Update on Ben’s Branch and Other Drainage Repair Projects from Flood Control District

In March of this year, Harris County Flood Control District (HCFCD) announced a project to excavate more than a mile of Ben’s Branch in Kingwood. HCFCD expects to remove approximately 8,600 dump-truck loads of sediment that clog the creek between Kingwood Drive and the San Jacinto River.

Bens Branch cuts diagonally through the heart of Kingwood. Project area circled.

Current Conditions on Ben’s Branch

During Harvey, hundreds of homes and businesses flooded near the creek. It contributed to flooding in Kings Forest, Town Center, The Enclave, Kings Harbor, and Kingwood Greens. The project area affects all of those subdivisions, plus Kingwood Village Estates where 12 seniors died, either as a result of injuries sustained during evacuation or the subsequent stress of losing their homes.

Harris County Surveying Crew in Ben’s Branch just west of West Lake Houston Parkway and south of the Kingwood Library.
More sediment buildups just east of West Lake Houston Parkway on Ben’s Branch, south of the Enclave and north of the YMCA.

Next Steps for Ben’s Branch

Since the announcement of the project to restore conveyance on Ben’s Branch, HCFCD has been busy negotiating access rights to the stream. The District has also finalized construction plans and bidding specs. According to Beth Walters, a flood control district employee who lives in Kingwood, here’s what to expect next and when.

“We plan to advertise the project five times,” says Walters, “to attract bidders. Ads will appear through June 15.” She also said HCFCD held a mandatory pre-bid meeting for all interested parties.

Eleven potential bidders attended. “Hopefully, we’ll get some good unit prices,” said Jason Brock, the manager of HCFCD’s maintenance engineering department.

Project Award by July 9, Construction to Start Immediately

HCFCD expects to open bids on June 17th and award the project at the commissioner’s court meeting on July 9. Mark your calendars!

The winning bidder will have 250 calendar days, per the contract, to finish the job. That means the project should be finished by next February or March.

Status of Other Kingwood Projects

Yesterday, Commissioners Court approved a Kingwood Area Drainage Assessment Plan. The objectives of the plan are to:

  • Dermine the current conveyance of all creeks and ditches in the Kingwood area
  • Measure that against current and projected needs
  • Make recommendations for improvements.

But first, HCFCD must select a consultant. The project should kick off this summer after consultant selection.

In the meantime, HCFCD is repairing damage due to Harvey at several locations.

1. Project ID G103-38-00-X020 consists of repairs at three (3) locations along G103-38-00:

a.    Site 5416 consists of slope failure repair, including excavation of sloughed materials, disposal of unsuitable materials, and rebuilding side slopes. The Site is located approximately 1900 feet north of Walnut Ln.

b.    Site 5680 consists of erosion repair and pipe replacement including reestablishing channel toelines, and rebuilding side slopes. The Site is located approximately 250 feet south of Walnut Ln.

c.    Site 5682 consists of erosion repair including excavation of sloughed material, reestablishing channel toelines, and rebuilding side slopes. The Site is located approximately 500 feet northwest of Deer Ridge Estates Blvd.

2. Project ID G103-38-01-X010 consists of repairs at one (1) location along G103-38-01:

a.    Site 3228 consists of slope erosion repair including rebuilding side slopes. The Site is located approximately 70 feet west of Chestnut Ridge Rd.

3. Project ID G103-41-00-X008 consists of repairs at two (2) locations along G103-41-00:

a.    Site 5622 consists of slope erosion repair including lishing channel toelines, excavation of soils to reestablish channel width, and rebuilding side slopes. The Site is located approximately 1350 feet south of Kingwood Dr.

b.    Site 5622A consists of channel scour and slope repair including filling scouring with a well graded mix, reestablishment of channel toelines, and rebuilding side slopes. The Site is located approximately 1600 feet south of Kingwood Dr. 

Helpful HCFCD Links

This page on the HCFCD web site explains their numbering system.

Some of these repairs may already be complete. This interactive map shows the status of active projects.

You can read more about the Harvey Repair Program here: https://www.hcfcd.org/press-room/current-news/2018/04/hcfcd-begins-drive-on-84-million-hurricane-repair-program/

For more specific information about Flood Control projects in the Kingwood area, including vegetation management, click here.

Posted by Bob Rehak on June 5, 2019

645 Days after Hurricane Harvey

Harris County Commissioners Approve Kingwood Drainage Assessment, But Not Without Battle Over Equity

Harris County commissioners approved a Kingwood Drainage Assessment Project Tuesday, but not before a 50-minute discussion of equity that had commissioners shaking fists at each other at one point.

Cagle Versus Ellis with Kingwood in Middle

The battle involved Precinct 4 Commissioner Jack Cagle and Precinct 1 Commissioner Rodney Ellis. The flashpoint concerned Item 2a14 on the agenda. It read:

The Lake Houston Redevelopment Authority and TIRZ #10 wanted to PAY Harris County Flood Control $100,000 to manage and conduct a study of Kingwood drainage capacity. The study would have supplemented a Flood Control District study approved as part of last year’s flood bond. The objective of Item 14: to determine possible improvements to channels and mitigation basins to reduce flooding potential. Click here to read the scope document that Flood Control asked Commissioners to approve.

Illustration showing some of the ditches/streams included in the study including the reach of Taylor Gulley, along which Chris Kalman reported many blockages last week.

Commissioner Ellis invited four “equity coalition” representatives to the meeting. Each gave speeches, using the drainage assessment project as an example to show how poorer parts of the county were being discriminated against. During and after the speakers, Commissioner Cagle, whose Precinct 4 includes Kingwood, got into heated exchanges with Ellis.

The Equity Flap Revisited

The equity flap first surfaced in February. It concerned prioritization of projects in the 2018 bond proposal.

