversion structure, 4.2 miles of channel work, and a new outfall that bypasses River Grove Park. See Page 18 of Petersen’s presentation.
Red Diagonal = Bens Branch. White = Kingwood Diversion Ditch. Green = new outfall to river.
Additional funding for Diversion Ditch improvements will come from Congressman Dan Crenshaw’s 2023 earmark to replace the Walnut Lane Bridge shown below. Crenshaw’s earmark helped rescue the project from oblivion in 2025 when the Democratic members of Harris County Commissioners Court passed a motion to reallocate all funding from projects that fell below the top quartile of their equity prioritization framework to projects in the top quartile.
However, Precinct 3 Commissioner Tom Ramsey PE warned of unintended consequences associated with that plan, i.e., the loss of federal funding already committed, such as Crenshaw’s. Crenshaw requested the funding in 2023. Congress awarded it in 2024.
U.S. Rep. Dan Crenshaw gives the thumbs up to the Walnut Lane Bridge project. Widening the bridge is necessary to widen the Kingwood Diversion Ditch (background) which will also help reduce flood risk along Bens Branch.
Diverting water from Bens Branch is important because Bens Branch runs through Kingwood Town Center where 12 people died from Harvey flooding.
Looking N toward Kingwood Drive from over the Walnut Lane Bridge.
Complementary Project
The Lake Houston Redevelopment Authority/TIRZ 10, also plans to build a detention basin and expand the Diversion Ditch north of Northpark Drive in Montgomery County. Spending Harris County money outside Harris County has encountered political resistance among some Harris County Commissioners in the past even though it could save Harris County lives.
4/14/26 – The San Jacinto Watershed received only 1% of all HCFCD spending in Q1, despite being the county’s largest watershed and having the worst flooding.
Harris County Flood Control District (HCFCD) has published updated spending figures for 2018 Flood Bond Projects through the end of the first quarter of 2026. Analysis also revealed:
No Kingwood or Huffman Area projects have reached the construction stage yet
Spending on Lake Houston Area projects continues to lag other watersheds throughout the county.
HCFCD’s years-long spending slowdown may be stabilizing
Separately, Dr. Tina Petersen, PhD, HCFCD’s executive director, recently announced several positive developments for projects on Cypress Creek, the East Fork and Lake Houston Dam.
Let’s look at the funding analysis first. The screen captures below come from the HCFCD Activity Page and speak for themselves.
Overall Spending Slowdown Stabilizing
The chart below shows incremental spending for ALL watersheds since the start of the flood bond in 2018. But the far right shows only one quarter for this year so far. If the first quarter were annualized, it would approximately equal 2025 year-end spending.
Incremental spending after 2026 Q1 for all watersheds.
However, all phases of activity have declined dramatically since the management change at HCFCD in 2021.
Where the Money Went in Q1
The chart below shows the San Jacinto Watershed ranked 14th versus others. Of the $52 million total dollars spent, more than half of the watersheds received less than $1 million each. Only five watersheds received more than $2 million. The Cypress Creek Watershed received $22 million (36% of the total). That $22 million was three times more than the next largest watershed – White Oak at $6.76 million.
Q1 2026 spending for all watersheds totaled only $52 million.
Petersen attributes construction delays to “getting the funding in place.”
San Jacinto Spending Slowed, Too
Looking closer at the San Jacinto watershed, we can see it dropped sharply. But part of the apparent drop has to do with the fact that you are only looking at one quarter so far for the first quarter of 2026.
Incremental spending for the San Jacinto watershed since 2018
In Q1, HCFCD spent only $524,000 in the entire San Jacinto Watershed. Of that, $491,000 came from partners. Only $33,000 came from HCFCD’s bond or budget.
Breakdown of 2026 Q1 spending in San Jacinto Watershed.Dark blue represents partner spending.
But the most significant takeaway should be the volume of spending in the watershed compared to the total for all watersheds during the quarter…
$.052 million is exactly one one-hundredth of $52 million.
Q1 San Jacinto spending vs. total for all watersheds
And that’s for the county’s largest watershed – where the worst flooding occurred during Harvey. See below.
Chart showing feet above flood stage of 33 gages of misc. bayous in Harris County during Harvey.
Total and Construction Spending
Overall, HCFCD and its partners have spent almost $2.2 billion to date.
Total spending by watershed associated with the 2018 flood bond
But most of that has been on upfront studies, engineering and right-of-way acquisitions. Of the total $2.2 billion spent so far, only $1 billion has been on construction – 36%.
