Pictures of Aftermath of July 4th Fire in Forest Cove Townhomes

As dawn broke this morning, the extent of the July 4th fire in the Forest Cove townhomes became apparent. It appears that the blaze affected three, or possibly four, of the northernmost townhomes on Timberline Drive. At least one of the units still smoldered when I took these pictures around 9 a.m. this morning.

On the morning of July 5th, you could smell the smoke two blocks away.
It appears that the fire caused at least one unit to collapse inward on itself.
Close up of northernmost unit still standing.
Fire burned through the roof in places.
The force of fire hoses may have displaced these shingles. The fire did not appear to spread this far.
Photo of same units from back side on Timberline Court shows fire damage to at least three townhomes.
Close up from center portion of shot above.
Note how even the globe of the streetlight on the right appears to have partially melted.
Close up from shot above. Also note the relatively straight burn line.
Meanwhile, outside the townhomes that burned on Aqua Vista last Sunday, people have already begun illegally dumping used carpet.

Last night, equipment and firefighters from several Houston Fire Department stations lined up for blocks to fight and contain this fire. It was the second fire in this area this week and at least the third this year. When more than 17 feet of water swept through the townhomes during Harvey, they became uninhabitable.

No Electricity or Gas to Area

Former owners say the electricity and gas have been cut off since Harvey. Since then, the townhomes have become the domain of vandals, squatters, drug dealers and graffiti artists.

FEMA, through Harris County Flood Control, is buying out the properties. But the process is voluntary, long, and cumbersome. They treat each unit in a multi-unit complex, such as this one, as an individual sale. Only when buyouts for all townhomes in a complex are complete, can Flood Control schedule demolition.

The area will never be developed again. However, FEMA buyout deed restrictions do allow some flexibility. These pictures underscore the urgency to complete the buyout process and transform this area into something new with social value.

Posted by Bob Rehak on 7/5/2016

675 Days since Hurricane Harvey

Second Fire in Week at Forest Cove Townhomes

Approximately 10 pieces of fire equipment as well as ambulances responded tonight to yet another fire at the Forest Cove Townhomes. This is the second fire this week and at least the third this year at a large complex that has been abandoned since it was engulfed by Hurricane Harvey’s floodwaters.

Earlier this week, fire consumed another part of the complex on Aqua Vista Street. Tonight, it destroyed more townhomes in the same area between Timberline Court and Timberline Drive where the latter intersects Marina Drive.

I could not get close for safety reasons, but managed to capture the images below with a wide-aperture Nikon telephoto lens.

Abandoned townhomes on Timberline Drive, photographed from Marina Drive in Forest Cove.
Houston Fire Department was spraying water from this elevated position to suppress the fire. Additional units were spraying water on the flames from the ground as you can see in the next photo.
Fire equipment was dousing the flames from multiple angles to keep the fire from spreading.

Massive Fire Department Response

Fire equipment and ambulances lined up for four blocks. From Marina and Timberline, they went up to Hamblen. Additionally, equipment blocked half of Hamblen for another block.

Cause of the fire has not yet been determined. Nor is it known whether there were any injuries.

Need to Accelerate Buyouts and Plan Alternative Uses

This underscores the need to accelerate buyouts in this area and tear down these abandoned buildings. They have become a haven for drug dealers, squatters and vandals.

Ironically, I was responding to questions about my last post on this subject – i.e., what to do with this area – when readers alerted me to this new fire.

Posted by Bob Rehak on 7/5/2019

675 Days since Hurricane Harvey

Mouth Bar Dredging Begins

It appears that dredging of the mouth bar of the San Jacinto West Fork has officially begun. Two weeks ago, I reported that the Great Lakes dredge had maneuvered into position. Then this weekend, residents started sending me pictures taken from the river showing equipment in operation.

Mouth Bar Imagery from RD Kissling

RD Kissling, a Lake Houston area resident and geologist, who first helped bring the mouth bar to the public’s attention sent me the photo and video below last week. “The dredge is up and running,” he said.

The image with the canoe below, Kissling said, “This is me standing in shin deep water about 200 yards south of the exposed mouth bar, looking north towards the bar and Scenic Shores.  There is another small channel about 20 yards south of me then the bar shoals again.”