Section 14 (g) of the approved bond language states: “Since flooding issues do not respect jurisdictional or political boundaries, the Commissioners Court shall provide a process for the equitable expenditure of funds, recognizing that project selection may have been affected in the past and may continue to be affected by eligibility requirements for matching Federal, State, and other local government funds.”

Kingwood was among the hardest hit areas in Harris County. As the flood bond language was being finalized, Lake Houston area leaders argued to include language that said all areas would receive their fair share of funds to prevent reverse discrimination. Historically, the Lake Houston area had received no flood mitigation dollars.

Greater Houston Flood Mitigation Report Misrepresented

The following figures and chart are taken from the Greater Houston Flood Mitigation Consortium’s April, 2018 report on Hurricane Harvey. Ironically, one of the activists speaking for Ellis used this report to suggest that poorer neighborhoods have suffered historical discrimination. The report does not support her argument relative to Kingwood at least, as the figures below show.

From the Greater Houston Flood Mitigation Consortiums April, 2018 report on Hurricane Harvey

The San Jacinto watershed, says the Consortium, contains 3% of the region’s population, gets 0% of the mitigation budget, and had 14% of the region’s damages.

Contrast that with Sims Bayou and Braes Bayou, both of which run through Commissioner Ellis’ Precinct 1. Those watersheds have 20% of the region’s population, get 42% of the mitigation budget, and had about 20% of the damages.

The Flood Control District’s own Federal report from March of 2018, shows a map of Harris County with Federal partnership projects everywhere … except the Lake Houston area.

Of the three other speakers, one evidently did not think Kingwood had apartments. Another complained that his community was still recovering (as if we weren’t).

So much for equity! The fact-defying arguments of Mr. Ellis and his surrogates do no one any good; they serve only to drive wedges between people who should be working together to triage a battlefield.

See the Video for Yourself: Blow by Blow

To see the video of the meeting, go to this Commissioner’s Court page, select Item 1, Part 2 of 2 from the menu, then fast forward to 30 minutes. That’s where this discussion starts with the first speaker. If you don’t have an hour, see these other key time markers:

  • 34 minutes: In response to the first speaker, Cagle and Ellis debate who has really gotten the lion’s share of spending.
  • 38 minutes: The second activist begins talking.
  • 42 minutes: Another activist complains that his community still has not recovered and therefore should go first.
  • 48 minutes: A fourth activist quotes the Greater Houston Flood Mitigation Consortium Harvey report. She overlooks the fact that Kingwood is part of the San Jacinto Watershed, which historically has received ZERO mitigation dollars.
  • 51 minutes: She complains that by counting structures, not people, the government discriminates against neighborhoods with multi-family housing. She ignores the fact that at least five major apartment complexes flooded in Kingwood.
  • 1:04:40: Commissioner Cagle complains to Ellis that the discussion is rubbing him raw.
  • 1:06:00: Cagle and Ellis shake fists at each other and nearly come out of their chairs.
  • 1:25:00: Discussion wraps up on this agenda item and the meeting then moves on.

Motion Finally Passed, Next Steps

Luckily and thankfully, when it came time to vote on the measure, it passed.

Matt Zeve, Deputy Executive Director of Harris County Flood Control, said of the plan approved today, “This is not the full scope of the project, just what HCFCD and the TIRZ are partnering on. The full scope will be determined once we have a consultant selected.”

Zeve continued. “The project will involve developing detailed hydrologic and hydraulic models to determine the current “drainage level of service” on open channels in the Kingwood area. Once those are determined, alternatives will be developed to increase the level of service for channels deemed to be undersized.”

“These alternatives,” concluded Zeve, “will be shared with the public in a community meeting. Final recommendations for future projects will be provided. Once Commissioners Court approves the final report, preliminary engineering for the recommended alternatives will begin.”

Zeve expects the assessment work to begin before the end of the summer.

Need for Vigilance and Balance

Today’s meeting underscores the fact that the Equity Flap has not gone away. Lake Houston area residents need to remain vigilant and fight for our fair share of dollars as this and every Lake Houston area project moves forward. We need several Kingwood residents to speak at the next commissioners court meeting to provide balance.

Posted by Bob Rehak on 6/04/2019

644 Days since Hurricane Harvey

Flash Flood Watch In Effect from Midnight Tonight Through Thursday Morning: Simple Ways to Reduce Flood Risk

The National Weather Service has issued a Flash Flood Watch for most of southeast Texas. The three graphics below tell the story.

Expected Tuesday: Source NWS, issued Tuesday AM.
Expected Wednesday: Source NWS, issued Tuesday AM.
Expected Thursday: Source NWS, issued Tuesday AM.

Expect Heavy Rain Late Tonight but More Likely on Wednesday

Showers and thunderstorms are expected to develop tonight as a surge of tropical moisture approaches Southeast Texas and merges with a low coming from the west.

Rainfall rates could reach 2 to 3 inches per hour at times. Widespread rainfall totals of 2 to 4 inches are expected across Southeast Texas by Wednesday evening with isolated totals exceeding 6 inches. The heaviest rainfall is expected to fall along and east of the I-69/US 59 corridor.

Those totals are close to what we experienced in early May.

Jeff Lindner, Harris County Meteorologist warned, “A low level convergence boundary may become established between the US 59 corridor and the coast and help to organize and focus thunderstorms and heavy rainfall. This pattern remains in place Wednesday and Wednesday night while 91L moves up the TX coast and likely either across SE TX or just offshore over our coastal waters.”

PRECAUTIONARY/PREPAREDNESS ACTIONS

A Flash Flood Watch means that conditions may develop that lead to flash flooding. Flash flooding is a very dangerous situation. You should monitor later forecasts and be prepared to take action should Flash Flood Warnings be issued.

Street Flooding Likely; Significant Rises on Bayous/Creeks Possible

Do not drive your vehicle into areas where the water covers the roadway. The water depth may be too great to allow your car to cross safely.