Construction spending through 2026 Q1 from 2018 flood bond.
Among watersheds, the San Jacinto ranks 13th on construction spending (not including County-Wide Spending) since 2018. White Oak ranks #1 with $148 million. To date, the San Jacinto watershed has received $21.5 million – one seventh of the construction dollars received by White Oak.
Status of Kingwood/Huffman Projects
Only three projects are active in the Lake Houston Area.
The Luce Bayou Watershed will receive a new detention basin near FM2100 and the Huffman-Cleveland Road to support regional drainage improvements. Construction plans for the fully funded project are nearing completion, according to Petersen.
Status of Lake Houston Gates and East Fork Detention
Farther upstream on Cypress Creek, Petersen said she expects to finally start construction on the TC Jester East Basin soon. HCFCD also claims to have finished construction on the Mercer Basin on Cypress Creek near the Hardy Tollroad.
When I met with Petersen and State Representative Charles Cunningham last week, she also addressed:
A $20 million Inter-Local Agreement with the City of Houston for new Lake Houston Gates. It is on the 4/16/26 Commissioners Court Agenda. See Item 126.
San Jacinto East Fork stormwater detention basins. It’s unlikely any will be built. But “we’ve identified several locations along the East Fork, where if someone wants to sell their property, we will buy it … and we will get FEMA funding to do that.”.
Posted by Bob Rehak on 4/14/26
3150 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/04/2018-Bond-Spending-by-WS-Incremental.png?fit=2060%2C778&ssl=17782060adminadmin2026-04-14 17:55:142026-04-14 23:21:29San Jacinto Received Only 1% of HCFCD Spending in 2026 Q1
3/28/26 – At the San Jacinto River Authority (SJRA) Board Meeting on 3/26/26, HCFCD Executive Director Tina Petersen updated the board on a number of Lake Houston Area projects including the Kingwood Diversion Ditch. She confirmed it is fully funded – through construction.
However, design of the Diversion Ditch Project has not yet started. It should begin in April and finish by the end of 2027.
A year ago, the preliminary engineering study estimated the cost of the project at $40.7 million. Current estimates put the cost at $43 million, according to Petersen.
Looking N at the Kingwoodwood Diversion Ditch from over the Walnut Lane Bridge
Relationship to Bens Branch Flooding
The Diversion Ditch splits off of Bens Branch near St. Martha Catholic Church north of Northpark Drive.
Stormwater flow to Bens Branch will be restricted by pipes. That will force more stormwater into the expanded Diversion Ditch. In the process, that would take enough stormwater out of Bens Branch to improve it from a 2-year level of service to a 100-year level.
Red Diagonal = Bens Branch. White = Kingwood Diversion Ditch. Green = new outfall to river.
Diverting water from Bens Branch is important because Bens Branch runs through Kingwood Town Center where 12 people died from Harvey flooding.
Crenshaw Connection
Ironically, funding obtained by US Congressman Dan Crenshaw back in 2024 to widen the bridge shown above at Walnut Lane saved this project from the chopping block – even though it was ranked the most important project in Kingwood by the Kingwood Area Drainage Analysis.
At the time, Precinct 3 Commissioner Tom Ramsey PE warned that killing projects in Quartiles 2, 3 and 4 could have dire unintended consequences. The Diversion Ditch project fell into Quartile 3.
After the Democrats saw how much partnership funding they would lose by killing projects in the lower quartiles, they relented. In their next meeting, they voted to exempt projects in the lower quartiles that already had partnership funds committed.
That breathed new life into the Kingwood Diversion Ditch project because it included widening of the Walnut Lane Bridge which Crenshaw had already secured funding for.
HCFCD spokesperson Emily Woodell confirmed the Diversion Ditch funding today. “It was categorized as a partnership project during the bond update presented to commissioners court in August [2025] which means it is fully funded through construction.”
For Updates on Other San Jacinto Watershed Projects
It covers a lot of territory including the history of HCFCD, status of the bond program, partnership funding, maintenance programs, gauges, the flood-warning system, and more.
Other capital improvement projects in the Lake Houston Area that she discusses include:
Woodridge Village/Taylor Gully – Construction starting in April.
Jackson Bayou Detention Basin – Construction starting Q3/2026.
Barrett Station Drainage Improvements – Currently in Design Stage.
Lake Houston/East Fork/West Fork Dredging – Completed.