Lake Houston Area geologist RD Kissling standing in shin-deep water 200 yards south of the mouth bar. This image, more than any other I have seen, dramatizes how critical the need for dredging has become...and how hilarious the Romerica proposal is to build a marina for more than 600 40-foot yachts.
Video shot by RD Kissling from the southernmost exposed portion of the mouth bar.  Starts looking west towards the dredge then swings around to the east.

Mouth Bar Images from Today Shot by Jeff Kristoff

Then Jeff Kristoff, a Kingwood resident, sent me the pictures below today. They show an excavator on the upstream end of the bar and dredging equipment immediately south of the bar. It appears there may be two excavators breaking up vegetative growth and sediment. Farther upstream, near River Grove Park, dredgers reportedly ran into submerged logs that had been covered by sand.

The loops in the pipelines will allow the dredge to maneuver up and downstream as it works. Note first of two excavators in background breaking up vegetation at edge of mouth bar.
Excavators can also be used to more or lift pipe for repairs.

Ultimate Plans Still Not Announced Yet

Exactly where or how much the Corps and its partners plan to dredge has not yet been announced. The Corps last issued a press release for the project on June 10, three weeks ago, and has not yet responded to a Freedom-of-Information-Act request for the dredging plans.

Because it’s hard to believe that the U.S. Army would move on a project this large without a plan, I can only conclude that all parties have not yet reached an agreement on volume and a permit for placement of the sediment.

For the time being, it looks as though the Corps will use Placement Area 2 on Sorters Road…at least initially. Pumping ALL of the sediment 10 miles upstream would hike the cost hugely because it would require at least 5 booster pumps. Each uses 1000 gallons of diesel per day.

For speculation on where and how much they might dredge, see this post.

Posted by Bob Rehak on July 4, 2019, with images and video from RD Kissling and Jeff Kristoff

674 Days since Hurricane Harvey

HCFCD Schedules Maintenance for Taylor Gully, Other Ditches

Jeff Miller, an Elm Grove resident, just reported receiving a note from Harris County Flood Control District (HCFCD). Will Sherman, HCFCD’s Precinct 4 coordinator, indicated the following.

Plans for Taylor Gully

The right-of-way transfer to HCFCD for the upper portion of Taylor Gully (see map below) is scheduled to be on the next Commissioners Court agenda on July 9th.

HCFCD right of way access along Taylor Gully (left) should be complete by July 9.

That portion of Taylor Gully has become badly clogged with sediment due to the construction of Woodridge Village upstream just across the Montgomery County line.

Woodridge did not have erosion control measures in place when three storms in early May caused massive erosion.

Part of the erosion in the area clearcut for the new Woodridge Village subdivision. Tree line on the left is the Harris/Montgomery County Line. No erosion control measures were in place at the time of this photo during the heavy rains in early May.

Here’s what Taylor Gully looked like on 6/24/19.

Reinforced concrete box culvert on Taylor Gully at the Harris/Montgomery County Line. 10′ high culverts appear to be half clogged with sediment. Harris County is in foreground. Woodridge Village and Montgomery County are in background. Photo by Jeff Miller.

Following approval of the right of way transfer:

  • Equipment should be on-site July 11th 
  • Work should begin by July 15th

Regarding debris in the downstream portion of Taylor Gully:

  • HCFCD cleared debris after Harvey
  • HCFCD plans to do it again “soon” as part of a general debris removal process on multiple channels in Kingwood.
  • The wider effort should begin this August.
Blockage on lower portion of Taylor Gully. Photo courtesy of Chris Kalman. When banks erode and trees fall into ditches and creeks, the trees can catch other debris floating downstream and form “beaver dams” that back water up into neighborhoods.

Work on Ben’s Branch Expanded

Yesterday, HCFCD extended its work on Ben’s Branch west of Woodland Hills. They excavated the area between North Woodland Hills and the businesses on the south side of North Park Drive (Walgreens, Firestone, McDonalds, etc.).

HCFCD maintenance work along Bens Branch west of Woodland Hills Drive in Kingwood. Photo courtesy of Thomas Blailock.

To Report Blockages Near You

If you are aware of downed trees blocking a channel near you:

Have a safe and happy Fourth of July!

Posted by Bob Rehak on 7/3/2019

With contributions from Jeff Miller, Thomas Blailock and Chris Kalman

673 Days after Hurricane Harvey

Planning for Rebirth of West Fork

This past Sunday night, the Houston Fire Department battled a blaze in the abandoned townhomes on Aqua Vista Street in Forest Cove. Since Harvey, the townhomes have been uninhabitable. 240,000 cubic feet per second roaring down the West Fork of the San Jacinto destroyed their structural integrity, literally ripping some of the buildings in half.

