HUD Clouds Future of Flood-Mitigation Funding in Texas

The U.S. Department of Housing and Urban Development (HUD) has clouded the future of dozens of Texas flood-mitigation projects worth billions of dollars.

HUD has alleged racial discrimination by the Texas General Land Office (GLO), which distributes HUD money in Texas. HUD based its finding of discrimination on complaints by two advocacy groups. The complaints stem from a statewide competition – the first of several rounds of HUD awards relating to Hurricane Harvey.

Now, deadlines for actually spending the money are fast approaching. But the uncertainty created by the racial discrimination allegations is causing entities that won HUD grants to question whether HUD will revoke funding and leave half-completed projects in limbo.

The GLO vehemently denies all allegations of discrimination and points out that:

  • HUD imposed the key rule governing competition for grants now in dispute
  • HUD approved the competition’s scoring criteria
  • More than two thirds of the beneficiaries of the funds are Black and Hispanic
  • 100% of the mitigation projects benefitted communities with a majority of low-to-moderate income (LMI) residents, when only 50% was required
  • GLO and HUD ultimately awarded Houston-area entities about $1.5 billion.

Allegations by Texas Housers and Northeast Action Collective

According to the Houston Chronicle, two advocacy groups (Texas Housers and the Northeast Action Collective) filed charges of racial discrimination after the first round of Harvey grant awards in 2021. They allege that the Houston area got zero dollars and are standing by their accusations, despite all the money the area received at the time and since then. (See amounts in timeline below.)

When developing the competition for Harvey grants, HUD insisted that the GLO could not base awards on actual flood damage. Regardless, Texas Housers and the Northeast Action Collective complained that rural areas received the majority of funding even though Houston and Harris County had the majority of flood damage.

After results of the competition became apparent, GLO attempted to remedy the rural/urban disparity by recommending to HUD that $750 million in remaining Harvey competition funds should go to Harris County – without a second competition. HUD approved.

GLO also recommended increasing the amount going to the Houston-Galveston Area Council (H-GAC) from the Regional Mitigation Program. H-GAC’s allocation more than doubled from $209 million to $488 million – again without a second competition. And again, HUD approved.

Regardless, HUD’s “finding” of discrimination based on allegations by the two advocacy groups still stands. Moreover, HUD issued administrative subpoenas to depose GLO executives, even though the Department of Justice (DOJ) already reviewed the racial discrimination complaints and declined to pursue them.

This mess is like throwing trip wires in front of exhausted marathon contestants.

While GLO defended its actions with more than 1,000 pages of documentation, HUD has reportedly produced only a four-page letter laying out vague generalizations.

HUD has not responded to requests from the GLO or ReduceFlooding.com for specifics regarding the allegations.

Uncertainty, Fear of Clawbacks Slow Progress

After spending years and millions of dollars to win HUD grants, the award winners now face the specter of not having enough money to finish their projects should Texas Housers and the Northeast Action Collective succeed.

Imagine your bank rescinding a mortgage commitment after you bought a lot and began building a new home.

Worse, HUD could try to claw back the money that grantees have already spent. According to GLO, many of the smaller communities awarded grants don’t have the funds to pay back HUD should that happen.

Faced with that kind of uncertainty, some awardees are reluctant to start construction on their projects – even though they face two looming “use it or lose it” deadlines. The first is only three years away – barely enough time to complete many projects.

As a result, the GLO issued a scathing press release last week, accusing HUD of “destabilizing vital funding.”

Timeline: Who Got What, When?

Is all that chaos necessary? Not if you look at the final score as opposed to the first inning. Houston and Harris County received far more than “zero dollars.” See below.

2017: Harvey

Hurricane Harvey strikes Texas. Presidential disaster declaration.

2018: Congressional Action

On February 9, 2018, Congress approves mitigation funds for 2015 and 2016 floods as well as Harvey-eligible areas. Two months later, HUD allocated money to Texas.

2019: Federal Register Notice

On August 30, 2019, HUD finally published the Federal Register notice enabling the State of Texas to proceed in drafting an action plan for the CDBG-MIT funds. GLO then conducted a public outreach campaign and collected thousands of comments from 117 meetings and 936 individuals. 

2020: HUD Approves Action Plan

HUD finally approved the GLO action plan which called for conducting a statewide competition for funding. The scoring criterion included in the state action plan for distribution of the funds was approved by HUD on March 27, 2020.

May 21, 2021: First Awards

The first $1.1 billion was awarded in the statewide competition:

  • Harris County municipalities received $117 million, not “zero” as the Chronicle article and certain local politicians claimed.
  • More than two thirds of the funding went to Black and Hispanic communities, according to the GLO.
  • 100% of the mitigation projects benefitted communities with a majority of low-to-moderate income (LMI) residents.
May 26, 2021: Second Awards

A mere five days later, GLO requested a direct allocation of $1.2 billion without a competition for Harris County and H-GAC. That included:

  • $488 million for H-GAC to distribute to municipalities throughout the region
  • $750 million for Harris County.
March 18, 2022

HUD approves GLO request for second batch of awards. From its $750 million, Harris County will spend:

  • $97.5 million for administration and planning
  • $502.5 million for 2018 Flood Control Bond Projects
  • $100 million for Partnership Projects, i.e., with City of Houston
  • $50 million for Other County Flood Mitigation Projects.
June 6, 2023: Third Award

GLO recently reallocated $322.5 million in unspent disaster relief funds from Harvey to Harris County Flood Control for mitigation projects. This is in addition to $222,519,672 Harris County received in infrastructure funding from the initial CDBG-DR allocation. 

Still, the Chronicle article alleges that the GLO somehow ran afoul of of the Civil Rights Act and Fair Housing laws by giving the Houston area “zero.”

The DOJ took less than 48 hours to review and dismiss the claim. But the continued legal harassment by HUD is distracting the GLO from its vital mission as deadlines loom.

