Tag Archive for: Northpark expansion

New Entergy Power Poles Finally Arrive On Northpark

I got a tip last night that new Entergy power poles finally arrived. Today, I photographed the long-awaited equipment. The poles are not up yet. Nothing is connected to them. Most are just lying in the dirt.

In the quest to build an all-weather evacuation route for 78,000 Kingwood residents, readers may remember that the Lake Houston Redevelopment Authority/TIRZ-10 has sparred with Entergy for four years. Entergy’s power lines need to be moved out of a City-owned easement to accommodate the expansion of Northpark Drive.

I have confirmed that the poles belong to Entergy. Entergy also claims that they will begin erecting the poles in the next few days, weather permitting.

My source did not provide an estimated date for completion. Nor did the source discuss plans for moving Entergy’s transformer near the Exxon station at US59.

But still, this is progress.

Making Way for Surface Turn Lanes

The existing Entergy power poles need to move back to make way for two surface turn lanes that will parallel the bridge over the UP railroad tracks at Loop 494.

One of the two new westbound turn lanes will let traffic turn left onto 494 and the other will let it turn right. This is a TXDoT requirement.

As you can see from the overhead clutter, this is not going to be a simple job.
Entergy has dropped new poles every few feet for several blocks down Northpark.
Entergy power poles back beyond the orange stakes on the left.

The City of Houston issued Entergy an ultimatum to have its equipment out of the way by March 8. March 8 came and went without a sign of Entergy along Northpark. Now, almost a month later, we finally have some movement that could avert a costly legal battle that had the potential to shut the expansion project down.

This is good news. The presence of the power lines in the right of way has delayed construction considerably and forced contractors to take tasks out of sequence.

Union Pacific access issues have already been worked out. So, hopefully, construction should move faster now.

Elsewhere Along Northpark

Northbound turn lanes at 59 have reached their full width and are growing longer.

Outbound traffic was confined to one lane today, causing considerable delays.
Note freshly poured concrete being finished.

As soon as the new turn lanes are complete, traffic in the old lanes will be rerouted to them. Then contractors will repave the old lanes. That process should take three months according to LHRA. Westbound traffic should expect delays.

LHRA encourages commuters to take alternative routes.  For the next phase of work, the contractor will install new storm sewer pipes and inlets along with the new concrete roadway.

Russell Palmer Intersection Closed This Weekend

Farther east, contractors have already removed a pole mounted traffic signal at the Northpark/Russell Palmer Intersection. This weekend, they will rip up the intersection to extend the box culverts in the median. The crossover will close from 9pm Friday night, April 5, to 5am Monday morning, April 8, to make way for construction.

Looking W toward US59 across Russell Palmer along Northpark. The crossover will be ripped up this weekend to extend the culverts.

Traffic was backed up for more than a mile in each direction this afternoon because of multiple lane closures as you can see above.

Construction is never easy. Pack your patience. Plan on delays. And search for alternative routes for the duration.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/2/24

2408 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Northpark Expansion Update, Still No Sign of Entergy

In the last three weeks, the Northpark expansion project has made slow, but steady progress, despite the fact that Entergy still has not moved any power poles or its transformer. For the moment, contractors seem to be working around the absentee utility issues, which have lingered for four years.

The bulk of activity has focused on the two stormwater detention basins near US59; drainage between 59 and 494; and new northbound turn lanes at 59. In addition, contractors spliced in a section of culvert by Parkwood Baptist Church near Russell-Palmer Road.

A gap was caused by a conflict with an existing water line to the church. The water line was too close to the surface. Therefore, contractors could not place the culvert deep enough. Rerouting the water line became its own small construction project, requiring engineering diagrams, approvals, estimates, change orders, permits and city inspections.

Another Week, Another Turn Lane

Most progress this week could be seen at the entries.

Looking NE from over 59 and Northpark Drive. Note fresh concrete for two additional right-hand, outbound turn lanes.
Looking east. Photos taken Wednesday afternoon 3/27/24. Outbound traffic was backed up to Russell-Palmer Road.
Note fresh concrete pour and men smoothing it. Also note culvert and connectors being stockpiled for new storm sewers.
Farther east, we can see more prep work for the drainage that must be installed before work on the surface.

Rain Slows Basin Excavation

More than three inches of rain in the week before I took these shots seems to have slowed down excavation of the detention basins at the 59 entry.

Ponding water gives hint of what is to come. Looking N over south pond.
Looking E across north pond. Both retaining walls in the north pond are finished and the concrete is curing. Backfill is already completed behind the walls.
Looking S across Northpark at south pond.
Workers are still removing the wooden forms around the last retaining wall. Fill has not yet been placed behind the wall.

Work at Russell Palmer Scheduled

Lake Houston Redevelopment Authority/TIRZ 10 has posted a lane closure notice for the Russell-Palmer crossover between the east- and westbound lanes of Northpark from 9pm on Friday, April 5th to 5am on Monday, April 8th. That’s next weekend.

Crews will remove old pole-mounted traffic signals and replace them with wire-mounted signals. This will enable contractors to continue laying culvert toward the west. Right now the pole-mounted lights are in the center the road. That area will eventually be paved over.