Townhomes in Forest Cove on Aqua Vista St. burned on Sunday, July 1, 2019

Since then, the townhomes have borne the marks of looters, squatters, drug dealers, vandals and illegal dumpers. When FEMA came to Houston to create a video about the horrors of Harvey and the need for flood insurance, they used these townhomes as a backdrop.

Ironically, the townhomes have also become a case study in how quickly properties can deteriorate when left unattended.

Then on Sunday, someone or something reduced most of one complex to ashes. The cause of the fire has not been determined at this time. It is the second fire in this complex this year; in January, the Houston Chronicle reported another.

Remaining Buildings a Magnet for Decay

Flood-damaged and abandoned townhome at the intersection of Timberline Drive and Aqua Vista Street in Forest Cove.
Despite the City’s efforts to keep the area clean, it has become a major dumping ground.

In recent months, the once-attractive townhomes have become an embarrassment. Despite efforts by the City to clean up the area, it has become a fertile dumping ground for old tires, used furniture and landscape waste.

What Next for West Fork?

Harris County Flood Control District (HCFCD) is buying out the townhomes and demolishing them, building by building, as quickly as they can. Matt Zeve, Deputy Executive Director of HCFCD said, “HCFCD owns all but three units in the building that burned. We’ll expedite the remaining purchases and proceed with demolition ASAP.”

That raises the obvious question, “What will become of this area?”

The townhomes lie on the north side of the San Jacinto West Fork.

Planning a Rebirth…Within Some Limits

Flood Control notes that legal restrictions exist. Says Zeve, “The properties purchased with FEMA grant assistance must remain as open space in perpetuity.  Open space can include parks, flood reduction projects, grazing, and more.  (See the attached FEMA deed restrictions and compatible uses.)

HCFCD will own the land in perpetuity.  However, HCFCD has the ability to transfer the property to another public entity or conservation agency.  Maintenance agreement options also exist.

Community and natural values will factor into the process.  However, whatever is decided it must meet FEMA’s deed restrictions

FEMA deed restrictions define compatible uses.

“The Property shall be dedicated and maintained in perpetuity as open space for the conservation of natural floodplain functions. Such uses may include: parks for outdoor recreational activities; wetlands management; nature reserves; cultivation; grazing; camping (except where adequate warning time is not available to allow evacuation); unimproved, unpaved parking lots; buffer zones; and other uses consistent with FEMA guidance for open space acquisition, Hazard Mitigation Assistance, Requirements for Property Acquisition and Relocation for Open Space.”

Buildings Prohibited With a Few Exceptions

No new structures or improvements may be erected on the Property other than:

  • A public facility that is open on all sides and functionally related to a designated open space or recreational use;
  • A public restroom; or
  • A structure that is compatible with open space and conserves the natural function of the floodplain, including the uses described above, and approved by theFEMA Administrator in writing before construction of the structure begins.

Public May Be Part of Process

Because HCFCD owns the property, community values will be considered in its future. However, the question is larger than the land that HCFCD will own. It also involves land that Romerica currently owns as well as surrounding vacant properties along Hamblen. Many suggestions have come forward so far.

These are all great ideas. They could reduce flood risk AND re-establish the reputation of Kingwood and Forest Cove as two of the most enviable places to live in the City of Houston.

It’s time to start the conversation now. I hope all stakeholders can come together to create a master plan for the area bordering the West Fork along Hamblen.

Posted by Bob Rehak on 7/2/2019

672 Days after Hurricane Harvey

Only 23% of Woodridge Village Detention Ponds Now Functional

One month into the 2019 hurricane season, only about 23 percent of the Woodridge Village Detention Ponds have been substantially excavated and have outflow control devices installed. At the time of the May 7th Elm Grove flood, that percentage was only 9 percent. So in a little less than 2 months, Rebel Contractors has more than doubled the percentage completed. However, as we head toward the peak of hurricane season, approximately three quarters of the detention capacity remains unexcavated, dysfunctional, or both.

Contractors also have yet to finish grading, planting, and cementing portions of the ponds that they have excavated.