Lake Houston Gates – Engineering should finish by end of this year.
3/20/26 – This week, we had more two more examples of flood-mitigation projects that are being studied to death.
Spring Creek Watershed Flood Control Dams on Birch and Walnut Creeks
Kingwood Diversion Ditch
They might not be buried yet, but they might as well be.
Let’s look at each and the implications for flood control.
Birch and Walnut Creeks
The two flood-control projects in the Spring Creek watershed were first studied in 1976 (see page 24) when the land was predominantly forested and could have been purchased for a tiny fraction of what it costs today. No one took action then. The benefit/cost ratio came in close to zero; project costs far outweighed benefits by more than 10:1.
This week, 50 years later, SJRA published another study, suggested by a previous 2020 study. And the new study suggested yet another study. But the study just published took so long – 5 years – that land for the projects sold to developers before SJRA completed the study. Whew! Follow all that?
So, the current study’s authors actually suggested yet another study to see if an unidentified sponsor could buy the property (which isn’t for sale) – while engineers design the dams, which probably won’t qualify for funding.
Why? The current study took so long that the federal government excluded social benefits from Benefit/Cost Ratios (BCRs). But the reported BCRs included social benefits…because the study’s authors hoped the Federal Government might include them again at some point in the future. So much for making studies actionable!
It may be time to put this one out of its misery. SJRA can’t even seem to interest Waller County in helping, even though its own residents would benefit the most.
Sites of proposed flood-control dams in NE Waller County within the Spring Creek Watershed.
Kingwood Diversion Ditch
One third of all the people who died in Harris County during Harvey died along Bens Branch when the Kingwood Diversion Ditch couldn’t divert enough stormwater.
Ben’s Branch and the Kingwood Diversion Ditch operate as one system to drain the western half of Kingwood. Friendswood conceived the Diversion Ditch as a way to take pressure off Ben’s Branch. But over time, upstream development has overwhelmed both.
Back in 2020, HCFCD’s Kingwood Area Drainage Analysis named the Diversion Ditch the most important project in the area. Congressman Dan Crenshaw requested a $1.6 million grant for Diversion Ditch design in 2021 and obtained it.
Then a preliminary engineering review took three years longer than planned and was widely criticized for missing opportunities.
Next, HCFCD took two years to negotiate the price of the design phase which should have finished by now. But it hasn’t even started yet. So yesterday, HCFCD requested a 2-year extension on the grant.
If lucky, we may see the design by 2028 – 11 years after Harvey. Then come the long and arduous tasks of obtaining funding and completing construction. By then, new upstream development will likely have changed design assumptions. And another study may be necessary.
To widen a straight-line ditch, we’ve already spent twice as much time as it took the U.S. to win World War II.
Looking South along the Kingwood Diversion Ditch from Kings Mill
Political Fragmentation Favors Delay, Not Decisiveness
In my opinion, both of these flood-mitigation projects have stalled because the people in charge of them have lost all sense of urgency or can’t see a clear path to completion.
Action is difficult in the highly fragmented world of flood control because it requires coordination among multiple government agencies on the local, county, state and federal levels. It’s much easier to create the appearance of action – with studies.
But the studies by themselves do nothing to reduce flood risk. For those with long memories or PTSD, they at least hold out hope that someday, somehow, something may happen.
In reality, though, these projects have almost a zero chance of getting built.
The study findings are already obsolete – because of inflation, new development, policy changes, and new political leaders with different priorities. So, we just keep studying things to death.
Meanwhile, indecision is a decision with consequences measured downstream. I have four suggestions:
The state should set up river-basin wide flood control districts. We’re all in this together.
Collectively, we need to redesign flood mitigation business practices around prevention, not correction. It’s much easier and exponentially cheaper.
Hold managers to deadlines. Hire people with entrepreneurial experience and a sense of urgency.
Quit studying things to death. If a project won’t happen, admit it and focus on projects with a fighting chance.
I can already hear the critics now. “Let’s study those suggestions!”
Posted by Bob Rehak on 3/20/2026
3125 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/10/RJR_4304.jpg?fit=1500%2C1000&ssl=110001500adminadmin2026-03-20 20:44:572026-03-20 20:44:58Studied to Death
3/13/26 – Harris County Flood Control District (HCFCD) has asked for a 20-month extension on the Kingwood Diversion Ditch Project scheduled to take 24 months. The original period of performance for the contract was from 4/1/24 to 4/1/26. But backup provided to Commissioners Court shows HCFCD doesn’t even expect to give the vendor a notice to proceed until 4/27/26.
