Update: Taylor Gully-Woodridge Progress, Contract
6/13/26 – The Taylor Gully-Woodridge Project in Kingwood is now in construction. That’s good news for the hundreds of families who flooded repeatedly, largely due upstream clearcutting for construction.
How Long Will Construction Take and Other Questions
Many have asked me how long the project will take, so I submitted a FOIA request for the contract documents.
The short answer: December 2027 … if all goes according to plan.
Harris County Commissioners approved Brice Construction and Design LLC’s $29.4 million contract in their March 31, 2026, meeting. The contractor has 552 calendar days with another 64 days for inclement weather. That’s 616 days total. From the start of the contract, that would put completion in December 2027. So, we’ll have to go through two hurricane seasons before we see promised flood-risk reductions.
Readers have also asked about the scope of the project, where they will start, and how the contractors are progressing.
Scope of Contract
The contract has two large components:
- Widening and deepening approximately two miles of Taylor Gully.
- Building a 421.6 acre-foot detention basin on the Woodridge Village property.
The County bought Woodridge from Perry Homes in 2021. Part of it was already excavated under a previous “Excavation and Removal” (E&R) contract with Sprint Sand & Clay. Under an E&R contract, HCFCD gives a contractor the right to remove dirt from an area where a detention basin will go for only a $1000. The contractor then makes a profit by selling the dirt for beneficial uses on the open market.
For the detention basin, the current contractor must:
- Excavate an additional 1,002,639 cubic yards of material
- Create a wet-bottom basin with 30-65 foot wide berms and backslope swales
- Construct a limestone aggregate maintenance access ramp
- Build a 30-foot wide bottom shelf
- Establish a 52-foot wide vegetative shelf for wetlands planting
- Construct a wet pool 6 feet deep
- Connect the basin with inflow/outflow culverts to the existing basin at the east end of Woodridge.

For the channel conveyance improvements, the contractor must:
- Lower the existing flow line of the channel by 4 feet by excavating 54,085 cubic yards
- Install 10,306 linear feet of a 20’x4′ concrete low flow channel

The contractor must also build a:
- Concrete maintenance access ramp
- 156-foot-long drop structure at the downstream end of the project
- New clear-span bridge at Rustling Elms to replace the culverts which back water up during floods.

Where They will Start
The contract documents contain a Q&A section with questions submitted by bidders buried in approximately 600 pages.
At least one bidder (we don’t know who) expressed reservations about completing a project of this size in 616 days. HCFCD responded that it expected the contractor to work on both parts of the project simultaneously. See below.

…But Work to Date Has Focused Only on Detention Basin
Regardless, in the first 2.5 months, Brice has focused only on the detention basin.
It took Brice several weeks to mobilize for the job. After being awarded the contract at the end of March, 2026, I first noticed activity on the site around mid-May. That’s when the contractor started breaking up old storm sewer pipe on the site.
Brice then started moving dirt by the first week in June. To see how much work Brice has completed to date, compare the first two photos below.


Brice appears to have:
- Cleaned up the site
- Broken up pipe, which they will likely use later
- Knocked down some trees at the far end of the project area
- Smoothed out the western edge of the pond
- Piled the dirt onsite rather than hauling it away now.
See below.

Meanwhile I saw no work on the Taylor Gully portion of the project.


Contract Documents
If you have other questions, consult the contract documents below. HCFCD sent me all the components of Brice’s contract in a file too large to post. So, I split the file up into the sections below for your convenience.
- GLO Amendment to County’s Agreement adding Woodridge/Taylor Gully to CDBG-MIT Contract on 1/8/2026
- Transmittal from Purchasing to Commissioners for 3/31/26 Agenda Recommending Brice
- Brice Qualifications
- Award Documents
- Bid Check Documents
- Bidding Requirements
- Contract Conditions
- GLO Compliance
- HUD Obligation Summary
- Minimum Wage
- MWBE
- Plan Sheets
- Project Manual
- Reference Docs
- Required Contract Provisions
- Significant Local Presence
- Sourcing
- Special Notice
- Specifications
- Subcontracting Plan
Note: As I post this, FEMA has the Lake Houston Area under a flash flood watch with another 8-12 inches of rainfall possible by Wednesday.
Posted by Bob Rehak on 6/15/2026
3213 Days since Hurricane Harvey