Pole-mounted traffic signals at Russell Palmer will be removed to make way for extension of culvert.

Here is the 3-week lookahead schedule posted on March 21.

Entergy Still MIA

Entergy was first notified of conflicts with the expansion project in 2020. They still haven’t moved their equipment, such as this transformer. At this point, they have ignored a City of Houston ultimatum for three weeks. Entergy has not returned phone calls to clarify when it plans to take action.

Transformer at Exxon Station. The box that’s putting the whole expansion project in a box.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 3/29/24

2404 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Entergy Ignores City Deadline to Move Northpark Power Lines

Today, Entergy missed yet another deadline in a long series of deadlines to move its power lines to make room for Northpark Drive expansion.

On February 6, the City of Houston sent a letter to Entergy, demanding that the company move its power lines out of the City’s right of way within 30 days. That would have given them until March 8 to comply. But as of today, March 9, 2024, not one of the poles had moved.

The City’s agent, Lake Houston Redevelopment Authority/TIRZ 10, first asked Entergy to move the poles four years ago. This is just another in a long line of disappointments that have delayed the Northpark Drive Expansion Project – driving up taxpayer costs, increasing flood risk, and snarling traffic.

Last month, Entergy refused to provide ReduceFlooding.com with a copy of its response to the City. And today, Entergy did not return a phone call explaining why the company ignored the City deadline.

Before/After Photos

Here’s how the north-side/west-bound expansion area near the UP tracks looked before the City sent its demand letter.

Entergy power poles in the way of Northpark expansion
Photo taken Jan. 13, 2024, before City sent letter to Entergy.

And here’s how the same area looked this morning. Not one pole has moved as a result of the City’s February 6 letter.

Photo taken around noon on March 9, more than 30 days after letter was sent. Nothing has moved.
Reverse angle. Looking E along Northpark at endless backups and poles still in original locations. Also taken March 9th.

As I took these photos Saturday near noon, traffic was backed up more than a mile!

Clash over Cash

In the past, Entergy asked for compensation to move its poles. But according to an LHRA spokesperson, compensation is not allowable under Texas law because the poles were in a City right of way and not covered by an easement. Thus, any payment would have constituted a “gift of public funds,” which the Texas Constitution prohibits

Entergy was, however, legally entitled to compensation for moving buried wires in an easement near the Exxon station at US59. Entergy had agreed to move them for $711,000 near Christmas last year. However…

Entergy still has not moved buried wires or a transformer near the Exxon station at US59.

…within days after the disagreement about payment for relocating the poles, Entergy’s asking price to move the underground wires mysteriously increased by half a million dollars. Simultaneously, their cost estimate went from line item to lump sum – without itemization. Since then, the asking price has increased another $200,000 without explanation.

Previous Communications with Entergy

City of Houston held Utility Coordination Meetings with Entergy on 10/8/20, 12/10/20, 01/14/21, 2/11/21, 3/11/21, 2/10/22, 3/10/22, and 4/14/22.

In addition, the City also emailed Entergy’s Utility Relocation consultant on 12/07/20, 06/21/21, 06/30/22, 07/22/22, 08/19/22, 09/20/22, 10/21/22, 01/11/23, 01/24/23, 03/03/23, 05/17/23, 07/19/23, 08/23/23, 10/16/23, 10/26/23, 12/01/23, and 12/13/24, 01/16/24.

I don’t care to speculate on the motives for Entergy’s lethargy. However, I’m pretty certain that if this goes to court, the entire project could be delayed years.

You can draw your own conclusions and point fingers where you will.

If there was ever any doubt, Entergy now knows that one of the main goals of Northpark Expansion is to provide an all-weather evacuation route for 78,000 Kingwood and Porter residents. Personally, I hate feeling like a pawn in Entergy’s game.

Posted by Bob Rehak on 3/9/24

2384 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Reminder: Northpark Phase II Input Meeting Thursday, 5-7 PM

TxDOT, the Lake Houston Redevelopment Authority (LHRA), City of Houston and Tax Increment Redevelopment Zone (TIRZ) 10 will solicit public comments at a Northpark Phase II Input Meeting, from 5-7PM Thursday, March 7 at the Kingwood Community Center.

A significant part of the effort to provide an all-weather evacuation route from Kingwood in the event of another superstorm, such as Hurricane Harvey.

Current Northpark Drive looking west toward 59. Major crossroad in center of frame is Woodland Hills Drive. Extent of project would go from bottom of frame to treeless area in distance.

Phase II will run from slightly west of the Kingwood Diversion Ditch to slightly east of Woodland Hills Drive. Part of the mile-long project falls in Montgomery County and part in Harris County. 

Purpose of Project

The purpose of the project is to address current and increasing traffic congestion. Utility and drainage features will also be upgraded.

And to improve safety for bicyclists and pedestrians, the project will include a new pedestrian underpass and 10-foot wide sidewalks that connect to the Kingwood trail system.

The TxDOT announcement provides a few of the details:

  • To improve commute times, the roadway will expand to three lanes in each direction and include turn lanes.
  • To improve safety, lane width will also increase.
  • The proposed reconstruction will include new signals at the Woodland Hills Drive and Hidden Pines Drive. 
  • To improve drainage and make Northpark passable in high water events so Kingwood residents have an all-weather evacuation route.

