Tag Archive for: Northpark expansion

Excavation of Northpark Detention Basins Starts

Excavation of the decorative ponds that will double as Northpark detention basins at US59 began this week.

Contractors will stockpile the dirt in two places for now: behind Duncan Donuts and at a sand mine on Sorters-McClellan Road several blocks to the west. Contractors will use the dirt later to level the road surface and build access ramps for the bridge over the Union-Pacific Railroad tracks.

In other Northpark-expansion news this week, Entergy still has not started moving its utility poles and transformer.

However, CenterPoint has almost finished relocating its gas line under the road’s center drainage ditch to the south side of the road. CenterPoint also surveyed the north side of the street to place a second line there.

Finally, the Lake Houston Redevelopment Authority (LHRA) is close to finalizing a drainage agreement with the Union-Pacific Railroad. For more details, see below.

Beginning of Entry Pond Excavation

Contractors will excavate the entry ponds/detention basins in several stages. For now, they will excavate down to the water table. Later, they will excavate below the water table, pumping water into new storm sewers as they dig.

Then they will place a liner at the bottom of each pond.

Finally, the ponds will be filled to the level of the storm sewers with a combination of well- and rainwater. But that will come much later.

The distance between the top of water in the ponds and the surface of the ground will retain stormwater to help prevent flooding of the intersection during heavy rains.

The photos below were all taken on 1/13/2024.

Looking at beginning of excavation of north pond. US59 and feeder on left, Northpark on right.
Looking west toward US59 bridge. These contractors appear to be defining the margins of the pond. Note stakes.
Excavated dirt on right waiting for shipment to a stockpile. Note storm drain on left and the wet earth that indicates proximity to water table.

Bens Branch, which crosses under 59 farther north, often overflows and backs up toward the Northpark intersection. The pipe above will carry water into the pond instead, thus reducing flood risk.

Start of one stockpile behind Duncan Donuts and Public Storage.

Where the Dirt Will Go

The stockpiled dirt will eventually be used to level the roadway over box culverts (when installation is complete) and also to build up ramps for the bridge over the railroad tracks.

When contractors finish placing box culverts, the stockpiled dirt will help level the center of the roadway, which will contain two additional lanes of traffic – one going each direction.

The bed must be raised to the level of the manhole shown above.
Looking west toward 59. Power lines belong to Entergy. They must be moved back to approximately where the fire hydrant is now. Yellow/green flags indicate route of new CenterPoint gas line.

Moving the utility poles back will create room for turn lanes next to the bridge over the rail tracks. The turn lanes must be at ground level for traffic turning north or south onto Loop 494.

Project managers first asked Entergy to move its power lines 2020. The utility still has taken no action. Ditto for the transformer below located near the Exxon station at 59.

Entergy transformer in red circle must also be moved back to make way for additional turn lanes.

An Entergy consultant claimed the company needed 50 weeks to move the transformer above.

The City is reportedly considering legal action against Entergy because of construction delays.

Meanwhile, Entergy continues to promote its social responsibility, even as it holds up construction of the only all-weather evacuation route for 78,000 people.

Railroad Agreement Should Be Resolved by End of January

In the good-news department, the last remaining issue with UP will hopefully be resolved within a couple weeks, according to project manager Ralph De Leon. The Lake Houston Redevelopment Authority sought permission to tunnel stormwater under the UP tracks to Ditch One. The railroad company required no more than a quarter-inch displacement of the tracks. Engineers figured out way to do it by splitting the flow from one pipe through two smaller pipes.

The Agreement covers both the aerial easement over UP’s tracks for the bridge and the railroad’s acceptance of the Construction Plans. The stormwater drainage pipes under the tracks held up UP’s final approval of the plans. Now that that has been resolved, UPRR is ready to accept the plans.  

Approval by the City will occur in the form of an Ordinance adopted by City Council.

The City of Houston contributed $15.4 million to the Northpark Project. Here is the contract between the City and Lake Houston Redevelopment Authority.

For More Information

De Leon said, “Once the UP agreement is signed, and CenterPoint and Entergy relocate their utilities, we can start building roads. Residents should then see a significant increase in in construction activity.”

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 1/13/24

2328 Days since Hurricane Harvey

Northpark Tree Moving Starts; Pond Excavation Next

The Northpark Drive expansion project understandably slowed during the holidays. But Northpark tree moving started in earnest this week. Contractors have returned and started moving trees to clear the areas where two detention ponds will be excavated at 59.