Only 2 of 5 Detention Ponds Substantially Excavated

The first phase of the 268-acre Woodridge Village shows a total of 4 detention ponds. But Rebel Contractors has excavated only two on the southern end so far: S1 and S2.

Together they provide a total of 49 acre-feet of storage. Pond N1 has not yet been excavated and Pond N2 does not yet have an outflow control device that will retain the water upstream from Elm Grove.

Detention for Phase 1 of Woodridge Village

In Phase 1, Pond N2, has no additional excavation. Existing excavation was done by Montgomery County starting in 2006. The county removed approximately 3-4 feet of dirt in a 20 acre area. Ultimately, N2 will be the largest pond in the development with 154.7 acre feet of detention. Note: the figures quoted below differ slightly from those I quoted earlier because LJA Engineers presents conflicting data in its Drainage Impact Analysis for Montgomery County. See pages 7 and 54.

Ultimate Detention for Woodridge Village from Page 7 of the document titled Report Addendum-2027-1002. N2 currently covers about 10 acres to a depth of 6-8 feet. However, it will be enlarged and deepened so that it holds 154.7 acre feet. That’s more than half of all the detention on the property.

Ultimately, the 5 ponds will have a total of 271 acre feet of storage. An acre foot covers one acre to a depth of one foot. So the five ponds will hold a little more than one foot of rainfall per acre of development.

Woodridge Village Detention by Pond in Ultimate Phase

That means, 12 inches of water should be able to fall on the entire development without flooding any adjoining properties. But with only 23% of detention functional (S2 – green, and S1 – blue), that 12 inches of detention is effectively reduced to 3 inches right now.

How Much is Functional and Where?

The bullet points and pie chart below summarize the total storage and current status of each pond as of July 1, 2019. The figures for acre-feet are taken from the map above representing the ultimate phase of development.

  • N1 = 13.2 acre feet (not started)
  • N2 = 154.7 acre feet (started by Montgomery County circa 2002, but is not fully excavated, nor is there any outflow control device installed to detain water upstream of Elm Grove)
  • N3 = 42 acre feet (does not appear to be started)
  • S1 = 18.6 acre feet (mostly functioning, but not fully finished)
  • S2 = 42.5 acre feet (mostly functioning, but not fully finished)
  • Total detention when complete = 271 acre feet
  • Total detention not functional as of July 1, 2019 = 77%

Photos and Video of S2 as of End of June 2019

Jeff Miller shot his video of S2, the pond immediately north of Village Springs in Elm Grove. It shows what progress looked like at the end of June. The pond has been widened by sloping the sides even more since the last update.

Video of Woodridge Village Detention Pond S2 shot from north of Village Springs in Elm Grove at end of June. Courtesy of Jeff Miller.
This shot, also by Jeff Miller, gives you a sense of the scale of the S2 detention pond. Remember, as large as it looks, it’s only designed to hold 16% of the runoff above it.
Taylor Gulley below the concrete box culvert that controls the outflow from S2 is becoming badly silted. Those openings are each supposed to be 10′ x 6′. They look far less than that right now because of the sediment.

N2 Will Contain More than Half of All Detention

Google Earth image showing the triangular shaped N2 detention area in March of 2011. This land was partially excavated by Montgomery County circa 2006-2012. The developer plans to widen and deepen it, but has not done so yet.
Google Earth image showing same area in February of 2019. According to MCAD-tx.org, Montgomery County still owns the triangular area that will become Detention Pond N2.
This is what N2 looked like at the end of May. It had not changed since the May 7th flood.
N2 from the reverse angle looking south on 7/1/19. Still no appreciable change.

N1 – Still No Excavation

This is where the N1 detention pond should be on the north section near the Webb Street entrance. No excavation in sight.

N3 – Still No Excavation Visible

Likewise, no excavation is visible near where the N3 pond should be.

Much More to Come Per Hydrologist’s Report

In Phase 1, Figure Four, a subsidiary of PSWA and Perry Homes, will develop 30 acres in the northern section and 58 acres in southern section. Ponds N1, S1 and S2 are to be built during this phase.

The hydrologist notes that a portion of N2 is already in place (although there is nothing there yet to detain the water upstream from Elm Grove). She also notes that:

  • N2 will be widened during the Ultimate phase
  • A pilot channel within N2 and  the E-W channel immediately downstream will be graded during Phase 1 to provide flow-line continuity with other proposed structures.
  • A concrete lined channel on the eastern side of the subdivision will be extended 150′ between the E-W junction and a 36″ plastic pipe.