Could this be politically inspired? Two Houston-based politicians running for election next year have close ties to the groups making the claims. More on that in a future post.

Baseless Racial Discrimination Accusations Have Backfired

Despite the vast majority of Harris County flood-control spending since 2000 already going to LMI areas, the baseless charges of racial discrimination seem to have backfired on Texas Housers and Northeast Action Collective.

In one notable instance, the Northeast Action Collective brought more than a hundred members to a Commissioners Court meeting. They pushed the meeting into the wee hours of the next day, repeatedly demanding the resignations of key Harris County Flood Control executives. Since their resignations in 2021 and January 2022, flood control spending has steadily declined – exposing the constituents that the groups represent to more flood risk.

HCFCD Spending by Year since 2000
Data obtained from HCFCD via FOIA request. Covers 1/1/2000 through 3/31/2023.

And the effects are across Harris County. For instance, in the first quarter of this year compared to the fourth quarter of last year, spending was down in two thirds of the county’s 23 watersheds.

watershed spending increases/decreases between 4Q22 and 1Q23
Data obtained from HCFCD via FOIA Request. Only significant increase was in Greens Bayou watershed.

The HUD/Houser/Collective accusations could produce a similar outcome across Texas – backfiring again.

HUD refuses to discuss its allegations of racial discrimination. HUD did not respond to a ReduceFlooding request for an interview, nor would it meet with GLO Commissioner Dawn Buckingham MD.

Posted by Bob Rehak on 7/8/23

2139 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Poor-Farm-Ditch Renovation Funding Finally Secured

On 6/28/23, civic leaders from all levels of government gathered to celebrate the acquisition of enough funding to finally begin renovating Poor-Farm Ditch.

Poor-Farm Ditch runs from Greenway Plaza on the north to Brays Bayou on the south between West University Place and South Side Place. Harris County Flood Control District started studying ditch improvements more than 20 years ago. The 70-year-old, crumbling concrete ditch carries stormwater runoff from 1,330 highly developed acres.

Numerous Problems Associated with Poor-Farm Ditch

Poor-Farm Ditch has several problems:

  • Pieces of the crumbling concrete periodically collapse into the ditch and block it, exacerbating flooding.
  • Erosion threatens homes and businesses, which crowd the ditch on either side.
  • Adjacent properties have been built up as much as five feet. The existing channel walls were not designed to support that much weight.
  • Railroad ties and other earth-retaining features (used to stabilize the extra fill) have failed and fallen into the ditch, reducing its hydraulic capacity by 50% in places.
  • The channel’s width varies along its length, creating choke points in some places. Parts can handle a 100-year rain with room to spare while others can only handle a 10-year rain.
  • Encroachments have been constructed within the Harris County Flood Control District’s (HCFCD) right of way.

Press Conference Celebrates Funding Success At Long Last

U.S. Congresswoman Lizzie Fletcher who secured $9.9 million for the $30+ million project kicked off today’s press conference by thanking all the officials and staff members present.

Left to right: West University Place Mayor Susan Sample, U.S. Representative Lizzie Fletcher, Harris County Precinct 1 Commissioner Rodney Ellis (speaking), Southside Place Mayor Andy Chan, District 134 State Rep. Ann Johnson, HCFCD Exec. Director Dr. Tina Petersen 

Goals of Renovation

According to the funding request filed by Congresswoman Fletcher, the primary goal of the project is to avoid a failure of the existing channel by constructing an entirely new channel structure in its place.

Channel rehabilitation will reduce flood risk by improving hydraulic capacity. It will also improve HCFCD’s ability to provide maintenance.

The construction project will include maintenance access ramps for HCFCD, and reinforced pavement for inspection and “maintenance by foot” on top of the channel banks.

Geographic scope of project. Source: Harris County Flood Control District

In total, the project will benefit 523 structures and 1,036 people.

On-Again, Off-Again Project Finally Finds Funding

As you can see from the pictures below, buildings on the banks of the ditch leave little room for expansion. The project was actually put on hold for two years by Harris County Commissioners Court given lack of funding and lack of consensus support for the improvements among local leaders and residents.

At the time, HCFCD said it would continue to perform spot repairs and debris clearing as needed.

Then in 2021, the project regained momentum. An engineering study concluded it would be necessary to mitigate the impacts of the proposed Poor-Farm Ditch improvements on Brays Bayou by providing 43 acre feet of stormwater detention along Brays Bayou. 

The pictures below illustrate just some of these problems. HCFCD started studying the ditch in 2002. But it has taken until 2023 to raise enough money to address these issues.

Note how close homes and businesses are to the ditch. This turned out to be THE key design constraint. As both Southside and West U policemen told me today, “No one wanted to give up property to improve the ditch.
Foliage over the ditch frequently forms log dams that can make flooding worse if not cleared promptly.
Aging concrete requires frequent repair but access is poor.

Funding Will Come from Five Different Sources

Funding breaks down as follows:

  • $5.7 million from the Harris County Flood Control District
  • $150,000 from the City of Southside Place
  • $150,000 from the City of West University Place
  • $16.9 million from State of Texas
  • $9.9 million from Federal government

That puts the total secured funding at $32.8 million, enough to begin final design, bidding and construction.

Congresswoman Lizzie Fletcher secured a huge win in Fiscal Year 2023 when she obtained a $9.9 million earmark.

But according to inside sources, Southside Mayor Chan, working with State Representative Ann Johnson and State Senator Joan Huffman secured the final funding needed for the project – another $16.9 million. Remarkably, the state earmark wasn’t even in the original budget bill this year, but was added during the conference committee phase!  

Construction will not likely start until at least next year at the earliest according to Mayor Chan.

During the press conference, participants used the phrase “dogged determination” numerous times. To pull off a project like this requires committed partners to coordinate efforts and pursue funding relentlessly from municipal, county, state and federal governments.

Civic leaders from other areas could learn from this team.

How Ditch Got Its Name

The ditch gets its name from a Poor Farm established by Harris County Commissioners in 1894 in what is now West University Place.