The announced reason for the extension request: “…an unforeseen delay in project cost negotiations to remain within budget…”
“Who negotiates with a vendor for two years on a job with a two year deadline?”
The Kingwood Area Drainage Analysis recommended expanding the Diversion Ditch as the top priority in Kingwood in 2020.
Preliminary engineering on the project began in 2021. But then the Democrats on Commissioner’s Court forced a management change at HCFCD.
The preliminary engineering was supposed to take 330 days, but it took four years instead. Worse, after all that time, it was criticized for not reflecting actual conditions and obvious recommendations. HCFCD blamed the problems on vendor “personnel issues.”
But it took HCFCD another seven months from publication of the preliminary engineering report to the time they officially delivered it to Commissioners Court for formal approval.
Congressman Dan Crenshaw first requested a $1.6 million grant for Diversion Ditch design in 2021. It was approved in the fiscal year 2022 budget by Congress. Now, HCFCD is requesting a two-year extension until December 31, 2027.
From the identification of the need in the Kingwood Area Drainage analysis on 10/20/20 to the projected end date of 12/31/27, 2628 days will elapse (assuming no more delays).
To put that in perspective, the U.S. won World War II in 1348 days.
So, it will take almost twice as long to redesign a channel as it did to win World War II! That takes some real talent! I’m not sure it’s possible to walk a project any slower and not have Commissioners Court notice. To be fair, the Diversion Ditch IS more than three miles long!
Posted by Bob Rehak on 3/13/26
3118 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/04/20230401-DJI_0363.jpg?fit=1100%2C733&ssl=17331100adminadmin2026-03-13 19:09:542026-03-20 14:19:22Kingwood Diversion Ditch Project Delayed Again
1/30/26 – A four-million dollar earmark secured by U.S. Representative Dan Crenshaw for widening the Walnut Lane Bridge in Kingwood saved the entire $44 Million Kingwood Diversion Ditch Project from being killed by the Democratic members of Harris County Commissioners Court.
U.S. Rep. Dan Crenshaw gives the thumbs up to the Walnut Lane Bridge project. Widening the bridge is necessary to widen the Kingwood Diversion Ditch (background) which will also help reduce flood risk along Bens Branch.
At the time, Precinct 3 Commissioner Tom Ramsey PE warned that killing projects in Quartiles 2, 3 and 4 could have dire unintended consequences. The Diversion Ditch project fell into Quartile 3.
After the Democrats saw how much partnership funding they would lose by killing projects in the lower quartiles, they relented. In their next meeting, they voted to exempt projects in the lower quartiles that already had partnership funds committed.
That breathed new life into the Kingwood Diversion Ditch project because it included widening of the Walnut Lane Bridge which Crenshaw had already secured funding for.
Multiple Benefits: A Texas Twofer
But the project will benefit far more of Kingwood than just the people who live in Diversion Ditch floodplains. It will also benefit people who live near Bens Branch. That includes the Villages of Bear Branch, Kings Forest, Hunters Ridge, Town Center, Kings Harbor and Kingwood Greens.
That’s because widening the Diversion Ditch will take excess stormwater out of Bens Branch and allow water to move safely down the Diversion Ditch. The planned improvements will take Bens Branch from a 2-year level of service to a 100-year level.
Kingwood Diversion Ditch in white, new outfall in green, and Bens Branch in red.
That means homes in the Bens Branch floodplains should be safe in anything up to a 100-year storm. Currently, the stream is at risk of flooding parts of its watershed every two years.
When the Diversion Ditch project is completed, Crenshaw will have helped protect people and property values in approximately half of Kingwood.
Bob Rehak
Crenshaw Support Crucial on Other Projects, Too
The Kingwood Area Drainage analysis found that, based on the number of people who benefit, the Diversion Ditch project is one of the two most important in Kingwood. Another is the Taylor Gully/Woodridge Project which Crenshaw also secured funding for.
Editorial Comment: I interviewed Crenshaw in 2018 when he first ran for Congress and have followed his work in Washington ever since. The man is a warrior, scholar and leader. He fights tirelessly to improve the lives of his constituents. He studies issues. And thoughtfully and patiently explains them. There’s no way he could have known what Commissioners Court would do in 2025 when he proposed the Walnut Lane Bridge funding in 2023. Regardless, his proactive effort will improve the safety of tens of thousands of his constituents.
