Lake Houston Dam

HCFCD Calls Projects Complete that Have Not Even Started

3/10/25 – In the last week, Harris County Flood Control District (HCFCD) launched a new interactive map at the bottom of its homepage. In it, HCFCD calls many projects complete that have not even started.

The map supposedly contains the status of each project in the county along with links to more project details.

However, the information is riddled with errors. The map also contains several usability issues that place barriers between people and information.

Together, the issues show a disturbing lack of attention to detail and quality control that undermines the credibility of HCFCD.

Examples of Incorrectly Coded Projects

For instance, you may be pleased to know that the project to add more floodgates to the Lake Houston Dam is “complete.” It’s not. Ask Houston City Council Member Fred Flickinger who just provided an update on the ongoing engineering of the gates.

This and all other screen captures below taken on 3/10/25. Note project status in lower right corner.

Neither are the projects complete to add stormwater-detention capacity to Woodridge Village and to improve Taylor Gully. However, the map shows them completed also.

HCFCD also marked the Kingwood Diversion Ditch Project “in progress.” It’s not.

“None of this information is true!”

– Bob Rehak

With the exception of the Woodridge project, the District has not turned one shovel of dirt on any of the projects above.

The District tabled the Woodridge project in November 2023 when it decided to seek HUD funding to complete it. Here’s how HCFCD left the site.

“Completed” Woodridge Village Detention Basin. Photo taken today, 3/10/25.

HCFCD even marked the TC Jester Detention Basins on Cypress Creek complete.

However, that project won’t even go out for bid until the fourth quarter of this year.

From HCFCD’s 12-month Bid Calendar. Arrow added.

HCFCD did not respond to questions about the errors, nor did it take the error-ridden, interactive map down as of close of business today.

Usability Flaws, Too

In addition to the project-status errors, the map also contains some serious usability flaws.

For instance, clicking on the link for more information about a project sometimes takes one to a page that asks you to sign into “ArcGIS Online.”

But that requires HCFCD employee credentials.

However, take heart. If you wait several minutes, information may eventually load OFFSCREEN and ABOVE the sign-in prompt…where few would ever bother to look for it. Very clever!

A source familiar with Harris County Universal Services, the county’s IT department, attributed the bizarre performance of the map, in part, to incompetent coders and project managers with forged credentials working on H1-B visas.

That may be an even bigger problem! If you think Elon Musk rummaging through IRS data is an issue, imagine foreign nationals rummaging through your Harris County tax information. But I digress.

Why An Untested Map?

The sudden appearance of the map follows fast on the heels of the Harris County Commissioners Court meeting on February 27, 2025.

In the meeting, Commissioners adopted several measures to limit the financial impact to the county in case DOGE rescinds $1.1 billion of previously promised HUD disaster-relief and flood-mitigation funding.

In the same meeting, Commissioners also demanded an update from HCFCD Executive Director Tina Petersen about the status of every project. The reason: so they could make sure so-called “equity projects” were completed in low-to-moderate income areas before those in more affluent areas.

Precinct 1 Commissioner Rodney Ellis said he didn’t want to wait “until all the money was gone.” He added, “I know there’s not enough money to do all the projects we talked about and everybody else knows it.”

I hope Ms. Petersen provides better information to her bosses than to the public. She just received a $90,000 raise. You could hire several proofreaders for that!

No telling how many errors are embedded in the interactive HCFCD map; I am not familiar with every project in the county. If you know of other errors in projects near you, please send me a note through the contact form on this website.

Posted Bob Rehak on 3/10/25

2750 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.