Posted by Bob Rehak on 6/28/23

2129 Days since Hurricane Harvey

Some Projects in Flood Bond Likely Won’t Get Done While Others Not in Bond Will

While speaking to a public meeting of the Harris County Community Flood Resilience Task Force, Scott Elmer, the Flood Control District’s new Chief Partnership and Programs Officer, predicted that some projects in the 2018 flood bond likely will not get done because of a funding gap.

Elmer made this remark while discussing a list of projects proposed by Harris County Flood Control District (HCFCD) for funding from grants totaling $825 million from the U.S. Department of Housing and Urban Development (HUD) and the Texas General Land Office (GLO).

The $825 million is the last large pot of money still sitting on the sidelines from Harvey. But it likely won’t stretch far enough to complete all the projects in the bond.

Despite a partner funding gap of approximately $800 million (published in 2021), the $825 million would only reduce the gap by approximately an estimated $420 million. How could that possibly be? For one thing…

Not all projects proposed to GLO were in the flood bond.

Origins of Funding Gap

To understand the funding gap, one needs to start with the structure of the 2018 flood bond. It contained a list of projects totaling almost $5 billion, but voters approved borrowing only half of that. The other half was supposed to come from partners, such as FEMA, HUD, local governments and the Texas Water Development Board.

Then COVID and inflation struck. Supply chain issues and labor shortages drove up the cost of projects approximately 20-30%, according to Elmer.

Meanwhile, not all of the hoped-for partner funding materialized. For instance, Harris County Flood Control District (HCFCD) was hoping for a billion dollars from HUD, added Elmer, but received only $825 million. (The County siphoned off almost a quarter billion dollars for Harris County Engineering and Community Services Departments.)

Some Projects Expand While Others May Be Excluded

Complicating the squeeze between the upward pressure of price inflation and less-than-hoped-for funding, HCFCD added (in some cases) to the scope of projects listed in the bond.

  • For instance, HCFCD originally budgeted the Greens Bayou Mid-Reach Project for $20 million in the bond. But HCFCD lists it at $90 million in the proposed GLO list – a 4.5X increase. The first figure reportedly includes the original phases of the project. The second includes those PLUS others which had been deferred for a subsequent bond.
  • Another example: The Arbor Oaks Stormwater Detention Basin in the White Oak Bayou watershed started out as a $13.3 million project in the bond, but now weighs in at $42.3 million. Its price more than tripled.

A person familiar with the Arbor Oaks project said it could easily be phased, but that it appears some phases (which had initially been deferred) were now recommended for immediate construction.

Lower part of Arbor Oaks area on bottom left. Bridge is on West Little York. Looking SE toward downtown.
Lower part of Arbor Oaks area on bottom left. Bridge is on West Little York. Looking SE toward downtown.

Those two projects alone account for an additional $100 million in scope.

“Use It or Lose It” Deadlines Place Emphasis on Shovel-Ready Projects

The projects recommended on the GLO list largely came from projects which had already been extensively studied and which are near shovel ready. That’s primarily because of two factors:

  • The county took 2-years between GLO’s announcement of a $750 million allocation for Harris County and the County’s submission of a plan for spending the money.
  • Meanwhile, the original HUD deadlines placed on using the money have not slipped. So, HCFCD now has its back up against a “use it or lose it deadline” wall.

If money isn’t spent before HUD deadlines, HUD will take the money back – not just unspent funds, but all funds allocated to incomplete projects. So, say for instance, HCFCD spent $50 million on a project, but had $10 million to go when the deadline arrived. HCFCD would have to give back the $50 million it already spent.

Obviously, the specter of having already-spent funds clawed back by the federal government made “construction readiness” a huge factor in project selection that wasn’t there almost six years ago when Harvey struck.

This means projects given priority by the Equity Prioritization Framework were closer to shovel ready. Presumably, they also helped meet Low-to-Moderate Income (LMI) requirements placed on the HUD funds.

No other large pots of aid dedicated to Harvey remain out there. So, annual programs, such as FEMA’s Flood Mitigation Assistance (FMA) and Building Resilient Infrastructure and Communities (BRIC) represent HCFCD’s best hope to make up the rest of the funding gap.

But the competition for those grants is nationwide. They include all states, territories, the District of Columbia and tribal lands. And Texas applications are handicapped because Texas has not updated its building codes in almost a decade to qualify for BRIC funding – despite an 11-to-1 payback.

Updating Project Cost Estimates to Recalculate Funding Gap

Elmer says he cannot calculate an exact funding gap at this time. “We’re still working on updating all project costs with the inflation estimates,” he said.

Elmer hopes to have a firmer estimate by August when the Flood Control District expects to issue its second flood-bond update this year.

I personally hope that the District’s recent reorganization can help it track such financing issues better in the future. It appears that after years of promising residents that all projects in the bond would be completed, now some may not be…while others that were not in the bond will be.

And I suspect I know whose won’t be.

Posted by Bob Rehak on 6/24/23

2125 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

GLO Announces Regional Mitigation-Project Approvals Totaling $128 Million

Two pieces of good news came out of the Texas General Land Office (GLO) in two days! Yesterday, the GLO announced that both Houston and Harris County met their respective expenditure goals for Harvey disaster-relief funds. Today, Commissioner Dawn Buckingham M.D. announced the approval of more than another $128 million worth of flood-mitigation projects in the region.

This batch of funds includes several major projects in the north Houston region:

  • City of Dayton received $1.45 million for sewer rehabilitation.
  • Liberty County received $21.27 million to develop a master-drainage plan and make drainage improvements.
  • Waller County received $6.7 million for drainage improvements and another $2 million for Prairie View Water Improvements and a Planning study.

Of these, the Liberty County batch stands out for its sheer size. And Liberty County will need it. That’s because of the recently completed Grand Parkway. It cuts a wide arc through the county’s farms and fields. Thousands of acres are currently under development thanks to improved transportation. And they will stress local watersheds, such as the San Jacinto East Fork and Luce Bayou.