1/28/26 – People living near the Kingwood Diversion Ditch and the Woodridge Village/Taylor Gully area have been asking what happened to their flood-mitigation projects. Good news: Both are moving forward. Here’s some historical context, where the projects currently stand, and what comes next.
Kingwood Diversion Ditch
The Kingwood Diversion Ditch splits off Bens Branch between Northpark Drive and the new St. Martha Catholic Church. It runs down the western side of North and South Woodland Hills past the fire station on Kingwood Drive. Then it continues south past Trailwood, Deer Ridge Park and finally joins the San Jacinto West Fork at River Grove Park. Along the way, it goes under four bridges.
Neel-Schaffer completed a preliminary engineering study in early 2025. The company recommended widening the Diversion Ditch and building a new outfall to West Fork west of River Grove Park. They projected the cost to be almost $41 million, but it would reduce the floodplain size by 177 acres and remove 34 structures from the floodplain.
Diversion Ditch shown in white, proposed new outfall in green, and Bens Branch in red.
The improvements would divert enough stormwater from Bens Branch to take it from a 2-year level of service to a 100-year level. That’s good news for the merchants in Kingwood Town Center. They all flooded during Harvey and 12 seniors died at Kingwood Village Estates.
The project almost died last year when Democratic County Commissioners voted to redeploy all remaining flood bond funds to the highest scoring projects on their equity prioritization framework. However, they later reconsidered that motion. The Diversion Ditch already had federal partnership funds allocated to it thanks to the work of Congressman Dan Crenshaw. His earmark for the Walnut Lane Bridge saved it from the chopping block.
Now the project is moving again. In late 2025, Harris County awarded a contract to Halff Associates, Inc. for the final engineering and design of the project.
In its January 22 board meeting, the Texas Water Development Board authorized an agreement with Harris County Flood Control District for a $5 million grant that State Representative Charles Cunningham obtained during the 89th Legislative Regular Session. (See item 12.)
HCFCD spokesperson Emily Woodell said the District expects the design work to start by March 1. She also says that additional funding will come from EPA grants to cover design and the 2018 bond to cover construction. Woodell expects construction to begin in late 2027.
Woodridge Village/Taylor Gully
The Kingwood Area Drainage Analysis ranked the Diversion Ditch and the Woodridge Village/Taylor Gully Project as the two most important projects in Kingwood because they help the largest numbers of people.
The 270-acre Woodridge Village Project is the aborted Perry Homes development purchased by Harris County and the City of Houston in 2020. It lies north of Sherwood Trails and Elm Grove in Montgomery County. Except for a few acres on the extreme western end, virtually all of it drains into Taylor Gully.
Perry’s contractors clearcut the Woodridge site starting in 2017 and sloped it toward Taylor Gully. Then before they installed detention ponds and drainage systems, runoff from the site flooded up to 600 homes twice in 2019. Residents had not even finished repairing their homes from the first flood in May, when they flooded again in September. A massive class action lawsuit resulted in a substantial settlement for the victims.
Taylor Gully flooding near Rustling Elms on May 7, 2019.
Before purchasing Woodridge Village from Perry, HCFCD stipulated that they had to finish building all of the stormwater detention basins planned as part of the buildout. However, those detention basins only brought the property up to pre-Atlas 14 standards. They fell 40% short of Atlas 14 requirements.
Shortly after the purchase, HCFCD started building an additional detention basin to bring the total detention capacity onsite up to and beyond Atlas-14 requirements. Sprint Sand and Clay began the work under an excavation and removal (E&R) contract. E&R contracts give HCFCD a head start on production. They let contractors begin removing dirt for a nominal fee and then sell it on the open market to make up their profit margin.
Woodridge Village on May 31 2025. The beginning of a new detention basin was never completed or connected.
However, when HCFCD applied for a HUD CDBG-MIT grant through the Texas General Land Office, HCFCD was forced to pause the project. That’s because projects cannot change while the GLO and HUD consider a grant request.
Scope of project outlined in preliminary engineering review. Compartment 1 is in current bid and will take project up to and slightly beyond Atlas 14 requirements. Compartment 2 will be treated as a separate project in the future if/when needed.
Expand a portion of Taylor Gully and line it with concrete.
Build another stormwater detention basin on Woodridge Village holding 412 acre-feet.
Replace the culverts at Rustling Elms with a clear-span bridge.