No Home Or Business Structures Expected to be Impacted at This Time

TxDOT does not anticipate impacting any home or business structures at this time. But strips of property that front on the roadway will need to be acquired. For additional details, see this TxDOT page or a schematic drawing on this LHRA page.

Meeting Details

LHRA and TxDOT will discuss plans for the next phase of the project. It will reach past Woodland Hills Drive. 

Thursday, March 7, 2024
from 5-7 p.m.
Kingwood Park Community Center
4102 Rustic Woods Dr.
Kingwood, TX 77345

Part of Northpark Phase II

The Northpark Expansion project will not only move traffic faster, it will create an all-weather evacuation route for 78,000 people in the Kingwood and Porter areas. During Harvey, other evacuation routes were cut off.

Pictures of Major Features

The pictures below show the way things exist now. Captions will describe the changes.

West is Up. Note Walgreens on south side of NP (top left) and Exxon on north side (top right). Three lanes of traffic will continue outbound and continue past bottom of frame inbound. Turning lanes widened and added.
Pedestrian underpass will be added between the Walmart Parking Lot (right) on the north and McDonalds/Executive Barber Shop (shown on the left). Road will be elevated as over other underpasses in Kingwood.

The underpass will improve safety for thousands of Kingwood Park High School, Kingwood Montessori, Creativity Shell, and Village Learning Center students.

Looking W along Northpark. Elevated roadway and new bridges over Bens Branch by St. Martha’s (upper right out of frame) will improve safety during high water events.

In addition, the road will be widened to at least three lanes, from US59 until approximately 1,000 feet east of Woodland Hills Drive.

Who Should Attend?

  • Any whose evacuation route was cut off during Harvey
  • Anyone who commutes along Northpark
  • Parents of Kingwood Park High School Students
  • Business owners in the Northpark Place Commercial Association
  • Anyone who flooded along Northpark, North Woodland Hills
  • Anyone who flooded downstream because of Bens Branch
  • Anyone who flooded along the Kingwood Diversion Ditch.

That’s because Northpark drainage is intricately connected with Diversion Ditch and Bens Branch Drainage.

Your input is vital to ensure the project remains consistent with your needs and community norms.

Please come. Speak now or forever hold your peace, as they say in wedding ceremonies. Many will to have to live with this project for the rest of their lives.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 3/5/24

2380 Days since Hurricane Harvey

February ’24 Northpark Expansion Update Including Lane Closures

In the past two weeks, construction activity for the Northpark expansion project has focused primarily on the ponds at US59 that will double as detention basins.

However, progress has also been made farther east. CenterPoint has been busy relocating gas lines. Contractors now have signed right-of-entry permits to UnionPacific (UP) property. And they have been busy installing a storm-sewer junction box in front of the Shell Station at Loop 494.

But the thing most people will notice this week is that two of the four outbound lanes on Northpark at 59 are now closed and will remain that way for several months.

Entry Ponds

I took all the pictures below during the last week of February 2024. For the first time, you can clearly see the outlines of both ponds. Contractors started on the north pond first. So, it is further along. But the outline of the south pond, ringed by transplanted trees, is now also clearly visible.

Looking N at S Pond
Closer shot shows three more decorative areas for plantings, one on each side of the triangle.
Men working on foundation for retaining wall around one of the landscaping areas along Northpark Drive.
Reverse angle. Looking S at N pond.
Retaining wall around area to be landscaped was just completed and contractors were removing forms for concrete.
Pipe for storm drains is being stockpiled in North Pond.

As you can see from these photos, the sides of the ponds will slope toward the middle. Maximum depth for each pond will be about 20 feet.

According to Northpark Expansion Project Manager Ralph De Leon, excavation currently is down to about 7 feet max, the approximate location of the water table. So, the ponds will eventually get almost three times deeper than they are now. That’s a lot of dirt to move!

Contractors will use the dirt to fill in over the box culverts which will go down the center of Northpark. But because of several utility conflicts, placement of the box culverts had to be put on hold.

So, contractors are storing the dirt at the Eagle Sorters Sand Mine on the West Fork. It will be transported back to Northpark when needed.

Stored dirt (center) from entry ponds at the Eagle Mine on Sorters-McClellan Road.

After Harvey, the Army Corps used the Eagle Mine as a placement area for sand and silt dredged from the San Jacinto West Fork.

Once contractors place the dirt over the culverts, they can then begin paving two additional lanes of traffic over where the center ditch used to be.

UnionPacific

Now that all the legal agreements are in place and engineering plans have been approved, work can begin around the UP tracks. It won’t happen immediately though. According to UP, rail traffic is now in its peak season. In the coming months, expect to see three types of activity.

  • Boring under the tracks to take excess stormwater from the entry ponds to the Kingwood Diversion Ditch and Bens Branch via Ditch One.
  • Placement of a one-piece concrete bed/continuous section of track over the project area with signal upgrades
  • Creation of ground-level feeder roads/turn lanes on each side of main lanes which will bridge over the tracks.
ditch one
Looking E at Ditch One, Part of Northpark Expansion Drainage. Northpark is in upper right.