Intersection of State Highway 99 (Grand Parkway) and FM1960 shortly before grand opening last year.
Just north of the Grand Parkway, Colony Ridge is doubling in size.

Another Liberty County example.

FM2090 at East Fork of the San Jacinto in Liberty County on May 3, 2021. New development has flooded Plum Grove and areas farther south along the East Fork.

And another.

FM 1010
Also in Plum Grove, FM1010 washed out at Rocky Branch during Harvey and has yet to be repaired.

Scope of HUD/GLO Awards

The GLO awarded the U.S. Department of Housing and Urban Development funds to improve street, water and drainage facilities in Brazoria, Fort Bend, Galveston, Jefferson, Liberty, Matagorda, Nueces, Polk, San Jacinto, and Waller Counties.

This is a separate tranche of money from the Houston and Harris County disaster-relief funds discussed in yesterday’s post.

$128,208,664 will benefit 19 federally eligible infrastructure projects to improve streets as well as water and drainage facilities. The cities of Aransas Pass, Coldspring, Corrigan, Dayton, Freeport, Hitchcock, Iowa Colony, Katy, La Marque, Palacios, Pearland, Richwood, Rosenberg, Shepherd, Texas City, and the counties of Jefferson, Liberty, and Waller will all receive the mitigation dollars.

Difference Between Disaster Relief and Flood Mitigation

Disaster relief dollars help individuals recover from past floods. Mitigation dollars, on the other hand, help strengthen infrastructure against future floods.

According to the GLO, HUD defines mitigation as “Activities that increase resilience to disasters and reduce or eliminate the long-term risk of loss of life, injury, damage to and loss of property, and suffering and hardship, by lessening the impact of future disasters.”

Locally-Led Methods of Distribution

The approvals announced today will filter down to cities and counties through regional councils of governments (COGs), such as the Houston-Galveston Area Council (HGAC).

Through its Regional Mitigation Program, the GLO enabled local prioritization. This local prioritization will have a tremendous impact across multiple regions, according to Commissioner Buckingham.

“Locally-led prioritization of mitigation projects is important because it strengthens critical infrastructure and protects communities against the impacts of natural disasters,” said Buckingham. “At the Texas General Land Office, we are not only helping those in need, but also supporting our communities as they grow.”

Who Will Get What

The table below shows a high-level description and the award amount for each of the 19 projects. For detailed descriptions of each project, click the caption below the table.

For project descriptions, click here.

How the Money Got from D.C. to Texas Projects on the Ground

The Texas General Land Office (GLO) allocated $1,166,997,000 in Community Development Block Grant Mitigation (CDBG-MIT) funds from the U.S. Department of Housing and Urban Development (HUD) for the Regional Mitigation Program. The program aims to reduce the risks and impacts of future natural disasters.

Each Council of Government (COG) with HUD-designated eligible counties developed a method of distribution (MOD) for allocation of funds to units of local governments. Each COG developed its MOD through extensive public participation.

HUD requires that at least 50% of total funds must be used for activities benefiting low- to moderate-income (LMI) persons.

For more information, please visit recovery.texas.gov/mitigation.

Posted by Bob Rehak on 6/20/23

2121 Days since Hurricane Harvey

A First: Houston, Harris County Both Meet HUD/GLO Disaster-Relief Benchmarks in Same Time Period

The Texas General Land Office (GLO) announced today that for the first time ever since Hurricane Harvey, both Houston and Harris County have each met their benchmarks for expending disaster relief funds – in the SAME time period. They may have individually met performance benchmarks before, but never together in the same review period.

Both Harris County and Houston have semiannual expenditure benchmarks in their Community Development Block Grant Disaster Relief funding contracts with the GLO, per HUD guidance. “These milestones were set by the City and County and approved by the GLO to ensure all programs will be completed as timely as possible,” said a GLO spokesperson.

A New Era of Cooperation Yielding Results Already

Dawn Buckingham, M.D., the new GLO Commissioner credits open communications and focused cooperation. “The GLO is dedicated to helping Harris County and the City of Houston put these vital funds to good use.”

GLO Commissioner Dawn Buckingham, M.D., speaking at a joint press conference in March. Others L to R: Harris County Community Services Interim Exec Director Thao Costis, HCFCD Exec Director Dr. Tina Petersen, P4 Commissioner Lesley Briones, P2 Commissioner Adrian Garcia, P3 Commissioner Tom Ramsey PE, P1 Commissioner Rodney Ellis, County Attorney Christian Menefee.

This is good news. In years past, the relationship between Houston, Harris County, GLO and HUD foundered over performance benchmarks, cooperation and communication. But now, new players are in place. And 5+ years after Harvey, the City, County and State all face “use it or lose it” deadlines from HUD.

More Money Hangs in Balance

While the performance benchmarks in question have to do only with unexpended, Harvey-related, disaster-relief funds, much more money hangs in the balance.

The success of the relationship will also affect $750 million in CDBG-mitigation funds and another $322 million in unspent funds that the GLO shifted from expiring projects to Harris County Flood Control District (HCFCD).

Earlier this month, HCFCD presented Commissioners Court with a proposed project list for those funds. HCFCD is reportedly still trying to define the areas benefited by each of those projects before final approval. However, HUD and the GLO seem pleased with both the progress and the collaborative working relationships that have developed.

Everyone seems to respond positively to Dr. Buckingham’s working style – described as “supportive,” yet “results oriented.”

  • Commissioner Adrian Garcia stated publicly, “I want to give a shout out to the GLO and Commissioner Buckingham for her support of Harris County and giving us a degree of trust.”
  • Commissioner Tom Ramsey complimented the fairness of project list, noting that it worked out to about 25% for each precinct. He stated, “job well done by the whole.” 
  • Commissioner Lesley Briones said, “This is so wonderful that we were able to hit reset and really focus on the progress going forward.” 

