Most Northpark Expansion Work Shifts West of Loop 494
7/7/25 – Most current Northpark expansion work has shifted west of Loop 494 out to US59.
Work had been underway to bore underneath the UnionPacific Railroad tracks in order to connect the drainage east and west of the tracks.

However, workers in the “receiving pit” encountered more unplanned utility conflicts and work stalled.

The boring work on hold pending approval of a plan to remove the conflicts.
Removing Old Junction Box by Sonic
Meanwhile, the focus of work has shifted west. One storm-drain crew is working to remove an old drainage structure by the Sonic driveway. See pit in front of yellow excavator below.

Getting Ready for Fast-Track Paving
This week another crew will complete the sub grade in this same area from Whataburger to LP 494 in preparation for Fast Track paving.

Drainage Work in Center Will Soon Begin

According to the Lake Houston Redevelopment Authority’s latest update, median work between I-69 and Whataburger will also include a detention pond equalizer pipe.

Eastbound Inlets and Lateral Drainage
A storm-sewer crew will soon finish placing the inlets and laterals on eastbound Northpark from Anderson to Kings Mill.

Loop 494 Paving and More

Installation of new driveways on westbound Northpark from Sherwin-Williams to Extra Space storage will soon finish. That’s good news for those merchants. See below.

But getting into and out of the Exxon Station will require some exploration for a while.

Here’s a three-week look-ahead schedule that tells you, weather permitting, what should happen when. Please note, however. The last item (illumination poles on south side of Northpark from Italiano’s to east end of project) has been delayed and will not happen as scheduled.
Posted by Bob Rehak on 7/7/25
2869 Days since Hurricane Harvey