If water is deep enough to cover your tailpipe, your car will stall.

Vehicles caught in rising water should be abandoned quickly. If your vehicle stalls…abandon it and seek higher ground immediately. Rapidly rising water may engulf your vehicle and its occupants and sweep them away. Move to higher ground.

Check Drains and Creeks Near You; Park on High Ground

During storms last month, yard debris (leaves, twigs, small branches, grass clippings, etc.) washed into sewers and drainage ditches. Also, in places, large trees had fallen into creeks and ditches due to bank erosion. Flooding doesn’t always come from the river. It can come from blockages anywhere in the drainage system.

So while the weather is still nice today:

  • Make sure your drains are clear
  • Do not stack branches or garbage where they could back up water
  • If you live near a creek or drainage ditch, walk it. Look for downed trees. Focus on areas downstream from you that could back water up onto your property.
  • Report clogged street drains to City of Houston by calling 3-1-1. Have address ready when you call.
  • Report downed trees in ditches to Harris County Flood Control or call 713-684-4197.
  • Park your car on high ground.
  • Move valuables and important papers to an upper floor or top shelf.
  • Make sure your cell phone and weather radio batteries are fully charged; have backup batteries in case of power outages.
Remember, streets are DESIGNED to be part of the floodwater retention system. They are meant to hold excess water until the ditches, creeks, streams and bayous can absorb it. So don’t park in the street if you can avoid it.

Attention Vacationers: Coastal Forecast is Rough

Winds will begin to increase this afternoon and evening over the coastal waters which will help to build seas on Wednesday. Tides are forecasted to reach near 3.5-4.0 ft on Wednesday which may cause minor coastal flooding on Bolivar and low lying coastal area on the west end of Galveston, Surfside, and in SE Harris County. A coastal flood advisory may be required on Wednesday.  

Posted by Bob Rehak on 6/4/19

644 Days after Hurricane Harvey

Kingwood Drainage Assessment on Commissioners Court Agenda Tuesday and Why We Need More Systematic Reporting

Harris County Flood Control tomorrow will ask the Harris County Commissioners Court tomorrow to approve money for a Kingwood-wide drainage assessment. One of the reasons why is shown below: trees that have fallen into Taylor Gulley since the last time someone from Flood Control reviewed it. That underscores the need for every community association to start a flood committee. With more eyes on drainage, we might be able to keep problems such as these at a sub-acute level and help prevent flooding from clogged ditches.

Thank You, Chris Kalman

Chris Kalman of Woodstream Village sent these pictures to Flood Control and to me last Friday. They show trees that fell into Taylor Gulley during the three huge storms early last month.

This and next four photos taken on Taylor Gulley near White Oak Creek. All photos courtesy of Chris Kalman.

Blockages, such as these, can quickly turn into even bigger blockages when they catch additional trees and debris swept downstream in floods. When blockages become big enough, they can back water up into neighborhoods.

Kudos to Chris for communicating these problems (and their locations) to Harris County Flood Control. HCFCD can’t be everywhere all the time; they have 2500 miles of natural streams and man-made ditches to patrol. They need the help of residents to report problems like these so that they can respond in a timely way.

Photographs like Chris’ help Flood Control find and recognize the problems when workers visit the site. After all, in print, one downed tree sounds a lot like another. Photos also help Flood Control visualize the number of people and type of equipment to bring. In addition, Chris provided them with a map.

Commissioners Court To Consider Kingwood Drainage Assessment Project

As a result of the efforts by people like Chris and Barbara Hillburn of Kingwood Lakes who has been beating the drum to improve internal drainage, HCFCD has an item on the Commissioners Court agenda for tomorrow. Item 2.a.14 on page 10 is a request for authorization to negotiate with the Lake Houston Redevelopment Authority to start HCFCD Bond Project F-14. It includes a drainage analysis of all open channels in the Kingwood area.

Matt Zeve, deputy executive director of the Flood Control District is adding an evaluation of Taylor Gully and the May storm event to the scope of work for this project. 

If you are interested, any Harris County resident can sign up to speak on items on the Court agenda.

The Lake Houston area has more trees than most other parts of town. We definitely need this.

Start a Flood Committee in Your CA

Also, please urge your community association to start a “flood committee” that A) periodically checks creeks and ditches for problems and B) reports them. Often people see problems but don’t recognize them as such. Or they recognize them, but assume someone else reported them already. That’s why, in my opinion, we need to set up a system for reporting problems such as these.

An organization like KSA could coordinate the flood committees of each CA. They could then compile a master list of problems so that Flood Control could better schedule and prioritize clearing and ditch restoration efforts. It would be much more efficient for Flood Control to deal with one entity rather than thousands of individuals, many of whom might duplicate each other’s efforts. Also, as Chris discovered, sometimes it’s difficult to know whom to email. But a group that manages reporting on a regular basis could quickly learn the proper channels.

Two-foot Sections

If your neighbors, CA or trail association tries to remove such blockages, remember this. Flood Control typically cuts trees like the one above into two foot sections. Two feet is small enough to float through culverts in the next flood without getting stuck.

Posted by Bob Rehak on 6/3/2019 with photos by Chris Kalman

643 Days after Hurricane Harvey

Governor Signs Flood Mitigation and Sand Mining Legislation. Now, what happens when?

Governor Greg Abbott has signed final versions of Senate Bill (SB) #7, SB 500, House Bill (HB) #907 and HB 1824. So, what will happen when? Let’s look at the implementation of each.

Flood Mitigation: SB 7 Implementation

SB 7 establishes special funds dedicated to flood mitigation. The bill creates dedicated Texas Infrastructure and Texas Infrastructure Resiliency Funds for flood control planning and the funding of flood planning, mitigation, and infrastructure projects.