Nature Provides Its Own Deadlines

It can’t happen soon enough for Harris County residents who live under constant threat of floods. Monday afternoon, Tropical Storm Brett formed in the Atlantic. Another storm with an 80% chance of formation in the next 7 days follows closely behind. That’s up from 50% yesterday afternoon.

National Hurricane Center update as of 10:45AM EDT Tuesday, June 20, 2023

It’s too early to tell with any reliability where/whether/when either of these disturbances will make landfall.

Posted by Bob Rehak on 6/19/2023

2120 Days since Hurricane Harvey and Updated on 6/20/2023 with new storm information and photo.

Harris County Approves $825 Million Flood-Mitigation Project List For HUD/GLO Funds

On June 6, 2023, Harris County Flood Control District (HCFCD) recommended to Commissioners Court a flood-mitigation and disaster-relief project list totaling $825 million. The U.S. Department of Housing and Urban Development (HUD) allocated the funds to Harris County via the Texas General Land Office (GLO). The projects will require another $145 million in local-match funds from the 2018 Flood Bond. Thus, the projects are worth close to a billion dollars.

Commissioners Court unanimously approved the project list with little discussion. Each precinct will receive a relatively equal amount of projects and funding, according to Commissioner Ramsey.

Two Buckets of Money

The money comes in two buckets: Community Development Block Grant Disaster Recovery funds totaling $322.5 million and hazard mitigation funds totaling $502.5 million. HCFCD intends to use both primarily for channel improvements and stormwater-detention-basin projects.

Further, HCFCD has divided its project list into primary and backup recommendations.

Factors Used to Determine Recommendations

HCFCD developed the project list with the following factors in mind:

HUD normally gives priority to projects that help minority and low-income areas. However, the two major buckets have different LMI requirements. They also have different deadlines.

HCFCD must spend 100% of the Disaster-Relief (DR) funds by August 2026. And they must benefit areas where 70% of the residents qualify as LMI (below the average income for the region).

The Mitigation funds have more time and a 50% LMI requirement. No less than 50% of the $750,000,000 – from which the $502.5 is carved – must be expended by January 12, 2027, with the full balance expended by January 12, 2032.

So the DR funds have more urgency attached to them and that list includes projects closest to “construction ready.”

Reason for Backup Projects

According to HCFCD, the project list will likely evolve based on review by GLO, project schedules and project costs. Budgets are estimates based upon today’s dollars. They will change as projects advance. 

Fatal flaws may also become visible as projects advance toward construction. So, HCFCD requested and received permission to substitute alternate projects as needed if the intended projects become non-viable.  

1 Recommended, 1 Alternate Project in Lake Houston Area

The “recommended” list includes one primary project in the Lake Houston Area: Taylor Gully Improvements.

It also includes one project on the alternate list: the Woodridge Village Stormwater Detention Basin, part of which is already under construction.

Locations of HCFCD Mitigation and Disaster-Relief project recommendations

9 Upstream Projects

HCFCD is also recommending nine upstream projects on tributaries that feed into Lake Houston.

Primary recommendations include:

  • Upper Cypress Creek Floodplain Preservation
  • Part 3 of the Kluge Stormwater Detention Basin on Little Cypress Creek
  • Rehabilitation of the Kickerillo Mischer Preserve Channel on Cypress Creek
  • Boudreaux Stormwater Detention Basin Part 1 on Willow Creek
  • Channel Rehabilitation, Batch 5 on the Main Stem of Cypress Creek
  • East and West TC Jester Detention Basins on the Main Stem of Cypress Creek
  • Detention for Channel Rehabilitation on the Main Stem of Cypress Creek, Batch 5

Alternate recommendations include:

  • Boudreaux Stormwater Detention Basin Phase II on Willow Creek
  • Mercer Stormwater Detention Basin on Cypress Creek

Click here to see the full list of projects.

Project-Specific Data Available Soon

The project list does not include information on how much these projects would contribute to flood reduction – either locally or downstream. However, HCFCD expects to post that information to its website before the projects go to the GLO for approval in the coming months.

Partnership-Funding Gap Affected

Likewise, HCFCD did not include with this list an estimate of how much it would affect the partner-funding gap.

Some time ago, HCFCD projected that it could finish all the projects in the flood bond using a combination of:

  • Taxpayer approved funds
  • Partner funds already committed
  • Harris County Toll Road Authority money allocated to the Flood Resilience Trust.

But to finish all the projects in the Flood Bond, HCFCD “phased” some projects. It knew it wouldn’t have enough money to complete 100% of some large projects. So, several phases might have been included and others deferred.

It appears that several projects on today’s list include some deferred phases. So the “partner-funding gap” may not be reduced as much as originally thought. Net: HCFCD may or may not have to look for additional funds. The District expects it will know more after GLO approves the list.

HCFCD must also come back to Commissioners Court by July 18 with an estimate for ongoing maintenance and land management costs for all the projects.

Posted by Bob Rehak on 6/6/2023

2107 Days since Hurricane Harvey

Last-Minute Funding Breathes New Life into Lake Houston Gates Project

The project to install more flood gates on the Lake Houston Dam has resulted in more nail-biting than a Steven Spielberg movie. Perhaps no project inspired more hope among flood-weary home- and business owners in the San Jacinto watershed. Importance is high, but the costs turned out far higher than expected and dollars proved hard to come by.

This morning, however, Dr. Greg Bonnen, chair of the House Appropriations Committee filed a rider to this year’s appropriations bill that will likely get the job done. The rider contains two provisions that affect funding for the gates.

  • Sec. 17.38 (a)(1) on page IX-22 contains $50 million for improvements to the Lake Houston Dam.
  • Sec. 17.38 (b)(1)(2)(3) on page IX-23 contains a provision that lets unexpended balances from previous grants be redeployed, so they can be spent on EITHER gates, a sediment capture pilot project, or sediment removal.
Lake Houston has four small floodgates only capable of releasing 1/15 the rate of Lake Conroe’s gates. New gates would go in the earthen embankment to the right of the old gates and spillway.