Northpark Expansion Project Lane Closures

Starting yesterday, 2/26/24, two westbound lanes on Northpark at 59 closed temporarily for reconstruction during the next few months.

During the first month, the existing left turn lane and one through lane will remain open. Then traffic will switch onto the newly constructed lanes, while the other lanes are completed. The contractor will install new storm sewer pipes and inlets along with new concrete roadway.

Looking N. Demolition has already begun on two westbound lanes.
At 4 PM on Tuesday afternoon, OUTBOUND traffic on northpark was backed up past Russell-Palmer Road because of the lane closures.

Westbound traffic should expect delays and alternative routes are encouraged.

Judging by the outbound delay I saw today, I plan to avoid this bottleneck for the duration of the Northpark Expansion project.

Other Activity

The Lake Houston Redevelopment Authority (LHRA) and City Councilmember Fred Flickinger are scheduled to meet with the City Attorney on Thursday, 2/29/24, to discuss the Entergy issue. After years of discussion, the utility has not yet begun moving its power lines and transformer out of the way.

LHRA will hold a board meeting on March 14th, in part, to discuss Entergy options.

On Friday, March 15, the City, LHRA and Entergy will meet. Hopefully, they will come to an agreement that doesn’t involve legal action, which could increase costs and cause delays.

Reminder: Phase II Meeting on March 7

Also don’t forget the public input session on March 7 from 5-7 PM. LHRA and TxDOT will discuss plans for the next phase of the project. It will reach past Woodland Hills Drive.

Thursday, March 7, 2024
from 5-7 p.m.
Kingwood Park Community Center
4102 Rustic Woods Dr.
Kingwood, TX 77345

Part of Northpark Phase II

The Northpark Expansion project will not only move traffic faster, it will create an all-weather evacuation route for 78,000 people in the Kingwood and Porter areas. During Harvey, other evacuation routes were cut off.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 2/27/24

2373 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Entergy Escalates Battle with COH over Northpark

Entergy power poles sit on City of Houston (COH) rights-of-way. The company also runs underground wires in an easement near US59. Yet after years of discussion, the company still has not moved them to make room for the widening of Northpark Drive. Nor did the company comply with a request by the City to say how it would move them by a March 8th deadline.

The Northpark project is intended, in part, to create an all-weather evacuation route for 78,000 people who live in the Kingwood area. Rising floodwaters during Hurricane Harvey cut off escape routes along Hamblen Road, Kingwood Drive, and West Lake Houston Parkway.

Offending Entergy poles where Northpark will be widened for turn lanes next to the bridge over UP railroad tracks.

First Notified in 2020 and Still No Action

On 2/10/24, I detailed how Entergy was first notified about the project in 2020. Yet the company has moved nothing along Northpark to make room for construction. Groundbreaking for the project was last April and construction began last July.

So, COH put Entergy on notice. It wrote a letter, discussed in last week’s LHRA board meeting, that was dated 2/6/24. The letter requested Entergy to submit a proposed schedule and plan by last Friday detailing how it would relocate its facilities within 30 days.

That letter was dated 2/6/24, meaning the equipment should be moved and out of the way by 3/8/24.

Entergy Response Contained Only Hypothetical Schedule

ReduceFlooding.com has learned that Entergy replied to COH Public Works by last Friday as requested. But the reply did not indicate how they would move their equipment by 3/8/24. Nor did it address why Entergy could not meet the 30-day deadline or why the company has taken no action since 2020.

Instead the response suggested Entergy needed many more months, but committed to no firm deadline, according to a COH spokesperson.

Entergy and LHRA had already worked through potential conflicts with other utilities. So, resolving conflicts was not the issue.

I do not have a copy of the Entergy letter to reprint at this time; an Entergy spokesperson refused to provide it, citing potential legal concerns. As a result of the Entergy letter, LHRA has now asked to meet with the City Attorney.

Cost Escalation Possible

Continued delays are escalating the stakes. The Lake Houston Redevelopment Authority (LHRA), which is acting as an agent of the City, has costly contractual obligations to its contractors.

Given the rate of inflation, delays could also reduce the purchasing power of LHRA’s budget. In the last four years, inflation in the construction sector has totaled 15-20%. And this project costs more than $75 million. Yet the original budget included only $3 million for change orders.

A legal battle could take years to resolve. That could needlessly put lives at risk and inconvenience tens of thousands of people daily.

Entergy Motive, Next Steps Unclear

It’s not clear what Entergy – a $4 billion company in Texas alone – hopes to gain through continued delays.

In the past, Entergy asked for compensation to move its poles. But according to an LHRA spokesperson, compensation is not allowable under Texas law because the poles were in a City right of way and not covered by an easement. Thus, any payment would have constituted a “gift of public funds,” which the Texas Constitution prohibits.

Entergy was, however, legally entitled to compensation for moving buried wires in an easement near the Exxon station at US59. Entergy had agreed to move them for $711,000.

Then, within days after the disagreement about payment for relocating the poles, Entergy’s asking price to move the underground wires mysteriously increased by half a million dollars. Simultaneously, their cost estimate went from line item to lump sum – without itemization. Since then, the asking price has increased another $200,000 without explanation.