Money from SB 7 could help fund additional flood gates for the Lake Houston spillway. They could help release water faster before and during floods such as Hurricane Harvey.

Within 90 days, a Texas Infrastructure Resiliency Fund Advisory Committee will submit recommendations to the Texas Water Development Board (TWDB) on rules it should adopt in administering the fund. TWDB has another 90 days to adopt rules governing the fund. After that, on or before the end of this year, the TWDB may begin financing projects in the state flood plan.

The bill itself takes effect immediately because it passed both the House and the Senate by more than a two-thirds majority. The Senate passed it 31-0. The House passed it 143-1 with two present but not voting. However, Article Two of SB 7 – the part dealing with the infrastructure fund – takes effect on January 1 of 2020 ONLY IF VOTERS APPROVE a constitutional amendment in November. If voters do NOT approve the constitutional amendment, Article Two has no effect.

Flood Mitigation Funding: SB 500 Implementation

SB 500 is an all-purpose special appropriations bill. It appropriates money for SB 7 and other Hurricane Harvey relief projects. For instance, it include $30 million to help dredge where the San Jacinto meets Lake Houston. SB 500 passed with greater than two-thirds majorities in both House and Senate. Therefore, it takes effect immediately.

That means $30 million should be available today to help dredge the mouth bar of the west fork.

$30 million can now used to help dredge the mouth bar.

Sand Mining Inspections and Fines: HB 907 Implementation

On its way to becoming law, the Senate strengthened HB 907. In its final form, it increased inspection frequency for all aggregate production operations (APOs) from every three years to every two.

Breach in Triple-P mine in Porter allowed process water to flow directly into Caney Creek, East Fork and Lake Houston, the source of drinking water for millions of people.

HB 907 also allows the TCEQ to conduct unannounced inspections if the TCEQ investigated a complaint about an APO operation in the previous three years.

It sets registration fees for APOs at a level that will allow the TCEQ to establish an active APO registry.

Finally, it increases penalties for failure to register an APO. It set the minimum at $5000 and the maximum at $20,000 per year with the total not to exceed more than $40,000 for any three year period.

This act takes effect on September 1, 2019. It passed in the House by 135-8 with one present and not voting. It passed in the Senate 28-3.

“Sand Trap” Bill: HB 1824 Implementation

Environmental groups and citizens, including me, fought to clarify the open-ended language in HB 1824. It allows the San Jacinto River Authority (SJRA) and Harris County Flood Control District take sand and gravel from the San Jacinto without a permit in order to restore the conveyance of the river. They can also deposit the sand and gravel on private land.

Opponents feared that it would open the door to river mining because the SJRA is essentially an economic development entity that is sensitive developers. The SJRA has also shown no desire in the past to control sand mining along the banks of the river.

When I asked legislators, miners, TACA and the SJRA how it would work, I received four different answers!

Proponents of the bill sold it as “the sand-trap bill.” The idea: to get sand mining operations to dredge the river, allow them to sell the sand, and avoid taxpayer expense. By dredging at certain locations under government supervision, proponents hoped to reduce the amount of sand coming downriver. That sand reduces the conveyance of the river and contributes to flooding.

If the bill actually works that way, great. But there’s nothing in its language that indicates how it will work or whether miners will be supervised. River mining is outlawed in many countries, including most of Europe. It has been linked to the destruction of private property in many of other countries that allow it.

Watch private sand mining activity on the river closely! This bill takes effect in three months, on September 1, 2019.

Posted by Bob Rehak on 6/3/2019

642 Days since Hurricane Harvey

The thoughts in this post represent my opinions on matters of public interest and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP statute of the great State of Texas.

Even More Discoveries Demand Independent Investigation into Causes of Flooding Around Woodridge Village

On 8/28/2018, LJA Engineers’ project manager for hydrology and hydraulics, submitted a 59-page letter to the Montgomery County Engineer’s Department. The subject: Figure Four Partner’s proposed Woodridge Village development. It shows that the developer knew of the potential for downstream flooding, yet did not develop the site in a way that might have prevented or reduced flooding.

Specifically, the developer’s team failed to construct needed detention ponds in a timely manner. They could have helped offset the effects of clearcutting the southern section of land. Instead, the contractor continued clearcutting the northern section, filled in existing drainage, and sloped land toward Elm Grove BEFORE installing needed detention ponds.

The contractor also failed to repair a culvert running next to North Kingwood Forest. Engineers warned that the damaged culvert had to be replaced.

Finally the engineers may have mischaracterized the soil in modeling assumptions. They classified soil as sandy loam instead of clay. That could have skewed a key factor in runoff models by 2X to 3X.

Parts of Porter Also Flooded That Were Not in Any Recognized Flood Zone

LJA’s letter also shows that residents who flooded in Porter on the western edge of the new Woodridge development were NOT in either 100-year or 500-year flood zones. This supports the claims of Porter flood victims, such as Gretchen Dunlap-Smith. They say they never flooded before. They also claim that Rebel Contractors pushed dirt up against the western edge of the development while filling in natural drainage and wetlands. These actions likely constrained drainage on May 7th, before the contractor began installing storm sewers, drainage ditches and detention ponds in that area.

Flood Plain Maps Show What Developer’s Team Knew Before Permit Granted

Section 1.5 of LJA’s letter to Montgomery County states, “The project site is shown on FEMA Flood Insurance Rate Map (FIRM) panel 48339C0750H for Montgomery County, Texas and Incorporated Areas, revised August 18, 2014. The area just across the county boundary from the project site is shown on FIRM panel 48201C0305L for Harris County, Texas and Incorporated Areas, revised June 18, 2007.” On Page 51, the letter shows existing floodplains on the map below.