In other news:

  • Concrete culvert is being stockpiled to carry stormwater from the ponds to the Kingwood Diversion Ditch via Ditch One behind the businesses on the north side of Northpark.
  • TXDoT has found a hazardous waste site for oil-contaminated dirt discovered during clearing for the north pond. Relocation of the waste should be complete by the end of January, if not sooner.
  • CenterPoint is almost finished moving its gas line that used to run down the center of Northpark. That will allow resumption of culvert placement in the center ditch.
  • Entergy is still delaying parts of the project by refusing to move its electric lines and transformers unless the Lake Houston Redevelopment Authority pays them $1.4 million. The amount originally demanded – $711,000 – mysteriously doubled during the holidays.

To learn more about each of these items, see below.

Moving Day Arrives for Trees

Before excavation can begin on the two stormwater detention ponds at US59, numerous trees must be transplanted.

This week, Northpark tree moving began in earnest on the south side of Northpark. Trees are being moved from the center of the entry to the periphery to form a green backdrop that says “Kingwood.” They will frame a decorative pond that doubles as a stormwater detention basin.

The giant machine shown below scoops out dirt and places it to the side. Then it scoops out a tree and drops it into the hole.

To see the complete sequence, view this post from an earlier press conference.
This shot shows the beginnings of the tree backdrop around what will become a pond.

But the job isn’t done yet. More trees remain. Heavy rain earlier this week is still slowing transplantation.

Looking south across Northpark. Wide shot shows where pond will go and trees yet to be transplanted.

Contaminated Soil Being Relocated

Before Thanksgiving, contractors struck oil in the soil on the north side of Northpark at 59. Someone dumped it years or even decades ago. To prevent further leeching into the groundwater, contractors excavated and isolated it with plastic sheeting.

Since then, TXDoT located a suitable permanent site for the contaminated soil and contractor will soon begin moving it.

Looking south toward Northpark over the contaminated soil.

All contaminated soil should be removed by end of January at the latest, according to Ralph De Leon, project manager.

The ponds on both sides of Northpark will keep the US59 intersection from flooding during heavy rains, helping to ensure that the new all-weather evacuation route for 70,000 people remains passable during extreme storms.

More Box Culvert Stockpiled to Reroute Drainage

Excess water from the ponds will be routed east toward the Kingwood Diversion Ditch instead of north along 59 toward Bens Branch – a shorter route.

Why? During heavy rains drainage to Bens Branch where it crosses under 59 can back up all the way to the Northpark intersection. Re-routing it will avoid flooding along the vital 59 corridor AND Northpark without adding to the burden on the Diversion Ditch.

Culvert stockpiled between railroad tracks and Ditch One.
Northpark Drive drainage improvements
Alternate route for stormwater from entry ponds to Kingwood Diversion Ditch and/or Bens Branch.

CenterPoint Gas Line Relocation

As of this afternoon, CenterPoint had reached Russell-Palmer Road with its new gas line. It is moving the line from the median to make room for 6×8 foot concrete box culverts. The culverts will allow the Redevelopment Authority to create two new lanes inside the old lanes, rather than outside, which would be more expensive because of the need for property acquisition.

When the last quarter mile is finished to the diversion ditch, culvert placement in the ditch will resume. It was temporarily halted earlier when contractors discovered serveral conflicts with the gas line; it was higher than expected. That interfered with a consistent gradient for the drainage.

Entergy Conflict Resolution

Before Christmas, the Redevelopment Authority had agreed to pay Entergy $711,000 to move a transformer and some power lines. After Christmas, Entergy doubled the price to $1.4 million. It’s one more setback in a years-long struggle with the corporate giant. More news to follow when and if a resolution becomes clear. (Editorial comment: Entergy does not seem to share 70,000 Kingwood residents’ sense of urgency about the need for an all-weather evacuation route.)

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 1/4/2024

2319 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Northpark Expansion Presses Forward While Fighting Entergy Obstacle

In the last two weeks, progress on the Northpark expansion project has slowed somewhat but is still pressing forward. Illegally dumped oil, utility surprises, and a traffic signal have all created bumps in the road, so to speak.

But there’s also good news to report: the Lake Houston Redevelopment Authority (LHRA) wired a $53,000 payment for a Union-Pacific (UP) easement to the railroad. That clears the way for construction of ground-level turn lanes near where the bridge over the UP tracks will go.

Let’s look at what’s happened in the last two weeks and what’s coming up.