LHRA has asked to meet with the City Attorney to discuss options and next steps. More news to follow.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 2/20/2024

2365 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Excavation of Second Northpark Detention Basin Well Underway

Since last week’s post about the Northpark expansion project, contractors have made significant progress on the two stormwater detention basins at US59. Contractors are forming concrete retaining walls for both ponds. They have excavated the north pond down to the water table. And, in the south pond, contractors are mounding dirt in three locations for removal and temporary storage.

The ponds are designed to provide storage capacity for excess stormwater that might otherwise flood this crucial intersection. The intersection will provide the final link in the only all-weather evacuation route in Kingwood for 78,000 residents. During Hurricane Harvey, floodwaters blocked both Hamblen Road and Kingwood Drive.

Photos Taken on 2/16/24

I took the following photos at noon on Friday, 2/16/24..

South Pond
Looking NW across the south pond at Northpark and US59. Transplanted trees in foreground.

Contractors are temporarily storying the dirt at the Eagle sand mine on Sorters-McClellan Road. They will later retrieve it to fill in the road bed above the box culverts that are replacing the center ditch down Northpark.

From opposite direction, you can see three mounds of dirt awaiting relocation and the first concrete wall by grass.
Ground level shot shows height of pile.
North Pond

Contractors began working on the north pond first, so it is further along. However, excavation is not yet complete. They will do it in two stages. For now, they’ve excavated down to the water table. When pond liners arrive (any day now), contractors will begin the second phase and excavate even deeper.

Looking NNW at north pond. Note wet areas. They indicate level of water table.

The pipe you see lined up in the photo below will help carry excess stormwater in the ponds to Ditch One which parallels Northpark on the north. From there, it will follow gravity to Bens Branch and the Kingwood Diversion Ditch which will carry it to Lake Houston.

Looking SE at retaining wall for what will become the focal point of the North pond.
Looking S from over north pond at another retaining wall around a grove of trees.
When complete, the ponds should look like this.

CenterPoint Almost Finished Burying New Gas Line

CenterPoint had one westbound lane blocked off at noon today where it was burying a new gas line outside of the City’s easement. Reportedly, the utility is close to finished with the relocation effort. It is replacing one line that used to go down the center ditch with two, one on each side of the expanded roadbed.

As Ralph De Leon, the project manager for the Lake Houston Redevelopment Authority/TIRZ 10 said, “It’s one thing for a company to say they’ll handle something. It’s another for them to show up with giant boring machines to make it happen.” De Leon was happy with the progress they were making.

Still No News from Entergy

Entergy had until the close of business today to respond to the City of Houston’s demand for a plan to relocate its electrical services along Northpark. Project coordinators asked Entergy to move its lines in 2020. But the company has not moved anything to date.

It’s not clear at press time, whether Entergy met the City’s deadline. More next week when I learn more from City Hall.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 2/16/2024

2362 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Entergy in City’s Crosshairs, Northpark Lane Closures Announced

The Lake Houston Redevelopment Authority/TIRZ 10 (LHRA/TIRZ) Board Meeting on Thursday, Feb. 8, 2024, focused almost exclusively on issues that have delayed the Northpark expansion project. LHRA/TIRZ also announced lane closures beginning Feb. 19, 2024.

One Source of Hold Ups Resolved, Another Remains

The Northpark expansion project is designed to move more traffic faster and to create an all-weather evacuation route for 78,000 Kingwood residents in the event of another major flood, such as Hurricane Harvey.

Two major hold ups have been:

  • Reaching right-of-way agreements with Union Pacific Railroad (UP)
  • Getting utilities, such as CenterPoint and Entergy, to move gas and electric lines.

As of this week, all railroad agreements have been resolved.

Approval of the agreements by the Houston City Council should be a formality.

And CenterPoint should complete the relocation of their gas lines within a week or two.

However, Entergy has not even started relocating its equipment. They were given notice four years ago to do so.

The board discussed the possibility of condemning an existing Entergy easement within the limits of Northpark Drive right of way, but ultimately decided to defer action for one more month. The outcome is inevitable. Entergy must move its equipment. But members hope to avoid the expense and delays of litigation involved in a condemnation proceeding.

It is unclear what Entergy hopes to gain through delays. In the meantime, it is jeopardizing its public image in the most densely populated part of its Texas service area.

Entergy Must Resolve Three Problems

Entergy has:

  • Utility poles it must move out of the City’s right of way.
  • A transformer next to the Exxon station at US59 on LHRA/TIRZ property.
  • Underground electricity lines that would be paved over in several places.

The existing wood poles between 494 and the Kingwood Diversion Ditch are in the City’s right-of-way. Entergy has sought reimbursement to move those, however, they are on City property and not entitled to reimbursement.

The transformer next to the Exxon station now sits on property purchased from Exxon by the LHRA/TIRZ.

Entergy wants 52 weeks and more than a million dollars to move this transformer in the Exxon parking lot at US59 and Northpark Drive.

Regarding the third item, utilities commonly run electricity lines under streets in urban environments. But Entergy apparently does not want that in this case and has not made arrangements to move the lines.