Page 51 from LJA letter to Montgomery County Engineer. The dark purple lines show the boundaries of the new development. The light purple and gray areas below the new development show the 100-year and 500-year flood plains in Elm Grove, North Kingwood Forest, Mills Branch and Woodstream Villages.
Drainage on the developer’s two tracts is sloped toward Taylor Gully, Elm Grove and North Kingwood Forest in red circle.

Clearcutting of the S2 detention pond area finished last November according to Nancy Vera of Elm Grove. However, only detention pond S1 and the flow-restricting box culvert next to Vera’s house had been substantially completed by May 7. Neither N1, nor the drainage ditch connecting it with N2 were excavated on May 7th; they still have not been excavated.

At the time of the May 7th flood, only detention pond S-1 had been installed. N-2 is on land owned by Montgomery County and was at least partially excavated in 2006, but none of the devices regulating flow into or out of it had been installed on May 7th.

LJA Engineering’s models assumed all the detention ponds are in and functioning, but we know they were not at the time of the flood. Instead of installing drainage first, the contractor focused on clearcutting and grading the northern section of land which exacerbated flooding on the southern section.

Drain Pipe Should Have Been Replaced

Page 3-1 of the LJA Letter mentions, “…an existing 36-inch-diameter x 290-foot HDPE culvert in Taylor Gully at the downstream end of the project. The upstream end of the culvert is within Montgomery County and the downstream end is within Harris County. Because of its poor structural condition, this culvert needs to be replaced.”

Intake end of the pipe referenced on page 3-1 of LJA Engineer’s letter to Montgomery County. Photo taken on May 12, 2019.

Judging by the poor condition of the pipe after the May 7th flood and the lack of disturbed soil around it, I feel it’s safe to say that it wasn’t replaced at the time of the flood.

Modeling May Have Included Faulty Assumption About Soil

Every time I re-read the letter to Montgomery County, new things jump out at me in light of new things I have learned. Today, I spotted another huge and potentially faulty assumption relating to runoff and flooding. The site description on page 1.1 states that the project site is “characterized by fine, sandy loam.” One of the oil industry’s leading geologists, however, characterized it as “mostly clay,” though he did say it became more sandy in natural drainage features, such as stream beds.

Major factors affecting the runoff coefficient for a watershed are land use, slope, and soil type. We know the contractor increased the runoff rate when it clearcut the forest and altered the slope of land. But I had not previously focused on how the engineers characterized the soil type, which affects water infiltration.

  • Sandy soils absorb more rain, generally reducing runoff.
  • Soils with more clay absorb less rain, generally increasing runoff.

In modeling runoff and flooding potential for Woodridge Village and downstream areas, LJA Engineers used the Army Corps’ Hydrologic Modeling System (HEC-HMS). Page 216 of the user guide for that program states that, “The sand percentage accounts for the effect of infiltration and surface runoff properties on hydrograph generation. Zero percent indicates essentially all-clay soils with characteristically low infiltration rates. Conversely, 100 percent indicates essentially all-sandy soils with characteristically high infiltration rates.”

BrighthubEngineering.com estimates infiltration rates in inches per hour for different types of soil. They show the rate for clay-based soils to average one-third to one-half the rate for sandy loam. That means…

The characterization of the soil could have skewed this component of LJA’s modeling by 2X to 3X. Certainly, that merits further investigation and verification of LJA Engineering’s results before contractors begin pouring concrete.

New Discoveries Argue for Independent Engineering Investigation

All of these observations argue for an independent investigation into the engineering of and construction practices on this site. They raise serious questions about the accuracy of LJA’s conclusions and whether their plans will protect downstream residents from future flooding.

Let’s pray that Montgomery County and the City of Houston commission a forensic investigation into the causes of this flooding. That’s the only way we’ll be able to prevent similar flooding in the future. By the time these issues work their way through the court system, contractors will have built homes and streets that could forever alter downstream flood potential. Harris County and the Federal government could be stuck with hundreds of buyouts costing tens of millions of dollars. A second opinion might save a lot of heartbreak, misery, and tax dollars. Better safe than sorry.

Posted by Bob Rehak on 6/2/2019

642 Days since Hurricane Harvey

The thoughts in this post represent my opinions on matters of public policy and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP statute of the great State of Texas.

That Time of Year Again: Hurricane Season is Here

June 1 marks the official start of hurricane season. And, as if on cue, the National Hurricane Center issued warnings about possible tropical storm formation in the Bay of Campeche. That’s the area between the Mexican mainland and the Yucatan peninsula. It is not forecast to move toward the Houston area. Northeastern Mexico and the Rio Grande Valley, however, should keep a close eye on this one.

This area of low pressure had been centered over land in Central America. High pressure over the central US blocked it from moving north. But now that our high pressure system is moving east, it is allowing the low to move north. As it moves out over water in the Bay of Campeche, it could strengthen. The NHC gives it a 50% chance of turning into a named storm in the next five days. Regardless of formation, it’s going to produce a lot of heavy rain for our friends to the south.

Hurricane Preparedness and Education

There’s no reason to panic over this. But its timing on the first day of hurricane season should remind us all about hurricane preparedness.

One of the first things I would do: Bookmark the National Hurricane Center website (NHC). It is updated several times per day, and gives you the most current information available. It also presents information in a wide variety of formats: for mobile and desktop platforms, maps, text, satellite images, aircraft reconnaissance, etc. NHC is the definitive source for this kind of information.

It also contains links to other weather-related web sites, such as the National Weather Service and NOAA.

Finally, it contains a wealth of information about hurricane preparedness and educational pages that can help you understand these storms better.

Educational resources available on the NHC website. You can drill down within each of these.

Meaning of “Invest” in Weather Context

Exploring the NHC glossary may answer questions that have had you scratching your head for years. For instance, everyone talks about the differences between tropical depressions, tropical storms and hurricanes. But what is an “invest”? You see that all the time.