Funding Now Close to Expected Costs

According to Houston Mayor Pro Tem Dave Martin, Black & Veatch Engineering estimates the cost of an 11-gate structure to be between $125 and $225 million.

Balancing that on the income side of the ledger are:

  • The remaining Federal funds of the $50 million provided by FEMA early on for engineering, environmental surveys, permits and construction. So far the City has reportedly spent about $5 million on upfront work.
  • An $8 million earmark by US Congressman Dan Crenshaw.
  • $20 million in County funds allocated in the 2018 Flood Bond (Project CI-61).
  • $11 million from the City of Houston in capital-improvement-project (CIP) funds.
  • The possibility of additional CIP funds from this year’s budget.
  • $50 million from 17.38 (a)(1) above
  • Up to another $50 million in State funds left over from a TWDB 2021 allocation in 17.38 (b)(1)(2)(3)
  • Redeployment of some FEMA dredging funds left over from the Mouth Bar Project.

That puts available funding somewhere north of $170 million. Martin says that should be enough to lock in the original FEMA funding and get the project started.

Redeployment of Funds Important

Congressman Crenshaw’s office emphasized that even though some FEMA money will be redeployed from dredging the mouth bar, additional FEMA funds from another FEMA grant will let dredging around the lake continue.

Re: 17.38 (b) above (that second bucket of $50 million in funding from the state) Martin points out that it includes two other important projects: dredging and the sediment trap pilot study. However:

  • The pilot study should not be very expensive and has no firm deadline.
  • Congressman Dan Crenshaw has helped secure additional funding for dredging from a second FEMA grant.

Finally, Martin points out that Black & Veatch is examining options to scale back the number of gates in case construction costs exceed funding if something falls through.

Enough Funding Committed to Move Forward with Confidence

While some uncertainty remains, Martin says the key point is that enough money has now been committed to move forward with confidence. This is a huge improvement over where the project stood just 8 days ago when concerned residents launched a call-in campaign to influential senators and representatives.

Lake Houston Area residents placed thousands of calls to save the project. Two days later, funding was placed in Bonnen’s rider. Martin thanks “ALL who placed phone calls, sent text messages and emailed state officials in support of our gates project.”

Thank you’s also go to all those who played key roles in this up-against-the-center-field wall catch:

  • State Senator Brandon Creighton
  • State Representative Charles Cunningham
  • Lieutenant Governor Dan Patrick
  • State Representative Armando Walle
  • State Senator Joan Huffman
  • House Speaker Dade Phelan
  • House Appropriations Chairman Greg Bonnen
  • Houston Mayor Sylvester Turner
  • US Representative Dan Crenshaw and Kaaren Cambio, his District Director

Several others deserve special thanks:

  • Mayor Pro Tem Dave Martin worked the phones relentlessly and made countless trips to Austin to raise awareness of the project and coordinate the area’s efforts.
  • City of Houston Chief Recovery Officer Stephen Costello convinced FEMA to include social benefits in the cost/benefit ratio (CBR). That raised the CBR to 3.5, making it the highest-rated project in the State of Texas.
  • City of Houston Mayor Sylvester Turner, who called in some favors among Austin influentials to make the project happen.
  • Former State Representative Dan Huberty and Ben Melson, a CoH lobbyist, lobbied extensively over the last few months, working with Martin, Costello and Bill Kelly, the City’s Director of Government Affairs.

Reason More Gates Needed

Additional gates will let the City lower lake water faster as large storms approach, thus reducing flood peaks both upstream and down. That will, in turn, reduce flood risk for thousands of homeowners and businesses, not to mention all the schools that flooded.

But lowering the lake level carries some risk. If it takes too long to lower the lake, storms can veer away before they arrive, wasting water. Narrowing the window between release and the storm’s arrival, raises certainty that the storm will refill the lake.

More gates will also help balance releases from Lake Conroe with those from Lake Houston.

Next Steps

It ain’t over till it’s over. But even though only days are left in this session, Chairman Bonnen’s office said, “The legislature has never failed to pass an appropriations bill.”

More news as the project evolves.

Posted by Bob Rehak on 5/25/2023

2095 Days since Hurricane Harvey

San Jacinto Flood-Mitigation Spending Down 81% in One Quarter

Just when you thought it couldn’t get any worse, it did. On 4/20/23, I reported about a drastic slowdown in the rate of Harris County Flood Control District (HCFCD) spending. Data obtained via a FOIA request indicate that with a few exceptions the slowdown has affected watersheds across the county.

Two thirds saw a decline in flood-mitigation spending last quarter. But the decline in the San Jacinto Watershed, which had the eighth most flood damage in Harris County in the last quarter century, was particularly steep.

The San Jacinto watershed decreased from $1.614 million in the fourth quarter of 2022 to $306,000 last quarter – an 81% decline in one quarter!

Admittedly, that’s over a very small base to start with. But that in itself is a testament to how little flood-mitigation activity there is in Harris County’s largest watershed at this time.

4Q22 to 1Q23 Changes

Comparing the last quarter of 2022 with the first quarter of 2023 shows that spending increased in only eight watersheds: Greens, Luce, White Oak, Armand, Goose Creek, Barker, Vince, and Spring Creek. Spring increased only from $24,000 to $37,000 in the first quarter.

Arranged in order of 4Q22 spending.

Increases totaled only $6.1 million. They were offset by $16.4 million in decreases, for a net spending decline of more than $10 million. Spending totaled only $38 million for the quarter.

San Jacinto Ranking Slips

Below, you can see how each watershed ranked solely on the basis of first-quarter spending.

Watersheds ordered by 1Q23 spending

The San Jacinto watershed slipped to 17th place in 1Q23 (down from 14th when the ranking includes spending going back to 2000).

Spending by watershed since 2000
From 1/1/2000 to 3/31/2023. Data supplied by HCFCD in response to FOIA request.