To resolve such conflicts, LHRA agreed to pay Entergy $711,000 in July last year. But then a consultant for Entergy demanded $1.462 million – doubling the costs. LHRA balked. The extra money wasn’t and isn’t in the budget. Neither were the cost increases itemized. Said another way, Entergy didn’t break down what caused the price increases.

Itemized Costs Being Demanded

To make sure Entergy is not folding in un-reimbursable costs such as relocating poles in rights of way with allowable relocation costs for the transformer, Ralph De Leon, project manager for LHRA, said he has requested itemized costs and a schedule of values for each part of the job from Entergy.

A schedule of values includes such things as material costs as well as labor costs. For instance, one line item might read, “X people at $Y/hr times Z hours.” He also wants to see that schedule signed and stamped by a licensed PE, whose license could be revoked for falsifying information.

Entergy First Notified in 2020

The LHRA Board reviewed a history of attempts to resolve the Entergy conflict issues. They included 22 meetings/discussions between October 2020 and January 2024.

  • October 2020: Began coordinating utility impacts with Entergy and other utility companies (at 60% design stage).  Held COH utility coordination meeting.
  • December 2020: Entergy reached out and asked if there were opportunities for relocation reimbursement.  Held COH utility coordination meeting.
  • January 2021: Held COH utility coordination meeting.
  • February 2021: Held COH utility coordination meeting.
  • March 2021: Held COH utility coordination meeting.
  • June 2021: Began discussions regarding the ground transformer near Exxon gas station.  M&S had preliminary plans prepared.
  • February 2022: Held COH utility coordination meeting.
  • March 2022: Held COH utility coordination meeting.
  • April 2022: Held COH utility coordination meeting.
  • July 2022: M&S determined that their preliminary plans were incorrect and had assumed overhead line relocations for crossing over Northpark Drive.
  • August 2022: M&S noted that their utilities were in an easement and would require reimbursement from LHRA.
  • September 2022: Additional correspondence regarding reimbursement for relocations.  Teams meeting with M&S to discuss relocations.
  • October 21, 2022: M&S provided a draft cost estimate via email.  Total estimated costs for the relocations were $1,218,000.
  • January 2023: Field meeting with M&S, AT&T and Exxon representative to discuss relocations on Exxon property. M&S provided easement documentation for their utilities and continued discussion about reimbursement.  Wade Carpenter (Entergy attorney) began involvement in the conversations.
  • February 2023: Entergy attorneys reviewing the matter internally.
  • March 3, 2023: M&S noted that utility relocations in easement (primarily west of Loop 494) would cost $710,000 and would be seeking reimbursements for these relocations.  For utility relocations east of Loop 494, those would cost approx. $500,000 and Entergy deemed these costs as non-reimbursable as they are not in easement.
  • May 17, 2023: M&S confirmed that relocation costs west or Loop 494 are reimbursable ($710,000) and relocation costs east of Loop 494 ($500,00) are non-reimbursable.
  • July 19, 2023: M&S provided draft agreement for relocations with relocation costs shown to be $711,186.26.
  • August 2023: Coordination with M&S on timeline of relocations.
  • October 2023: M&S noted that they are waiting for the go ahead to send plans to construction group.
  • December 2023: Coordination with M&S regarding fiber companies attached to their poles.  M&S provided an update relocation cost estimate with a new total being $1,462,135.57.
  • January 2024: Coordination with M&S on timeline of relocations.

M&S is an Entergy consultant.

30-Day Deadline Given on Feb. 6, 2024

On February 6, 2024, Carol Haddock, Director of Houston Public Works, sent Entergy a letter giving the company 30-days to move its property. The letter included a request to submit a timeline for the relocations by Feb. 16.

Haddock’s letter parallels one sent by LHRA/TIRZ10 on Nov. 9, 2020, which the City says suffices as proper legal notification. That’s because the LHRA/TIRZ10 is acting as an agent of the City.

The City’s position is that Entergy is not moving into the City’s footprint. But the city is getting bigger and expanding into Entergy’s footprint. It appears that the City has the upper hand at the moment.

Impact of Delays

De Leon believes the City’s letter will resolve enough issues to keep crews busy for now. Next up:

  • Continuing excavation of two stormwater detention ponds at US59 and Northpark
  • Placement of box culverts in the middle ditch
  • Creation of some temporary lanes on the north side of Northpark.

However, he admits that the Entergy delays have caused problems. Instead of following the optimal critical path, his contractors are hopscotching around to keep crews busy.

If Entergy continues to delay, he could face contractual penalties, including costly demobilization.

Lane Closure Announced

LHRA/TIRZ posted this announcement on its project website. It affects westbound traffic.

“Beginning February 19th, Lake Houston Redevelopment Authority’s (LHRA’s) contractor, Harper Brothers Construction will be closing the right two lanes of westbound traffic near the Northpark/I-69 intersection.  The first month of this closure will leave two westbound lanes open – the existing left turn lane and one through lane.  The next 3 months of the closure will switch traffic onto the newly constructed lanes while construction of the existing left turn lane and through lane are completed. Westbound traffic should expect delays and alternative routes are encouraged.  For this phase of work the contractor will be installing new storm sewer pipes and inlets along with new concrete roadway.”