Much work remains before their tables and charts on water flow can be used.

Remember, per their own report, the larger portion of Woodridge Village is in the north. It comprises two thirds of the development and the ground there slopes 10 times greater than the southern portion. (1 degree vs.  0.1 degrees).

The Woods are Gone, But We’re Not Out of the Woods Yet

As Elm Grove resident Jeff Miller said, “It sure seems to me that once they clear cut the north, that the potential for flooding rose exponentially.”

Let’s see!

  • More clear-cut area.
  • No functional detention.
  • Sloping toward Elm Grove.
  • And only one fourth of the total detention installed on the southern section.

I would agree.

As we approach the second anniversary of Harvey in 7 weeks, everybody on the periphery of this development is on edge…no pun intended.

Montgomery County needs development rules that protect neighbors from such development practices.

Posted by Bob Rehak on 7/1/19 with help from Jeff Miller

671 Days since Hurricane Harvey

All thoughts expressed in this post are matters of opinion and safety involving public policy. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Maintenance and Construction Work Beginning on Bens Branch

Here’s some much needed good news regarding Bens Branch. One small maintenance project began last week and an even bigger one should kick off within the next two weeks. Bens Branch cuts diagonally through Kingwood and drains a major portion of the community.

Bens Branch Between North Park and St. Martha Started Last Week

Last week, Harris County Flood Control crews began excavating Bens Branch from North Park to below the old St. Martha’s church. In recent years, the creek had become badly silted and overgrown with vegetation. When the May 7th rains hit, several local businesses flooded including the St. Martha Catholic School and Kids in Action. County maintenance should soon restore normal conveyance through this area. These photos taken last Friday by Thomas Blailock, a Bear Branch resident, show how badly the creek had become constricted.

Photo of Bens Branch taken from Woodland Hills Bridge on Friday, 6/28/2019. Kids in Action is in background. St. Martha is out of frame on the right. Courtesy of Thomas Blailock.
Another photo courtesy of Thomas Blailock showing how badly Bens Branch was constricted in this area.
Note how shallow the ditch has become. Only the bottom tread of the excavator was visible in this standing water.

Bens Branch South of Kingwood Drive Starts Next Month

For the last two months, Harris County Flood Control has also been compiling specs, soliciting vendors and receiving bids for the excavation of Bens Branch between Kingwood Drive and about 1000 feet north of the West Fork San Jacinto River. That area has also become badly silted.

Scope of new Bens Branch excavation project
Bens Branch at West Lake Houston Parkway immediately south of Amegy Bank.

Excavation of approximately 80,000 cubic yards of sediment should begin in July and last for several months. Prepare for dump trucks on the road for the next few months. It will be inconvenient and dirty, but that’s the price of restoring the conveyance of the creek.

This portion of Bens Branch contributed to the flooding of Town Center, The Enclave, Kingwood Village Estates, Kingwood Greens, the YMCA and Kings Harbor and five apartment complexes. Twelve people in Kingwood Village Estates died as a result of injuring sustained during the evacuation or the stress of losing their homes when they returned.

Jason Krahn, the project manager at Harris County Flood Control said last Friday that, “A recommendation to award Project ID # G103-33-00-X004 – Conveyance Restoration on Bens Branch to Solid Bridge Construction, LLC, has been made, and that recommendation to award is scheduled to be on the Harris County Commissioners Court (HCCC) Agenda for HCCC approval of the recommendation to award on July 9, 2019.”  

Once the award has been officially voted on and approved by the Commissioners Court, the Harris County Purchasing Agent’s office will work to obtain the executed contract, and the necessary bonds from the  Contractor so that the project can move forward to construction.  Expect to see about 40 dump trucks per day (8600 loads in total) on the streets of Kingwood.

Money for both of these projects does not come out of the flood bond. It comes from the Harris County Flood Control District Maintenance Budget.

Posted by Bob Rehak on 6/30/19

670 Days since Hurricane Harvey

Tribune Story about Elm Grove Flooding Says Defendants Now Suing Flood Victims

Nothing like kicking people when they’re down. Evidently the defendants feel the victims should have solved their own flooding problems. Read this Tribune story and weep. http://www.ourtribune.com/headlines/22147-suit-filed-in-elm-grove-flooding.html.