Invest is shorthand for “investigative area.” It’s simply a weather system for which the NHC wants to start collecting data or running models on. Once a system has been designated as an invest, a number of government and academic web sites initiate data collection and processing.

Designation of a system as an invest does NOT correspond to any particular likelihood of development of the system into a tropical cyclone.

Peak of Hurricane Season

Hurricane season lasts from June 1 through November 30 in this area. Even though today marks the start of hurricane season, the peak isn’t for several months. September 11th is the statistical peak. Tropics heat up the most throughout August and September. Hurricane Harvey lasted from August 25 through 30 – in the middle of that window.

So start preparing now.

Posted by Bob Rehak on June 1, 2019

641 Days after Hurricane Harvey

Woodridge Problems Still Piling Up for Porter Resident Chris Yates

Photo looking west toward Yates property just out of frame on right. Developer continues to build site up relative to neighbors – before installing drainage. This has created problems for Chris Yates and his neighbors in Porter.

Some more bad news surfaced today for the people whose drainage has been affected by Woodridge Village construction activity. Rebel Contractors has built up the level of Woodridge before installing drainage between Woodridge and neighbors. As a result, water has ponded in Porter yards for months and damaged their property. Then, to add insult to injury, about a week after finally erecting a long-awaited silt fence, Rebel Contractors covered it with dirt.

Woodridge: The Yates Family Curse

Chris Yates, who lives at 25395 Needham Road in Porter, sent me these pictures today. They show how construction activity has affected his property. First up: two BEFORE shots showing his happy family in front of the Woodridge site.

Yates’ daughter Amber in back yard before clearcutting began. Looking east. A small ditch ran through the tree line which forms the property line between Yates and Woodridge. Note the telephone lines at the top of the picture for reference in subsequent photos.
Yates with family in happier times. This was taken after construction began but before water started piling up. Note piles of dirt being stacked up on Woodridge property in background.
After clearcutting and grading of the Woodridge property in the background, water started collecting in Yates’ yard. This rain fell in March and remained there until Friday, May 31, when Yates pumped it out.

Contractor Should Have Maintained Positive Drainage at All Times

Page 6/Point 12 of the Woodridge Village Detention Plan states that, “Contractor shall maintain positive drainage from construction site at all times. Any damage to existing ditch system as the result of the contractor’s activities shall be repaired to existing or better conditions.” Oops! Neighbors up and down the western border of Woodridge have experienced stagnant water. Some have even experienced flooding.

Almost 4 Feet of Standing Water Before Any Drains Away

The Yates back yard on May 7. Their four-foot fence is barely visible in these two shots taken as water built up. It could not drain away according to Yates until the stormwater crested at a high point to the south between his home and Sherwood Trails..
This recent shot shows how the standing water killed Yates’ grass. Silty runoff ponded for two months.
Today, Yates pumped the water out to his street drain. It took him eight hours, pumping at 3,700 gallons per hour. While this kind of damage does not compare to the loss of a home, I’m sharing this story because it seems to illustrate the contractor’s disregard for the problems it causes neighbors.
Yates raises several animals on his property but has had to keep them caged for months because of the standing water.
Detention plans show that developer knew runoff was moving west to east toward development.
Page 12 of the Water, Sanigtary Sewer and Drainage Facilities & Paving Appurtenances Plan shows that developer was expecting to compensate for 10-aces of offside drainage from the Yates neighborhood, but didn’t start installing the storm drains for months, until well after three heavy May rains.
Looking north from Yates back yard along western boundary of Woodridge. Note the standing water between development and neighbors. The Woodridge side of the property (right) was elevated approximately 3 feet before drainage was installed. Photo taken 5/31/2019.
Plans show that this drain should eventually handle water that collects between Yates’ property and Woodridge. Question: Why wasn’t this installed before the Woodridge property was elevated? Said Yates who has years of construction experience, “Drainage is put in by elevation so this could have been put in before building up.” Photo taken 5/31/2019.

More Out-of-Sequence Construction?

Yates, whose father owned a clearing/grading business, worked in the family business when younger and said that on a site like this, they typically installed drainage first thing. The reason: ponding water slows down construction. “Even though it takes time, it saves time,” said Yates. “You can’t work when the site is wet. Construction on this site seems to be out of sequence.”

Yates also said that he had talked to the developer and learned they were six months behind schedule. One can only wonder whether the delayed installation of drainage had anything to do with the construction delays.

This sequencing complaint echoed the concerns of Elm Grove and North Kingwood Forest residents. They flooded, in part, because the developer clear cut the entire 268 acres before installing critical detention ponds.

The Silt Fence Saga: Part 2

This and detention ponds were not the only out-of-sequence construction that neighbors have suffered through. Silt fences should have been installed before clear cutting started. Instead, they were put up almost a year later.

Additionally, the developer finally installed silt fences last week. The developer was supposed to install them before clearcutting began. For months, residents complained about sand, silt and clay pouring out of the construction site into streets and storm drains. Then about a week or so ago, after a complaint to the TCEQ triggered an investigation, silt fences finally appeared. Now they are buried under dirt again.

1-2 Week old silt fence … buried under silt. Said Yates, “What’s the point of silt fences if you are piling dirt on top of them an on the other side of them?” Photo taken 5/31/2019.

Chris Yates must feel at this point as though he’s Rodney Dangerfield. “Can’t get no respect.” Let’s hope he and the hundreds of other families affected by Woodridge construction find some before this is all over.

Posted by Bob Rehak on 6/1/2019 with images courtesy of Chris and Tammy Yates of Porter

641 Days since Hurricane Harvey

All thoughts expressed in this post are my opinions on matters of public policy and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP statute of the Great State of Texas.

Better Late Than Never: Large Detention Pond Taking Shape North of Area that Flooded

Elm Grove resident Jeff Miller reported tonight that Rebel Contractors was busy widening and deepening a crucial detention pond near homes that flooded in Elm Grove and North Kingwood Forest. According to Miller, “The pond is starting to assume its final shape with the sloping of the edges.”