Fast forward: GLO and HUD approved grants for $42 million in October, 2025. HCFCD put the project out for bids. And proposals are due by Feb. 16, 2026. See screen capture from County purchasing below.
Screen capture supplied by Precinct 3 Engineer Eric Heppen
Even though the bid above is listed as “channel conveyance improvements,” according to Woodell, it also includes the Woodridge Village Stormwater Detention Basin(s). “Since Woodridge mitigates Taylor Gully, those two projects have been combined forever after,” she said.
The HUD/GLO deadline for finishing the project is March 31, 2028. That’s do-able if everyone hustles.
Additional funding for this project came from U.S. Representative Dan Crenshaw. He secured federal funding for Taylor Gully improvements in March 2022. And Representative Charles Cunningham helped secure state funding through the TWDB.
At a September 2024 press conference where Woodridge meets Taylor Gully. Left to Right, Harris County Precinct 3 Commissioner Tom Ramsey PE, US Rep. Dan Crenshaw, HCFCD Exec. Dir. Dr. Tina Petersen, Houston City Council Member Fred Flickinger and State Rep. Charles Cunningham.
More news to follow when we see the bids.
Posted by Bob Rehak on January 28, 2026
3074 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/01/Kingwood-Flood-Mit.jpg?fit=1100%2C670&ssl=16701100adminadmin2026-01-28 14:44:172026-01-28 17:05:33Update on Two Kingwood Flood-Mitigation Projects
9/15/25 – Harris County Commissioners Court is being asked to approve a contract for final engineering of new Kingwood Diversion Ditch conveyance improvements this Thursday, 2/18/25. See Item 272 on the Agenda.
The Kingwood Area Drainage analysis ranked Diversion Ditch improvements as the most important project in Kingwood. That’s in large part because improving flow through the Diversion Ditch will take floodwater out of Bens Branch which runs through Kingwood Town Center. So, it’s like a Texas twofer.
Diversion Ditch shown in white, proposed new outfall in green, and Bens Branch in red.
County Purchasing Dept. Recommending Halff
The Harris County Purchasing Department recommends Halff Associates, Inc. based on “highest overall evaluation” for their proposal. The County reserves the right to negotiate with the next highest ranking proposal if it can’t reach a suitable agreement with Halff.
This is a request to authorize negotiation for an agreement that will provide final design, bidding and construction phase services for Kingwood Diversion Ditch channel conveyance improvements.
The project begins upstream of the confluence of Bens Branch and the Kingwood Diversion Ditch and ends downstream at the West Fork San Jacinto River. The total project length is approximately 4.2 miles along the Kingwood Diversion Ditch.
Looking upstream/north at the Diversion Ditch toward Kingwood Drive from over the Walnut Lane Bridge. The “Kingwood Rapids” are just out of frame at the bottom of the frame.
Conveyance improvements will include:
Construction of a diversion structure to divert flow off Bens Branch into the Kingwood Diversion Ditch
Erosion protection against a naturally steep portion of the existing channel near Walnut Lane
A new outfall at Woodland Hills into the West Fork San Jacinto River
405 acre-feet of stormwater detention to mitigate for impacts from the channel improvements
Improvements to five existing bridges.
The project area along Kingwood Diversion Ditch consists of approximately 3.86 miles inside Harris County limits and an additional 0.32 miles extends into Montgomery County. The project falls into the second quartile of the County’s Equity Prioritization Framework.
Looking S at Kingwood Diversion Ditch from near the Montgomery County Line and Kings Mill.
Earlier this year, Commissioners voted to redeploy all remaining funding in Quartiles 2, 3, and 4 to complete projects in Quartile 1. However, they later reconsidered that motion. The fact that the Diversion Ditch already has federal partnership funds allocated to it thanks to the work of Congressman Dan Crenshaw, whose earmark for the Walnut Lane Bridge saved it from the chopping block.
Separately, the County expects to hear a new proposal from HCFCD Executive Director Dr. Tina Petersen this Thursday. Petersen reportedly hopes to explain less Draconian ways to address a shortfall in bond funding that could affect the fate of a large number of other projects.
Posted by Bob Rehak on 9/15/25
2939 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/05/20230401-DJI_0363.jpg?fit=1200%2C799&ssl=17991200adminadmin2025-09-15 22:09:152025-09-15 22:16:30Final Kingwood Diversion Ditch Study Up for Approval Thursday
6/5/25 – The Northpark Drive Expansion Project has been a beehive of activity recently.