Two westbound lane closures beginning Feb. 19 circled in red.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 2/10/2024

2356 Days since Hurricane Harvey

Northpark Tree Transplantation Finished, Drainage Updates

Despite constant rain that brought widespread flooding to the Houston region last week, contractors finished the Northpark tree transplantation. They also made significant progress on two other parts of the road expansion project since my last update two weeks ago. I took the pictures below on 2/1/24 with one exception.

Among the highlights:

  • Dozens of trees were transplanted on the south side of Northpark at US59. The trees now form an arc around what will eventually become a decorative pond/retention basin on the south side of the intersection.
  • Excavation of a companion decorative pond/retention basin on the north side of Northpark is much farther along than in my previous report.
  • The first leg of 8-foot culvert linking the ponds with Ditch One is almost complete. The other two legs (under the railroad tracks and from US59 to Loop 494) should start within weeks.

Ideal Weather for Northpark Tree Transplantation

The cool, wet weather created ideal conditions for the transplanted trees to take root and thrive. Ralph De Leon, project manager, noted that the spacing of the trees also gives them room to spread and thrive.

Each transplanted tree has a ring around the base designed to retain supplemental water. The trees will receive extra water for two years to ensure they thrive after the shock of being transplanted.

Looking south. Transplanted trees will form a backdrop for what will soon become another decorative pond.

Pond Excavation Progress

Meanwhile, across Northpark, excavation of the first of two ponds is proceeding despite the wet weather.

Looking north. Across Northpark Drive, excavation of the pond/retention basin is already well underway.
Reverse angle of same area makes it easier to see the extent of excavation.

Excavated dirt is being stored temporarily at a sand mine on Sorters-McClellan Road. After the culverts are installed down the center of Northpark, contractors will retrieve the excavated dirt and place it over the culvert sections to form the road bed.

The pond above will go 8-12 feet deeper than you see now. The contractor is only digging down to the water table for now until: a) pond liners arrive and b) drainage connections for the ponds are complete. That’s because the contractors will have to continuously pump water as they excavate to the final depth.

Pond Landscaping Plans

That horse-shoe-shaped area on the left (above and below) will be a decorative focal point for the pond.

The trench you see above will contain a brick retaining wall that keeps the area from eroding into the ponds.

Final design of the north pond will look like this.

The peninsula will contain decorative trees, shrubs and other plantings.

The next diagram shows how the north and south ponds will closely mirror each other.

Current plans call for colorful crepe myrtles. Japanese ardisia, a ground cover, will ring the area.

Japanese ardisia, also called marlberry, is a flowering, evergreen ground cover introduced from the Far East. It is a low-growing, woody shrub that spreads laterally while growing to a height of 8-12 inches.

No Identifying Entry Signage

Unlike Kingwood Drive, where KSA owns the land behind the ponds, TXDoT owns all the land at Northpark Drive. So you will not see any prominent Kingwood identification as you do at Kingwood Drive.

Drainage Progress Between Railroad and Ditch One

The entry ponds above will drain to “Ditch One.” The ditch runs parallel to Northpark behind the businesses on the north side of the road.

Culverts will carry the water from the ponds eastward, then under Loop 494 and the railroad tracks. The culvert will then turn north and back east again behind the businesses (see red line below).

Route of culvert from entry ponds to Ditch Ditch One.
Route of drainage from north pond to Ditch One. Photo from 1/24.

The agreement with UnionPacific to tunnel under the tracks has been completed and the plans approved. However, tunneling has not yet started. UP indicated that their busy season ends after February, so boring under the tracks will likely be delayed until then for safety reasons.

Regardless, the link to Ditch One around the storage businesses above is almost complete. Culvert has already been buried parallel to the tracks and behind two storage businesses.

Looking SW. Culvert placement almost complete. Contracts use the dirt to level ground above the culvert.

Existing drainage will join the new culvert behind those businesses. Currently, contractors are working on the junction. See below.

The new 8′ pipe from the ponds is the one with the man standing inside of it.

Contractors are also working on the outfall into the ditch. Because of the expected velocity of the water, they must create concrete walls to prevent erosion of the surrounding earth that could undermine the pipe.

Start of the concrete outfall into Ditch One.
ditch one
Ditch One (center) will then carry the stormwater to the Kingwood Diversion Ditch and Bens Branch.

Ditch One will eventually be widened to handle the increased flow. Connecting the ponds at US59 to the link under the railroad tracks should start in the next few weeks.

The project requires the additional retention and drainage capacity shown above to handle runoff from the extra lanes of traffic.

In front of the businesses shown above, Northpark will eventually expand to 10 lanes from the current four. Six will carry traffic on a bridge over the railroad and Loop 494. Four turn lanes will remain at ground level – two on each side of the bridge. The two will let traffic turn north or south onto 494 from each direction.

Built to TXDoT Highway Standards

This entire project is being built to TXDoT highway standards. Those standards exceed normal neighborhood street standards. You would expect nothing less for what will eventually become a critical evacuation route for 78,000 people.

  • Lanes will be 12-feet wide instead of 10 to safely carry traffic at higher speeds.
  • Concrete will be much thicker than normal to carry heavier loads without cracking.
  • Storm drains will be sized to carry the volume of runoff you would expect from highways. The wider inlets will help avoid water flooding roads during intense rainfalls.