Here’s the plan for the pond.

S2 (the second detention pond in the south section of Woodridge Village.

May 8

For comparison, the “pond” looked like this after the storm on May 7…non-existent. For comparison purposes, consider this the BEFORE SHOT.

Photo taken shortly after the flood on May 7 shows the area where S2 detention pond should be had not yet been excavated. Nor was silt fence in place.

May 30

Here’s what it looked like on the afternoon of 5/30/19. This Woodridge Village detention pond should ultimately hold about 50 acre feet of runoff. Had it been excavated before the May 7th rains, many homes might not have flooded. It could have reduced the height of the flood by one whole foot across a 50-acre area.

Photo of S2 taken by Jeff Miller on 5/30/19

Said Miller, “Better late than never.” The video below lets you get a better look at the expansiveness of the pond.

Video by Elm Grove resident Jeff Miller showing S2 pond in Woodridge Village taking shape.

Dirt from this pond and others will build up the rest of the subdivision.

Posted by Bob Rehak on May 30, 2019, with photos and reporting from Jeff Miller

639 Days since Hurricane Harvey

Gretchen Dunlap-Smith’s Flood Experience: “You Sunk Us”

To date, most of the press coverage about the May 7th flood has focused on Elm Grove and North Kingwood Forest to the south of the new Woodridge Village development. However, the flood also affected many homes in Porter to the west of it. This is an interview with Gretchen Dunlap-Smith in Porter whose home was built in 1994. It flooded for the first time – after Woodridge Village started clearcutting and grading the land next to her, and wetlands disappeared.

USGS National Wetlands Inventory shows that government classified much of the northern section of Woodridge as wetlands (dark green overlays). Porter borders Woodridge Village to the west. Smith home located in white circle.

“This Area Never Flooded”

Rehak: Has this area ever flooded before?

Dunlap-Smith: This area never flooded.

Rehak: How far back does “never” go?

Dunlap-Smith: I grew up in the Kingwood area. My parents moved here in late 1976. We had 2.5 acres off of Hueni. My brother built this house in ‘94. So I’ve known this home since its inception. I saw it being built. One house at the end of the block did get water in it, but none of the other houses ever flooded. Ever!

Rehak: What do you think caused the flooding on May 7th?

Dunlap-Smith: (Pointing to bulldozers in the distance) The construction down there. That’s the only thing that’s changed. During Harvey, there was never any fear, threat, or worry in my mind that “I’m going to have water in my home.” Ever! During Harvey, during the Tax Day flood and all the stuff before that…never any concern. This (pointing to the construction again) changed the game.

We used to ride four wheelers on that property so I know there used to be a huge detention ditch and a huge pond. There used to be a natural creek down off of the end that went up to the wood line. From what I’ve been seeing and what I’ve been told, they backfilled all that in. The wetlands disappeared.

Note dirt pushed in ditch along western edge of Woodridge Village. Homes from the north end of this development in Porter all the way down to Mace and Joseph streets flooded, including Dunlap-Smith’s home on Flower Ridge.

Ditches No Longer Drain

Dunlap-Smith: Even now, the ditches don’t drain. Our ditches drained before. They never had standing water in them. You look at the ditches now and you will see green algae and moss growing in them. We never had that before. We could mow our ditches. They were dry, because the water drained. And now it doesn’t do that. 

Rehak: Where did the water go before? 

Dunlap-Smith: It went to the end of the road and flowed out.

Rehak: And now it’s getting to the end of the road and stopping?

Where drainage from Flower Ridge in Porter joins the new Woodridge Village in Porter.
Residents say water now stands so long in altered ditches that it grows algae.

Dunlap-Smith: Right. Now it’s backing up and flooding the street.

Rehak: Were you blocked in on May 7th?

Dunlap-Smith: We got out Tuesday night when the rain receded a little bit…for like 3 hours. The water went down enough to where I felt comfortable going through it with our Nissan Altima.

Ditches Became Invisible in Flood

Rehak: These ditches are kind of…deep.  If you didn’t know they were there…!!!

Dunlap-Smith: Yeah! You could really do some damage. Or worse, drown yourself in your car.

Photo by Gretchen Dunlap-Smith from May 7 of Flower Ridge in in Porter.

Rehak: How many homes in your subdivision were affected?

Dunlap-Smith: I don’t have a count. But I know that several homes flooded on our street and other streets in the subdivision.

Rehak: How high did the water get?

Dunlap-Smith: A couple inches in our house. Deeper in others.

Rehak: How much did you lose?

Saved by the Peaches!

Dunlap-Smith: Carpet. I was able to get some furniture up onto soup cans and big jars of peaches.

I put most of our furniture up on stuff like that. Hopefully, I may be able to salvage a couple rooms of carpet. Most of my house was tiled by my brother and sister. So the only rooms that had carpet were my living room and my three bedrooms.

Swamped utility room after the flood. Photo. by Gretchen Dunlap-Smith.

Rehak: Is there any concern that the water got under the tile?

Dunlap-Smith: I talked to a couple people about that. I have two dehumidifiers that have been going non-stop since the day after the flood. Those haven’t quit. I’m dumping them constantly. 

Cleaning Up the House Without Flood Insurance

Rehak: How long did it take the water to recede? When you came back the next day was it out?

Dunlap-Smith: It was out of the streets.

Rehak: How about the house?

Dunlap-Smith: No. The house…I had to pull every bit of carpet out. It had not receded.

Rehak: Did you have to squeegee it out?

Dunlap-Smith: That carpet was a soaking wet mess! You see that shop vac behind you? That’s a wet/dry shop vac.

Gretchen Dunlap-Smith tries to save her carpet by drying it on the bed of her truck.