HFD high water rescue truck trying to save Kingwood homeowners on May 7th. Perry Home’s subsidiaries and Revel Contractors are now suing the victims.

Posted by Bob Rehak on 6/28/2019

668 Days since Hurricane Harvey

Thoughts expressed in this post represent my opinions on matters of public policy. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP statute of the Great State of Texas.

Where the Flood Mitigation Dollars Have Really Gone: Part 4

The last three posts on the equity flap have focused on how minority neighborhoods in Precinct 1 already receive more flood mitigation funding than affluent areas like Kingwood. Tonight, I focus on why that is likely to continue for the foreseeable future. But first, a recap for context.

Biggest Beneficiary of Funding Claims Discrimination

Last Tuesday, the equity flap erupted again in Harris County Commissioners Court. Precinct 1 Commissioner Rodney Ellis complained that because of historical discrimination (i.e., slavery, which was abolished more than 150 years ago), he needs to fight for “equity” in the distribution and implementation flood bond projects. Precinct 1 already receives the lion’s share of many types of funding.

What Mr. Ellis does not point out to the Commissioners Court is that Precinct One:

Exploiting Past Wrongs to Perpetuate Inequity

When talking about “historic discrimination,” Commissioner Ellis needs to shift his focus forward in time and look at other areas of the county that receive NO such joint projects and far fewer flood mitigation dollars. Take the San Jacinto Watershed, for instance. It contains Kingwood. Because of Kingwood’s affluence, it’s one of the favorite whipping boys for Commissioner Ellis and his surrogates who argue for equity. They keep bringing equity up every time a Kingwood-related item is on the Flood Control agenda at commissioners court. But the Kingwood/Lake Houston Area has NO such joint projects. Why?

Causes of Inequity

There are two reasons for this inequitable distribution: one obvious, one not so.

First, the obvious: The Houston region has grown from the downtown area outward. Precinct 1, which includes downtown, is older. Flood problems became apparent sooner. Precinct 1 documented problems, identified solutions, and rallied Federal support decades ago.

Commissioner Ellis’ predecessors also started this process decades ago and Precinct 1 enjoys the rewards today. As a consequence…

Buffalo Bayou and all of its tributaries are eligible for Corps support on non-emergency projects; the San Jacinto is not.

The Corps is working on Buffalo Bayou and all of its tributaries thanks to legislation passed years ago. The Cypress Creek watershed actually overflowed into the adjoining watershed during Harvey. For a complete Corps presentation on Buffalo Bayou and its tributaries, see this link.

Even though the problems in the Lake Houston Area have been building for decades, the danger didn’t become apparent until Harvey.

At this point, rallying the kind of Federal support that Precinct 1 has historically enjoyed will involve an act of Congress and Presidential approval. Literally. That’s an uphill battle compared to the battle that Mr. Ellis’ projects face.

Political Challenges for San Jacinto Watershed

A local sponsor, such as the City, would have to file an application for a project. Congressional representatives would have to get the President to build it into the annual budget, then include it in the Water Resources Development Act. Both houses of Congress would have to pass the act. The President would have to sign it. And then the government would have to distribute the money. The distribution usually happens in phases, after approval of each phase of a project, such as:

  • Feasibility study
  • Engineering and design
  • Construction, operation and maintenance
  • Changes after construction authorization
  • Changes after construction

It could easily take three to five years just to get the engineering and design phase on a project, such as additional flood gates for Lake Houston.

A second challenge: Mr. Ellis and his surrogates using unfounded “equity” arguments to further handicap and delay flood mitigation in the Lake Houston Area.

Damages in Lake Houston Area

Unfortunately, the sedimentation and conveyance problems on the San Jacinto only became apparent after decades of additional upstream development. That exacerbates flooding by funneling water to the river faster. In recent years, Conroe was the fastest growing city in America.

Then along came the Tax Day, Memorial Day and Hurricane Harvey floods. They deposited an estimated 5 to 10 million cubic yards of sediment in the East and West Forks. Much of that came from sand mines upstream of Lake Houston, which Lake Conroe inundated when it released 80,000 cubic feet per second at the peak of the storm. This further exacerbated flooding by backing water up in the river and drainage ditches.

As a result, the Lake Houston area suffered billions of dollars worth of damage to schools, bridges, roads, homes, churches and businesses during Hurricane Harvey. At least 13 people in the Kingwood Area died as a result of the flood, 12 in ONE senior living complex.