Contaminated Soil Isolated

Two weeks ago while preparing to work on a detention basin on the north side of Northpark at US59, contractors encountered oil dumped years ago. That forced crews to see how far the pollution extended. They excavated a wide area and isolated contaminated dirt.

All contaminated soil was isolated with plastic sheeting before the rains last week.

Contractors are now getting ready to remove the contaminated soil to a safe site for permanent disposal where contaminants can’t leach into groundwater. While that cost time, it will make the site safer in the long run.

Looking west at area where north retention basin will be excavated.

Entergy Estimated It Would Take 50 Weeks to Move a Transformer

In other news, an Entergy consultant in The Woodlands has tried to hold the Northpark expansion project up for two years. He wanted an extra half million dollars (above and beyond the $700,000 already budgeted) to move some power lines and a transformer near the Exxon station at US59.

The consultant demanded 50 weeks to move the ground-mounted transformer alone. His motive was unclear. Was he using a not-so-subtle form of extortion to make himself look better in his client’s eyes?

It’s also unclear whether Entergy, a company that trumpets its social responsibility, knew about the consultant’s demands. Entergy is a Fortune 500 company with 3 million customers in Arkansas, Louisiana, Mississippi and Texas. 

The Northpark Expansion project is designed to create an all-weather evacuation route for 70,000 people. One would think that a socially minded company with a $4.4 billion rate base (in Texas alone) could move a transformer in less than a year if it really wanted to.

Ralph De Leon, project manager for the Northpark expansion project, finally managed to bypass the consultant and is now working directly with Entergy executives in Beaumont.

Lawyers for LHRA have negotiated a settlement in lieu of condemnation. Hopefully the Entergy issue will resolve amicably before the end of the year. The agreement will be on the December 14, LHRA board meeting agenda.

Traffic Light Alternative

At Russell-Palmer, contractors are still waiting for the City of Houston to change a pole mounted traffic signal to a wire-mounted one. That will enable them to continue installing box culverts when Centerpoint returns to finish moving its gas line. Centerpoint crews were MIA during the holidays.

Traffic signal in median at Northpark and Russell Palmer Road must be replaced with wire-mounted system for now.

Replacement of Ditch with Box Culverts

The City of Houston has approved the plan to detour a waterline across Northpark to the Parkwood Baptist Church (see upper right corner of photo above). The original contractors didn’t install the waterline deep enough. That created a conflict with the 6’x8′ box culverts being installed in the median. But the water-line detour should be resolved soon.

The culverts will replace the ditch in the median so that the road can be expanded inward, adding an extra lane of traffic in each direction.

Looking west in opposite direction from over Russell Palmer.

Plan for Next Three Weeks

Construction is always difficult, even in the best of times. The holidays make it even more so. Weather permitting, here are the priorities for the next three weeks.

  • Continue burying reinforced culvert at Outfall B depending on weather 
  • Alternatively, continue working on 8″ waterline on south side of Northpark between railroad tracks and King’s Mill
  • Install 12″ waterline in front of the Chick-Fil-A.
  • Complete filling in around new sidewalks west of US59
  • Mobilize on December 4th to begin tree relocation throughout the month of December.
  • Continued Retention Pond Excavation on north side at US59.

For More Information

For more information about the project including construction plans, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 12/3/23

2287 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

CoH Removing Sediment under Northpark Bridges, More Good News on Northpark Expansion

To help accommodate the expansion of Northpark Drive and the Kingwood Diversion Ditch, City of Houston (CoH) contractors are cleaning sediment from under the Northpark Bridges. This effort will eliminate a constriction in the Diversion Ditch that backed stormwater up, forcing it into Bens Branch, flooding people, businesses and schools downstream.

Separately, Week 2 of Northpark Drive expansion has seen other breakthroughs farther west.

  • Cleaning and expansion of the median ditch have reached almost to the UnionPacific (UP) railroad tracks that parallel Loop 494.
  • CoH and UP are also reaching agreements – at long last – that will let contractors move forward with construction at a much faster rate.

See more details and photos below.

Photos of Bridge Clean-out Taken 8/8/23

Looking east toward Woodland Hills at sediment removal project under Northpark bridges.
Side view looking SE toward North Woodland Hills shows more of work under bridge.
Looking west across Diversion Ditch and sediment removal project toward Russell Palmer. Photo by Father TJ Dolce of St. Martha Catholic Church.