You know, this isn’t a flood zone. When we bought the home, we weren’t required to have flood insurance. We called our agent after the flood and he said we weren’t covered, but we could get coverage for four or five hundred dollars per year. But it wouldn’t activate for 30 days.  

“You Sunk Us”

Dunlap-Smith: My neighbor told me that they were down there digging a ditch line, trying to open up the drainage again from the damage they had done. But you’ve already damaged natural drainage. You changed and affected how the flow goes. So I don’t care what you do now. You sunk us

Rehak: Their plan shows a huge detention pond up in the northwestern corner of this land that they clearcut. And then there’s a linear ditch running inside their property all the way down to the bottom.

Where N1 detention pond and drainage ditch should have been before flood. Excavation still had not started weeks after flood. This area used to be wetlands before the developer “improved” the drainage.

Dunlap-Smith: Right. But that ditch is not there. And if you look down Ivy Ridge, every home has trash in front because every one of them flooded.

Trash pile at end of Ivy Ridge. Looking east toward new development where drainage used to go.

“They Will Never Build on that Property”

The gentleman behind us, when he bought his house, told us there was an easement on that property. He was told they would never build on that property and not to worry. And here they are (pointing to construction).

Rehak: I’ve heard that same story from a dozen different people!

Dunlap-Smith: You get told something and you take it as gospel truth. And you run with it. You don’t check. You don’t research it. You just believe it because they’ve been honest up until now. Which is unfortunate.

Rehak: Do you have any idea what the financial loss is so far?

Counting Her Blessings, Minus the PTSD

Dunlap-Smith: Not really. Honestly, I counted my blessings. It could have been a lot worse. I saw what those people in Elm Grove were hit with. And my husband lost everything in the ’94 flood, including his whole family home. He lived right behind where Reeves furniture used to be on 59. It’s an antique store now. He lived on Treasure Lane. In ’89 there was a flood. They lost everything. But then the one in ’94 really did them in.

As far as the financial? I’m grateful. I know it could have been worse. But I know there’s been a huge emotional cost. It triggered PTSD in my husband.

Rehak: How?

Praying as the Water Rose

Dunlap-Smith: My husband is 6’4”. Not a little guy. He dwarfs me. Works for the Harris County Sherriff’s office. Takes down inmates every day. He’s not a timid guy.

When water was coming in the house, he sat down with his head in his hands and had tears. And I’ve never seen him cry.

We both were under stress. Water’s coming in our house. I have our dogs in a kennel. And I realized then…oh my gosh. The dogs are standing in water inside their kennels. So I moved them up. My husband and I were both getting a little snippy, which isn’t in our nature. There we were. Standing up to our ankles in water in the middle of our living room. He grabbed my hand and I grabbed his, and it’s like, “OK, right here. Right now. We’re praying. Stop. We have to see this for what it is not. It’s not as bad as it could be. And now he’s seeing that. 

That Sour Smell

Rehak: Are you going to have to pull out wallboard and electrical?

Dunlap-Smith: I don’t think so. That’s why I said, “I’m counting my blessings.”

Rehak: Floorboards?

Dunlap-Smith: (sighs heavily). Probably. After the first three or four days, I could smell the sour. There was a heavy sour smell. Not so much mildew, but sour.

May 15th was the deadline to dispute our taxes and ours went up like $10,000. So I’m disputing them. I fired off a letter. (She begins reciting complaints in the letter.) “Are we going to be in a flood plain now?” “Are we going to require flood insurance?” We’re not a high-income neighborhood. We don’t have money to throw at that stuff.

Rehak: What kind of assistance have you gotten from Montgomery County so far?

Dunlap-Smith: Nothing. (Pause) Absolutely nothing.

Too Poor to Repair, Too Proud to Ask for Help

Rehak: What would you like to get?

Dunlap-Smith: I would like to get those sticky floor tiles at cost or at a highly discounted rate. I don’t know. I would like to get a dehumidifier because they’re not doing squat about this or taking accountability. My husband and I don’t have credit cards that we can buy things with.

We bought two dehumidifiers out of our pocket. That was nearly 500 dollars. You’re living paycheck to paycheck and you want to fix your house back. My Aunt told me to call Red Cross. But I’m not going to take money out of somebody’s hands that I can see needs it more than I do.  I’m not going to do that.

Wants Developer to Restore Drainage

Rehak: Let me rephrase the question. In regard to your development, what would you like to see Montgomery County and the developer do?

Dunlap-Smith: For starters, come in and dig out the ditches. Maybe lower the streets to create more capacity for the water before it gets into our homes.

Rehak: And in regard to that new development going in over there?

Dunlap-Smith: I would love to see the County force the developer to create a true, correct drainage ditch.

Rehak: Do you think the county is even aware that you flooded?

Dunlap-Smith: No. They sent out a message on Twitter saying, “Contact us if you had any flooding.” I don’t think they have any clue. 

We had water backing up and leaking from our toilet. Our tub was filling up with this noxious looking water and a septic smell. It was brown. 

No, I don’t think the county knows that it happened in a place that it’s never happened before. The developer says they aren’t the culprit. But they changed the drainage. And they’ve gone too far to turn back.

Rehak: You can’t put back nature the way it was.

Dunlap-Smith: Agreed. I wish the county could force them to create drainage. This flooding will happen again if things stay as they are.

Reluctant to Water Plants

Rehak: How do you feel about your future here?

Note: As with other flood victims I have interviewed, curiously, Ms. Dunlap-Smith thinks in terms of tomorrow, not next year.

Dunlap-Smith: We have a little joke here. Every time I water my plants, it rains. For some people it’s washing their cars. But I told my husband this morning that, “I’m afraid to water my plants.” So … if that tells you anything.  (Laughing) I’d rather let the plants die.

Posted by Bob Rehak on 5/31/2019

640 Days since Hurricane Harvey