Greater Safety at Rail Crossing/Loop 494

Safety will also improve at the railroad crossing.

  • A bridge will carry most traffic over the railroad.
  • The entire train track at Northpark will have a one-piece steel and concrete foundation. That will reduce the chance of track shifting or dipping and causing a derailment.
  • Pedestrian/bicycle crossings will have “escape gates” in case people get caught on tracks when trains come through.

However, installation of those safety improvements will cause some inconvenience. To install that one-piece steel and concrete foundation, the railroad will shut down for three days. That will require closing off Northpark for three days also.

Originally, project managers hoped to have four lanes open at all times for the duration of the project. So this is a change.

All in all, a 3-day shutdown is small price to pay for a great improvement in safety.

The road closure is still months away.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 2/2/24

2348 Days since Hurricane Harvey

First Northpark Entry Pond Taking Shape

One week after contractors began digging the first Northpark entry pond, you can see a broad area that has already been excavated.

Looking S toward Northpark and US59 on 1/21/24.

The decorative pond, when complete, will double as a detention basin to temporarily store extra runoff from the newly widened Northpark roadbed and US59 feeder road during heavy storms.

Stormwater will collect between the pond’s normal water level and the surface of the ground, then drain slowly at a rate (constrained by the outfall pipe) that drainage ditches can safely handle.

Stormwater from 59 feeder road as well as Northpark will flow into ponds.

Why Ponds?

Traffic heading to 59 during an evacuation must not be trapped behind a flooded intersection at the freeway. Likewise, overflowing ditches must not flood homes and businesses in the area. Hence, the need for stormwater detention capacity.

The basins/ponds will also serve as decorative attractions that welcome people to Kingwood, exactly like they do at Kingwood Drive.

Contractors will build one pond on each side Northpark. Culvert that runs under Northpark will connect the ponds and carry overflow from the south pond to north pond.

Overflow from the ponds will then drain east toward Loop 494, under the railroad tracks, and behind the businesses on the north side of Northpark.

What to Expect in Coming Weeks

In coming weeks, contractors will complete the outline of the ponds. But, for now, they will only excavate down to the water table, according to project manager Ralph De Leon. Before contractors can go lower, they need a place to pump water as they dig. That means finishing the drainage-culvert connection(s) to Ditch One first. Ditch One leads to the Kingwood Diversion Ditch and Bens Branch farther east.

So the next steps will be:

  1. Place culvert in the easement between the north entry pond and Loop 494.
  2. Place culvert east of the railroad tracks that will connect to Ditch One.
  3. Connect both segments by tunneling under 494 and the UP Railroad tracks.

A satellite image clearly shows the entire route.

Northpark Drive drainage improvements

Here’s what it route looks like from a couple hundred feet.

Stormwater will travel from the entry ponds in the background at 59 via culvert in the easement (middle of the frame).
Then, the storm sewer will go under 494 (left) and the UP tracks before turning left and going behind two storage facilities.

In the pictures above and below, note the culvert already pre-positioned.

Behind Public Storage and Duncan Donuts, the storm drains will empty into Ditch One (top middle). Photo Oct. 2023.
Looking west. Water will flow through ditch toward the foreground behind Calvary Christian Fellowship (lower left).
Looking opposite direction from same location. Ditch One flows toward St. Martha Catholic Church (top center).

Just before reaching St. Martha Catholic Church, the water will turn right and cross under Northpark in either Bens Branch or the Kingwood Diversion Ditch.

Building from the Ground Up

De Leon emphasized that all underground work (drainage and utilities) must be completed before any road building can begin. The underground work still entails:

  • Building a second CenterPoint gas line on the north side of Northpark. CenterPoint will also build two connections to the first CenterPoint gas line on the south side. The first connection will be at Russell-Palmer Road and the second near Loop 494.
  • Relocating Entergy power lines and transformer.
  • Moving fiber-optic lines from internet and telecom companies.
  • Relocating a water line to Parkwood Baptist Church.
  • Finishing tree transplantation.
  • Tunneling storm drains under the railroad.

All of the above require permissions, permits and inter-local agreements with the City, Lake Houston Redevelopment Authority/TIRZ, utilities, and UP Railroad).

Three-Day Road Closure

At some future point, after those details are worked out, Northpark will have to close for three days. Previously, the plan had been to keep at least two lanes of traffic open in both directions at all times. So this represents a change. But any closure is still months away.

The closure will happen during construction of turn lanes under the bridge that will go over the UP Railroad Tracks.

UP intends to install a one-piece, 100-foot-long section of track and concrete that spans all ten lanes of traffic. The one-piece construction will involve multiple giant cranes. It will also mean shutting down rail traffic. But the final result will be a more stable track.

However, the one-piece construction also means alternate-side road closures are no longer a viable strategy.

Ideal Conditions for Tree Transplantation

The cool, wet weather during the winter months when trees are dormant makes ideal conditions for moving them. The trees should have a much higher survival rate now than during the drought and heat, as we experienced last summer.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 1/13/24

2336 Days since Hurricane Harvey