8/8/23 Photos of Northpark Ditch Clean-out

Looking East from Northpark median at Public Storage. Note Duncan Donuts on left.
Reverse angle looking West shows remaining distance to UP tracks and Loop 494 at intersection.

The ditch clean-out will make room for 5′ x 7′ box culverts like those you see below. Workers have now buried all of the round concrete pipe stockpiled last week. They have also cut through concrete in the crossover between the fireworks stand and Flowers of Kingwood.

Steel cofferdam prevents wall collapse, protects workers in ditch.

The “step-down” from the box culverts to the round concrete pipe (now buried) will provide in-line stormwater detention during heavy rains that helps reduce flood potential in the receiving ditch, i.e., the Diversion Ditch.

UP and CoH Near Agreement on Access Rights

According to Ralph De Leon, project manager for the Lake Houston Redevelopment Authority and TIRZ 10, CoH and UP have come to terms on one agreement and are close to finalizing a second.

The first covers covers maintenance and construction. It will let contractors drill under the railroad tracks to address utility issues. Cost: $2.2 million.

The second agreement covers vertical and horizontal easements. Cost: under $200 thousand. The easements will let contractors build a bridge and access roads over the tracks.

However, it will also require the TIRZ to purchase two additional tracts of land north and south of Northpark at the railroad tracks.

Resident Reacts to Sediment Removal in Diversion Ditch

Flood activist and Kingwood resident Chris Bloch lauded the CoH sediment removal under the Northpark Bridge. He called it, “Great news for Kingwood!” 

“Removal of the sediment under the Northpark bridges will substantially recover conveyance capacity of the Diversion Ditch,” he added. “When the water level in the Diversion Ditch touches the bottom of the Northpark bridges, the bridge acts as a dam and water levels upstream rise rapidly.”  That forces water into Bens Branch, threatening homes and businesses on either side of it.

Remembering Stan Sarman

Bloch worked with former TIRZ president Stan Sarman, who was also an engineer, to approach Mayor Pro Tem Dave Martin and CoH about the need for this project. They agreed that sediment removal from the Diversion Ditch under the Northpark Bridges would help reduce flood risk in Woodland Hills, Hunters Ridge, Bear Branch and Kings Forest.  

Martin’s office arranged for the purchase order to get this project done.

Bloch took video during Imelda and shared it with Sarman, who had the original drawings of the bridge and channel from 1972. He is quick to give credit to Sarman who has since passed away. “I am not sure most Kingwood residents appreciate all Sarman did for Kingwood,” said Bloch.

This project and the repair of the channel under the Tree Lane Bridge are valued at nearly $1 million dollars.

Up Next

The LHRA/TIRZ are now providing weekly updates of construction activity so you can see what’s coming next.

Come back soon for more updates. The Lake Houston Redevelopment Authority will hold a public board meeting Thursday at 8 a.m. at the Kingwood Community Center to discuss this and other business.

Posted by Bob Rehak on 8/9/2023

2171 Days since Hurricane Harvey

Deeper Dive into Northpark Expansion, Drainage Plans

On 7/27/23, I interviewed Ralph De Leon, Northpark project coordinator for the Lake Houston Redevelopment Authority (TIRZ 10) and Kevin Perkins, a project manager for HNTB, one of the contractors on the job. The discussion covered both the eastern and western phases of the project from Woodland Hills Drive on the east to US59 and beyond on the west.

Since Tuesday, the contractors have made visible progress. Let’s cover that first. Then I’ll cover some surprising facts I learned about the project, including flood-mitigation plans; why the project has taken so long; how it will expand to 10 lanes near the railroad and Loop 494; parts of the project that will be elevated; bridge reconstruction; Atlas-14 conflicts; and more.

Box Culverts Arrive

By mid-day today, contractors had box culverts stacked several blocks in the median between Russell-Palmer Road and Flowers of Kingwood. They also had three excavators working Thursday, compared to one on Tuesday. And they were cutting concrete in the cross-overs.

Looking west from the diversion ditch (foreground). Only the 66″ round concrete pipe by the first excavator was there on Tuesday.
Looking east down the Northpark Drive median in opposite direction. Those rectangular culverts measure 6’x8′.
Note men cutting concrete in the median between Flowers of Kingwood (upper left) and the fireworks stand (out of frame, lower right).

The 6×8 box culverts stacked in the distance will extend under the cross-over and connect to the round concrete pipe using the junction box stacked in front of the four round pipes. See below.

Box culverts were stacked up to the red rib truck in the background.