Two Wrongs Don’t Make a Right

Citing historical discrimination that goes back to pre-Civil-War days, Mr. Ellis argues for equity to increase his precinct’s share of flood mitigation dollars and to accelerate projects in his precinct.

As the data shows, his precinct already has far more than its fair share of mitigation dollars. Now, he threatens other areas, property and lives by delaying and usurping their aid.

If any area is underfunded and fighting discrimination now, it’s the Lake Houston Area. Ironically, the discrimination is coming from the Rodney Ellis’ of the world.

I don’t begrudge Precinct 1 a penny of the flood mitigation funds it has received to date. And I admire Mr. Ellis for fighting so hard for his constituents. However, I despise the way he does it.

Mr. Ellis represents one fourth of the people in the county. Yet he cries “equity” and ignores facts to usurp more than half of flood mitigation funding and put his Bond projects at the front of the construction line. I wish he would acknowledge:

  • The inequality that exists in current funding and that is likely to continue for years.
  • That a Kingwood, Humble, Atascocita or Huffman life is as valuable as a life in Precinct 1.
  • Facts.

Ironically, the Lake Houston Area argued for equity in the bond language to prevent the very kind of reverse discrimination that we are now seeing. We need to work together to mitigate flooding everywhere as quickly as we can. This equity flap is fanning racial flames that divide us, perpetuate distrust, delay mitigation, and threaten lives. It’s time to get on with the hard work at hand. Two wrongs don’t make a right.

Posted by Bob Rehak on 6/28/2019

668 Days since Hurricane Harvey

Where Flood Mitigation Money Really Goes: Part Three

Yesterday, the equity flap continued in Harris County Commissioners Court. Surrogates for Precinct 1 Commissioner Rodney Ellis again took the podium to talk about how affluent neighborhoods deprived low-to-moderate neighborhoods of flood mitigation dollars. The argument they use: FEMA prefers buying out high dollar homes to reduce repetitive flood insurance losses.

Commissioner Ellis describes his district as 78% African-American and Hispanic, with another 6% from other minorities. And according to HUD, Precinct One contains many low-to-moderate-income neighborhoods. See below.

Low-to-moderate-income neighborhoods by precinct in Harris County.

Harris County has four precincts; each has roughly the same number of people. In an equitable world, you would expect roughly 25% of the buyouts to be in each district. If there really is a “buyout bias” against low income neighborhoods, you would expect Precinct 1 to have less than 25%. But it doesn’t.

Precinct 1 Gets More Than Its Fair Share of Buyouts

Under the Freedom of Information Act, I requested the number of buyouts in Precinct 1 and other precincts since 2000. Once again, hard data contradicts the self-serving myth. Since 2000, when buyouts began in Precinct 1, HCFCD bought 955 homes in Precinct 1 and 2,413 homes in other precincts.

Precinct One has slightly more than its fair share of buyouts.

So where’s the discrimination in buyouts?

HCFCD is buying out homes faster than ever. To learn more about their process, visit this page. With FEMA funds from Harvey, HCFCD hopes to buy out 1,100 homes in the next few years. By comparison, the District bought out only 2,075 homes in the 32 years before Harvey.

Precinct 1 Gets More Than Its Fair Share of HCFCD Construction

In part one of this series, we learned that Precinct One gets the lion’s share of Harris County Flood Control District construction spending for flood mitigation.

Precinct One receives almost half of all Flood Control District spending on construction, leaving the other three precincts to divvy up the other half.

Precinct 1 Gets More Than Its Fair Share of Federal Benefits

In part 2 of this series, we also learned that five of the six active federally-funded flood mitigation construction projects in Harris County are on bayous that flow through Precinct One. No other precinct comes close to receiving that kind of support. That means Precinct One receives more benefits from federally funded flood mitigation projects than any other Precinct in Harris County.

Based on total estimated contributions when completed. Data source: Harris County 2018 Federal Report.

If Commissioner Ellis or his surrogates have any data to back up their claims of discrimination in flood mitigation spending, they should share it. In every commissioners court meeting they spout the same half truths to bolster their share of flood mitigation dollars. So far, it appears to be working quite well for them. And not so well for residents in other precincts.

Posted by Bob Rehak on 6/26/2019

666 Days since Hurricane Harvey