A major traffic switch will happen Friday.
Crews have paved several blocks of new westbound lanes and are working their way toward the railroad tracks.
They have finished the first pit for boring under the UnionPacific tracks and are getting ready to place the boring machine into it. They have also started excavating the receiving pit on the west side of the tracks.
Contractors at the Northpark Enclave continue to work even as Montgomery County Precinct 4 is trying to set up a meeting between Montgomery County Engineering, City of Houston, EHRA (the Enclave’s engineering company), and HNTB (the Lake Houston Redevelopment Authority’s engineering company). The purpose: to discuss concerns about potential overflow from the development’s retention pond during extreme weather events into the evacuation route for 78,000 people.
Lane Switch
Westbound traffic between Loop 494 and US59 will be routed to recently paved lanes on the north side of Northpark starting Friday, June 6.
According to Ralph De Leon, Northpark Expansion project manager, “Beginning June 6th at 9pm, Harper Brothers Construction will shift westbound Northpark Drive traffic to the newly constructed westbound lanes.”
The contractor will then install new storm sewer pipes and construct new concrete roadway between the eastbound and westbound lanes. This shift should last approximately 6 months. And no additional lane changes will take place during that time in that area.
De Leon provided this map to help motorists understand Friday’s change.
Beginning 6.6.25 at 9 PM
That same area looks like this from a lower angle.
Crews will reroute traffic to the lanes on the right with the orange traffic cones.
Westbound traffic now in the middle will move to the right and crews will begin work in the middle.
Paving
During the last few months, work on the north side of Northpark east of the railroad tracks has focused mainly on utility relocations and drainage installation. Now, crews are starting to pave that area working from east to west – toward the tracks.
Note the fresh concrete on the left below.
Looking East along Northpark DriveReverse angle. Looking W from same location. Crews are working on pavement prep work, i.e., rebar placement.
Boring Under Union Pacific Tracks
Steel pipe previously stockpiled south (left) of Northpark has been moved to the north side in preparation for the bore.Workers have completed the steel frame for the boring operation and poured a concrete floor for the bore pit.
They have also placed a section of railroad tracks into the pit. The boring machine will later be placed on the tracks.
On the far side of the tracks, you can see them starting to excavate the receiving pit.
Two steel pipes will run under the tracks side by side to convey storm water toward the Diversion Ditch from the area on the west side of Loop 494. As crews push each section in, they will weld a new section on.
Enclave Construction
Contrary to earlier reports, construction at the Enclave has not stopped during a peer review of the subdivision’s drainage.
Photo taken 6/4/25 at approximately 2 PMshowed activity throughout the site.
Victoria Bryant, Montgomery County Precinct 4 Project Coordinator says that she is trying to set up a meeting between the engineering companies, MoCo Engineering and the City of Houston.
Pictures below show activity on the site.
Culvert installation almost reached the development’s detention basinat 2PM on 6/4/25.More drainage being installed on 6/3/25Pipes going in the ground.Also on 6/3/25.
Drainage Concerns
Meanwhile, construction plans show that the detention basin could overflow into the only evacuation route for 78,000 people during extreme rainfall events.
Enlarged and cropped detail from construction plans.
But it doesn’t take a 100-year rainfall to create a 100-year flood in the Kingwood Diversion Ditch.
The photo below taken by Kingwood flood activist Chris Bloch during the May 2024 flood shows runoff in the Kingwood Diversion Ditch reaching above the bottom of the Northpark Drive Bridge, which was above the predicted 100-year flood level.
But the closest Harris County Flood Control rain gage showed that the May 2024 event that caused water to reach that high was approximately a 5-year rainfall by today’s Atlas-14 standard.
Photo courtesy of Chris Bloch
But there’s more. Plans for the bridge show that the bottom is at 75.76 feet.
About a half mile downstream, drainage from the Enclave and the rest of Kings Mill crosses under Russell Palmer Road and enters into the Diversion Ditch.
Water in the Diversion Ditch at the bridge was higher than the crown of Russell Palmer Road at the detention basin.
When water in a receiving ditch is higher than water in a connected detention basin, it creates back-pressure on the water in the basin. Water can actually flow into the basin from the ditch.
At a minimum, higher water in the Diversion Ditch would slow the water coming out of Kings Mill and the Enclave. That raises the height of stormwater in the detention basin(s) and keeps it there longer.
Also, note that the outfall pipe for the Kings Mills Detention Basins is at the BOTTOM of the Diversion Ditch. (See below.) That exacerbates the back-pressure issue.