San Jac had ranked as high as 7th in post-Harvey spending back in mid-2021.

HCFCD construction in the San Jacinto watershed has seen multiyear delays in start dates while other areas received higher priority based on factors unrelated to flooding.

So-called “equity policies” instituted by a majority of Harris County Commissioners starting in 2019 have punished San Jacinto residents. That’s because the watershed contains only 31% low-to-moderate income (LMI) residents and the area is predominantly white. Under the County’s current policy…

“Socially vulnerable” areas with higher percentages of minorities and LMI residents get priority, even if they have less severe flooding.

Damage No Longer a Factor in Allocation

For instance, in five major storms since 2000 (Allison, Tax Day, Memorial Day, Harvey and Imelda), the San Jacinto Watershed had the eighth largest number of damaged structures. It also ranked fourth in the percentage of the population affected by flooding (see below).

When looking at flood incidents as a % of population, the San Jacinto has fourth highest % in Harris County.

Clearly, Hunting and Halls Bayous need all the help they can get. So do Greens and the San Jacinto Watershed. But the San Jac is getting little. Despite the percentage of residents who have flooded. Not to mention that 40% of all businesses in the Lake Houston Area Chamber of Commerce also flooded.

If I hear County Judge Lina Hidalgo, Commissioner Rodney Ellis or Commissioner Adrian Garcia talk about “worst first” one more time, I’m going to send them “GET REAL” cards. What rationale do they offer for ignoring the watershed with the deepest flooding – the San Jacinto?

worst first
Feet above flood stage at 33 gages on misc. bayous in Harris County during Harvey.

Here’s what that 20+ feet of floodwater looked like.

San Jacinto West Fork at I-69 during Harvey

If Judge Hidalgo, Commissioner Ellis and Commissioner Garcia want to see “social vulnerability,” I challenge them to visit Kingwood Village Estates, a complex 1.2 miles from the San Jacinto West Fork that caters to seniors.

Residents trying to escape as Harvey's floodwaters rose
Twelve seniors ages 65 to 95 from Kingwood Village Estates died as a result of Harvey.

I doubt Hidalgo, Ellis and Garcia will take me up on that challenge. So, in the meantime, we need to accelerate flood-mitigation spending – across the board. HCFCD spent just $38 million in the first quarter in the entire county. That’s very close to the spending rate before the 2018 flood bond.

We need to determine the reasons new projects are not starting in a timely way. We’re only 25% of the way through the flood bond. We have plenty of pressing projects waiting.

Policies, procedures, practices and people that subject anyone anywhere to higher-than-necessary flood risk longer than necessary need to change. More on that in a future post.

Posted by Bob Rehak on 4/22/23

2062 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

$750 Million Flood Plan Ignores Flood Risk, Public

Twenty-two months after learning it would receive $750 million from the US Dept. of Housing and Urban Development (HUD) and the Texas General Land Office (GLO) for Harvey Flood Mitigation, Harris County Commissioners finally approved a Method of Distribution (MOD) for the money on 3/14/23.

The MOD must be approved by the GLO and HUD before the county can begin spending the money. However, the plan virtually ignores flood risk and public comments.

What Happened to Flood-Risk Reduction?

The basic purpose of the HUD money, administered by GLO, is to reduce flood risk. The word “risk” appears 490 times in the MOD submission. Only one problem!

The proposed project scoring matrices never mention “risk,” at least not directly.

The plan contains one scoring matrix for Harris County Flood Control District (HCFCD) Projects and another for Partnership Projects.

HCFCD Projects

For the portion of the money going to the Harris County Flood-Control District, the MOD bases funding on:

  • LMI (Low-to-Moderate Income) Population Percentage (35 points)
  • Social Vulnerability (30 points)
  • Population (15 points)
  • Repetitive Flood Loss (20 points)

Unfortunately, giving weight to damages as opposed to risk, gives the same weight to areas that have already been mitigated as it does to areas that have not received a penny.

The MOD also says distribution of flood-control funds will be governed by the Equity Prioritization Framework (even though it doesn’t explain how). The 2022 version of that Framework gives 20% weight in scoring projects to “Existing Conditions.” Existing Conditions refer to the capacity of a channel to manage flood events of different intensities. But that’s as close as the MOD comes to addressing flood risk in project scoring.

Watersheds with a majority LMI population have roughly a billion dollars worth of uncompleted 2018 flood bond projects. With roughly a half billion of the $750 million going to HCFCD, the LMI and SVI requirements put on that portion of the money virtually guarantee that none will be left for more affluent watersheds.

So even though HUD and GLO rules allow 50% of the money to be spent in more affluent watersheds, the criteria adopted by Commissioner’s Court will likely preclude any of the money going there.

Partnership Projects

The portion of the money going to Partnership Projects has slightly different criteria. But that matrix also includes NO references to flood risk. It scores projects based on:

  • Project Readiness (20 points)
  • Percent LMI Population (25 points)
  • Project Efficiency (cost per person and building benefitted) (20 points)
  • Ancillary Benefits (environmental, economic, quality of life) (10 points)
  • Partner Contribution (25 points)

Nowhere did the plan provide direct comparisons of flood risk so that areas with the highest risk could be addressed first. Neither did the plan address flood severity. Thus, areas already mitigated that got one inch of flooding will rank as high as unmitigated areas that got 20 feet.

worst first
Chart showing feet above flood stage of 33 gages of misc. bayous in Harris County during Harvey.

Virtually No One Happy

The Harris County Community Resilience Flood Task Force submitted a letter strongly prioritizing flood-risk reduction. That got ignored as were most of the 235 pages of other public comments submitted.

Virtually no one seemed happy with the plan or the fairness of the distribution of money.

The county did not bother to respond directly to those who took the time to study the plan and submit comments. However, it did provide responses within the plan itself.

To paraphrase one of the generic responses: “Thank you for your comment. Here’s what we’re going to do. The GLO encourages regional and countywide investments in flood mitigation. But we’re prioritizing population in low income and socially vulnerable areas.”