The box culverts will convey 35 square feet of stormwater compared to slightly fewer square feet for the round pipe.

That “step-down” as stormwater moves toward the diversion ditch will provide inline detention.

Also note that the existing culverts under the crossovers provide even less conveyance/storage than the new pipe. The old pipes were much smaller and frequently become clogged with weeds and grass due to long maintenance intervals.

According to Perkins, the new pipe/culvert solution offers less friction from end-to-end. The pipes shouldn’t become clogged like the old pipes did because grass and weeds won’t grow in them. Also, their consistent dimensions under the cross-overs should let more water pass through faster.

To make sure water can get into the culverts quickly during heavy rains, contractors will use extra large inlets, similar in size to those used on freeways.

Why Project Has Taken So Long

De Leon and Perkins discussed approval delays at length, mostly related to multiple groups giving input and approvals.

  • The project goes into, out of and back into the City of Houston.
  • It straddles two counties, each with different leadership and regulations.
  • A TIRZ, several MUDs, homeowner associations, commercial associations, KSA and Lone Star College are also involved.
  • Harris County Flood Control District is reviewing all the plans and approvals.
  • TxDoT has final say over design criteria.
  • Funding will come from State, Federal, and local authorities.
  • The Union Pacific (UP) Railroad has had multiple changes in leadership since the project started.
  • Gaining utility easements and rights of way has taken much longer than expected. For instance, Entergy wants 50 months to move a SINGLE transformer, almost half again as long as it will take to build the ENTIRE bridge over 494 and the UP railroad tracks.

Getting all those dominos to line up has challenged everyone involved.

Project Will Expand to 10 Lanes Near Loop 494

Where the western phase of the project crosses Loop 494 and the UP railroad tracks, traffic surveys indicate that 80% of the traffic will go over the bridge. Regardless, TxDoT requires two lanes of feeder road in each direction to handle local traffic not going over the bridge. Six lanes of bridge and four lanes of feeder will require some property acquisition still to be completed. Not all of the expansion will fit over the center ditch.

Pedestrian Underpass

The eastern phase of the project will contain a pedestrian underpass similar to others found throughout Kingwood. Engineers hope to keep water out by making the entrances higher than surrounding areas so water drains away. The tunnel will be 10 feet wide to accommodate special extra-wide wheelchairs for people with curved spines. Ten feet will accommodate two such wheelchairs moving in opposite directions.

Elevated Roadway with Cheek Walls

In certain areas that experience repetitive flooding, especially east of the drainage ditch where Bens Branch cuts under Northpark Drive, the road will be elevated. Feathering out the bed toward the sides would require killing hundreds, if not thousands of trees. So instead, contractors will elevate the road using “cheek walls.” Highway 59 makes extensive use of cheek walls for the same reason – to conserve space and allow trees to grow.

Two 10-Foot Sidewalks to Lone Star College

West of 59, contractors will build two 10-foot sidewalks along Rock Creek south of Northpark. The sidewalks will help cash-starved Lone Star College students ride bicycles to class when weather permits. Katherine Perrson, now retired head of the college, made the request.

Leaving Room for Diversion Ditch Expansion

The City has hired a contractor called NBG Constructors to clean out the diversion ditch under both Northpark Drive bridges and return the channel to its original as-designed capacity. Over the years, sedimentation has constricted the flow as you can see below.

Note accumulated sediment constricting flow under bridge.

Eventually, Harris County will widen the diversion ditch. HCFCD rated it one of the two most important projects in Kingwood. As part of the Northpark Expansion project, both bridges will be rebuilt, but with enough width to accommodate eventual expansion of the ditch.

Meets Harris County Atlas-14 Requirements

When complete, the project will meet Harris County Atlas-14 requirements for 77339 which are more stringent (about 40% higher) than Montgomery County’s. That’s because virtually all of the water associated with this project will drain into Harris county. MoCo standards are lower because Montgomery averages requirements across the entire county. Rainfall drops off with distance from the Gulf.

Detention Basins and 59 Entry

To reduce the chance of flooding near 59, contractors will build two detention basins on either side of Northpark at 59. They will connect with each other underground and also connect with another basin and channel north of Northpark via an 8 foot pipe.

Timetable

All this won’t happen overnight. De Leon is working on updating the timetable and will post it with a new project website that gives Kingwood and Porter residents weekly or bi-weekly updates. More news to follow, including a deeper dive into the drainage analysis and how some water will be diverted around Northpark.

Posted by Bob Rehak on 7/27/23