Northpark Crews Begin Pouring Concrete Monday, Road Narrowed
Northpark Drive construction crews have finished placing rebar in a 1000 foot long stretch on both sides of the entrance to Kings Mill. They will begin pouring concrete there on Monday, 9/16/24 at 3 AM. Concrete trucks will enter and leave the construction zone approximately every six minutes.
Because workers will spread the concrete next to the inbound lanes, traffic will be reduced to one lane until approximately 1 PM. However, both inbound lanes should open for the evening rush hour.
At this time, the construction team has scheduled additional concrete pours for 9/20, 9/27, and 10/1; times and dates subject to change.
Project managers evaluated all-night and all-weekend scenarios for pouring the concrete, but encountered legal restrictions having to do with worker safety and/or cost.
Back-and-Forth Paving Plan
The general plan is for crews to pour one side of one stretch of the road while prepping the other. After they finish the new middle lanes, the old outer lanes will be demolished one side at a time. They will reroute traffic to the middle lanes will reconstructing the old lanes.
At this point, neither inbound nor outbound traffic will be shut down completely, though it will narrow to one lane on the side where concrete is being poured.
More Visible Progress
Ralph De Leon, the project manager, emphasized that most of the wrinkles that the project experienced in the last year have been ironed out at this point. However, one small snag remains re: a switch of fire hydrants and buildings with commercial sprinkler systems on the north side of Northpark.
Several companies and a church are migrating to the City of Houston water system, and it’s apparently taking longer than expected for the City’s billing and meter installation department to catch up with the new infrastructure installation. Worst case: some businesses may get free water for a month or so.
De Leon asked for patience. “People don’t see all the work that’s going on underground, but that’s the real heavy part of the lift,” he said. “People will begin to see a lot more progress on Monday. The above-ground ‘flat work’ that everyone sees goes much faster.”
Major Steps After This
The area between the Diversion Ditch and Russell Palmer Road will be paved as part of Phase II, which includes everything up to and a little bit past Woodland Hills Drive.
Paving crews will next complete the new lanes between Russell Palmer and 494.
Next, paving crews will turn their attention to 494.
Finally, crews will begin work west to US59.
The entry ponds will likely be among the last things completed.
In my last post, I alluded to a total shutdown of Northpark while UnionPacific installed new beds and track across the road. Originally scheduled for sometime in October or November, that will now happen in January or February.
It’s too early to tell when bridge construction over 494 will commence.
For More Information
For schematic diagrams of the paving plan, click here.
As paving moves east to west, crossovers will need to close temporarily. To see the schedule, click here.
For a three-week look-ahead schedule, visit the Lake Houston Redevelopment Authority website.
Also, see these posts on ReduceFlooding for a history of the project:
- 24/08/18 Northpark Drive Construction Sequence Changing
- 24/08/08 Northpark Drive Expansion Project Overcoming Hurdles
- 24/06/21 Northpark Expansion Obstacles Finally Being Addressed
- 24/04/21 Northpark Floods at Russell-Palmer Road
- 24/04/19 Entergy Makes Some Progress on Northpark but Significant Issues Remain
- 24/04/07 Northpark Entergy Saga: New Power Poles Slowly Going Up
- 24/04/02 New Entergy Power Poles Finally Arrive on Northpark
- 24/03/29 Northpark Expansion Update; Still No Sign of Entergy
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/08 TXDoT, LHRA Engage Kingwood at Northpark Phase II Meeting
- 24/03/05 Details of Phase II Meeting
- 24/02/27 February ’24 Northpark Expansion Update Including Lane Closures
- 24.02/24 Save the Dates: Public Input Meetings for Diversion Ditch, Northpark Expansion Phase II
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/10 Entergy in City’s Crosshairs, Lane Closures Announced
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/12/03 Northpark Expansion Presses Forward While Fighting Entergy Obstacle
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/26 Project moving forward on multiple fronts
- 23/10/12 Transplanting first tree
- 23/10/02 Clearing of south-side entry for second pond
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
Posted by Bob Rehak on 9/13/24
2572 Days since Hurricane Harvey