Typical comment and response to proposed MOD. Name of commenter redacted.

Harris County has already spent $1.7 billion on flood mitigation since Harvey – the vast majority of it in LMI areas. There’s no hint of spreading the $750 million around to other areas.

Transparency Issues Also a Problem

The Harris County Community Services Department (CSD) will manage this money. But CSD has a serious transparency problem.

  • The transparency portion of its website hasn’t been updated in six months.
  • The MOD portion of the website hasn’t been updated for six weeks, even though much has changed since then.
  • Potential partners have complained about being in the dark.
  • Two weeks ago, the interim director promised to put out a call for partner projects. But the website still hasn’t announced the opportunities yet.
  • CSD still has not posted the plan approved by commissioners.

CSD’s lack of transparency was a major theme in the hundreds of pages of public comments.

What Next for Flood-Bond Projects in Outlying Areas?

With virtually all of the HUD money going to LMI areas, and with not enough money left in the flood bond to finish all the projects, Judge Lina Hidalgo and Commissioners Rodney Ellis and Adrian Garcia owe us an explanation. How do they intend to fulfill the County’s promise to voters who approved the 2018 Flood Bond thinking they would get something out of it?

Posted by Bob Rehak on 3/29/2023

2038 Days since Hurricane Harvey

Plum Grove, Splendora, Liberty, Others Receive HUD Grants Through GLO

GLO Commissioner Dawn Buckingham, M.D., announced yesterday more than $43 million in HUD grants for 44 infrastructure projects stemming from 2019 Disasters. The $43 million is the combined total of grants made to counties and cities stretching from the Rio Grande Valley to southeast Texas.

Counties where 2019 community development block grant disaster-relief (CDBG-DR) money will be distributed for infrastructure projects.

The infrastructure-project grants will help communities recover from the 2019 South Texas Floods as well as Tropical Storm Imelda, which devastated SE Texas.

List of Recipients

The funds will be used to improve streets as well as water and drainage facilities in:

  • Counties:
    • Cameron
    • Chambers
    • Harris
    • Hidalgo
    • Jefferson
    • Liberty
    • Montgomery
    • Orange
    • San Jacinto
    • Willacy
  • Cities
    • Beaumont
    • China
    • Combes
    • Daisetta
    • La Feria
    • La Villa
    • Laguna Vista
    • Liberty
    • Mercedes
    • Mission
    • Nome
    • Old River-Winfree
    • Orange
    • Palmview
    • Pasadena
    • Pine Forest
    • Pinehurst
    • Plum Grove
    • Port Arthur
    • Port Isabel
    • Primera
    • Rio Hondo
    • Santa Rosa
    • Splendora
    • Vidor
    • West Orange
    • Woodloch 

“Here to Help”

“Consecutive disasters have devastated communities in the Lower Rio Grande Valley and Southeast Texas, but the Texas General Land Office is here to help,” said Commissioner Buckingham. “These critical infrastructure awards will divert floodwaters away from homes, increase the resiliency of communities to respond to natural disasters, and restore peace of mind when the next storm hits.”

Texas GLO 2019 Disaster-Recovery Funds

The Texas General Land Office (GLO) is administering $227,510,000 in Community Development Block Grant Disaster Recovery (CDBG-DR) funds from the U.S. Department of Housing and Urban Development (HUD) related to 2019 flooding. This is separate from the $750 million in mitigation funding related to Harvey and Harris County.

Out of the $227.5 million, GLO allocated $61,430,000 in disaster recovery funds for infrastructure projects. They will assist disaster relief, long-term recovery, and restoration of infrastructure for local communities. The rest of $227 million was allocated to grants that help individuals recover.

GLO announced the opening of the application for eligible counties and cities on March 15, 2022. Applications closed on August 1, 2022. Each applicant was eligible to submit a total of two applications. All activities had to contribute to the long-term recovery and restoration of infrastructure.

The GLO recognizes that repair and enhancements of local infrastructure are crucial components of long-term recovery and viability of communities.

To learn more, visit https://recovery.texas.gov/2018-floods-2019-disasters/programs/2019-disasters-infrastructure-competition/index.html.

Plum Grove Drainage Improvements – $1,000,000

Tropical Storm Imelda released an unprecedented 3-day total rainfall amount of 28 inches on Plum Grove. That limited the city’s ability to provide an immediate response due to the inundation of flood water. As a result, this project will provide much-needed drainage improvements within Orange Branch Creek which is located in the middle of the city and runs from the northeast down to the southeast. The project will install culverts and restore roads.

Splendora Lift Station Drainage Improvements – $596,625

Imelda flooding submerged the Pinewood Lift Station site, as well as its emergency generator and electrical switchgear located at the northern intersection of Pinewood Drive and First Street. Loss of both primary and emergency back-up power led to a sanitary sewer overflow at Pinewood lift station. Vehicular access, including emergency vehicle access, was not possible because of the depth of flooding in the area. This project includes drainage and generator improvements at the Pinewood Lift Station.

Construction will include the following activities:

  • Regrade ditch and install double headwalls
  • Install reinforced concrete pipe culverts under First Street with road restoration and ditch regrading 
  • Install new natural gas generator and automatic transfer switch
  • Install an elevated metal platform, staircase and skid for generator

Liberty Water, Sewer Improvements – $1,000,000

The project will provide for water and sewer line improvements located within the eastern side of the city along Beaumont Road, Minglewood Road, Glenn Street and Tanner Street. These should reduce overflow concerns for residents and businesses along these streets. The project will make improvements to sewer lines and water lines and remove and replace existing lift stations with gravity sanitary sewer lines.

Descriptions of Other Grants

For a full description of other grants in this batch, see the GLO website.

Posted by Bob Rehak on 3/22/2023 based on information from the Texas General Land Office

2031 Days since Hurricane Harvey and 1280 Days since Imelda