Route of stormwater from Kings Mill Detention Basin (right) to Kingwood Diversion Ditch (left)
Conclusion: Mismatch Between Regulations and Reality
The Diversion Ditch has become seriously overburdened with runoff from subdivisions that were developed when the rainfall probability estimates used by Montgomery County were 40% lower than they are for this area today.
That may or may not cause the Enclave detention basin to overflow into Northpark during a REAL 100-year event. It will be interesting to see what the engineers determine. Only they can tell how high, how far, and how long the water will back up.
Chances are small that the Enclave detention basin will overflow into Northpark during an evacuation. But the stakes are huge.
Posted by Bob Rehak on 6/4/25
2836 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2025/06/20250604-NorthPark-Traffic-Switch-06-06-2025R.jpg?fit=1100%2C712&ssl=17121100adminadmin2025-06-04 20:17:332025-06-05 13:46:02Northpark Update: Lane Switch, Paving, Tunneling, Enclave
3/10/25 – In the last week, Harris County Flood Control District (HCFCD) launched a new interactive map at the bottom of its homepage. In it, HCFCD calls many projects complete that have not even started.
The map supposedly contains the status of each project in the county along with links to more project details.
However, the information is riddled with errors. The map also contains several usability issues that place barriers between people and information.
Together, the issues show a disturbing lack of attention to detail and quality control that undermines the credibility of HCFCD.
Examples of Incorrectly Coded Projects
For instance, you may be pleased to know that the project to add more floodgates to the Lake Houston Dam is “complete.” It’s not. Ask Houston City Council Member Fred Flickinger who just provided an update on the ongoing engineering of the gates.
This and all other screen captures below taken on 3/10/25. Note project status in lower right corner.
Neither are the projects complete to add stormwater-detention capacity to Woodridge Village and to improve Taylor Gully. However, the map shows them completed also.
HCFCD also marked the Kingwood Diversion Ditch Project “in progress.” It’s not.
“None of this information is true!”
– Bob Rehak
With the exception of the Woodridge project, the District has not turned one shovel of dirt on any of the projects above.
The District tabled the Woodridge project in November 2023 when it decided to seek HUD funding to complete it. Here’s how HCFCD left the site.
“Completed” Woodridge Village Detention Basin. Photo taken today, 3/10/25.
HCFCD even marked the TC Jester Detention Basins on Cypress Creek complete.
HCFCD did not respond to questions about the errors, nor did it take the error-ridden, interactive map down as of close of business today.
Usability Flaws, Too
In addition to the project-status errors, the map also contains some serious usability flaws.
For instance, clicking on the link for more information about a project sometimes takes one to a page that asks you to sign into “ArcGIS Online.”
But that requires HCFCD employee credentials.
However, take heart. If you wait several minutes, information may eventually load OFFSCREEN and ABOVE the sign-in prompt…where few would ever bother to look for it. Very clever!
A source familiar with Harris County Universal Services, the county’s IT department, attributed the bizarre performance of the map, in part, to incompetent coders and project managers with forged credentials working on H1-B visas.
That may be an even bigger problem! If you think Elon Musk rummaging through IRS data is an issue, imagine foreign nationals rummaging through your Harris County tax information. But I digress.
In the meeting, Commissioners adopted several measures to limit the financial impact to the county in case DOGE rescinds $1.1 billion of previously promised HUD disaster-relief and flood-mitigation funding.
In the same meeting, Commissioners also demanded an update from HCFCD Executive Director Tina Petersen about the status of every project. The reason: so they could make sure so-called “equity projects” were completed in low-to-moderate income areas before those in more affluent areas.
Precinct 1 Commissioner Rodney Ellis said he didn’t want to wait “until all the money was gone.” He added, “I know there’s not enough money to do all the projects we talked about and everybody else knows it.”
I hope Ms. Petersen provides better information to her bosses than to the public. She just received a $90,000 raise. You could hire several proofreaders for that!
No telling how many errors are embedded in the interactive HCFCD map; I am not familiar with every project in the county. If you know of other errors in projects near you, please send me a note through the contact form on this website.
Posted Bob Rehak on 3/10/25
2750 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2025/03/20230812-RJR_2246.jpg?fit=1100%2C733&ssl=17331100adminadmin2025-03-10 20:29:092025-03-10 23:38:55HCFCD Calls Projects Complete that Have Not Even Started