More Northpark Concrete Poured Today; Expansion Update
10/04/24 – At 3 AM this morning, contractors narrowed outbound traffic down to one lane to begin pouring more Northpark concrete west of the entrance to Kings Mill.
It wasn’t the first pour in the two-mile-long project designed to create an all-weather evacuation route from Kingwood. And it won’t be the last. But together with other improvements, one can finally start to see the finished project taking shape.
The pour continued until early afternoon. Elsewhere along Northpark, one could see other workers installing asphalt underlayment for future concrete pours and working on lateral drainage where it ties into culverts down the center of the road.
Next Steps
Contractors are also getting ready to bore under the UnionPacific Railroad Tracks, Loop 494 and Northpark itself. The bore(s) will connect via a series of junction boxes to “Ditch One” behind Public Storage and Dunkin’ Donuts.
From there, the ditch will carry excess stormwater to Ben’s Branch and the Kingwood Diversion Ditch.

Pictures Taken 10/4/24
I took the following pictures of more Northpark concrete being poured around 10 AM this morning.




Plans also call for widening 494. It too will become three lanes in each direction. See below.

More Northpark concrete should be poured next Friday – 10/11/24. Again, it will happen between approximately 3 AM and 1 PM and should involve the closure of at least one lane.
Also of note: on the last weekend of October, there will be a full closure of Northpark at the Russel Palmer intersection to place paving across the intersection. This will begin on Friday and completely close the intersection until Monday morning 5AM. Detours will be in place for Russel Palmer traffic.
For More Information
Consult the Lake Houston Redevelopment Authority project pages including a new 3-week lookahead schedule posted today.
For a history of the project and its goals, see these ReduceFlooding posts:
- 24/10/02 Lane Closure for Upcoming Concrete Pour
- 24/09/16 Pictures of First Concrete Pour
- 24/09/13 Northpark Crews Begin Pouring Concrete Monday, Road Narrowed
- 24/08/18 Northpark Drive Construction Sequence Changing
- 24/08/08 Northpark Drive Expansion Project Overcoming Hurdles
- 24/06/21 Northpark Expansion Obstacles Finally Being Addressed
- 24/04/21 Northpark Floods at Russell-Palmer Road
- 24/04/19 Entergy Makes Some Progress on Northpark but Significant Issues Remain
- 24/04/07 Northpark Entergy Saga: New Power Poles Slowly Going Up
- 24/04/02 New Entergy Power Poles Finally Arrive on Northpark
- 24/03/29 Northpark Expansion Update; Still No Sign of Entergy
- 24/03/16 First Concrete Poured for Northpark Expansion
- 24/03/09 Entergy Ignores City Deadline to Move Power Lines
- 24/03/08 TXDoT, LHRA Engage Kingwood at Northpark Phase II Meeting
- 24/03/05 Details of Phase II Meeting
- 24/02/27 February ’24 Northpark Expansion Update Including Lane Closures
- 24.02/24 Save the Dates: Public Input Meetings for Diversion Ditch, Northpark Expansion Phase II
- 24/02/20 Entergy Escalates Battle with COH over Northpark
- 24/02/16 Excavation of Second Northpark Detention Basin Well Underway
- 24/02/10 Entergy in City’s Crosshairs, Lane Closures Announced
- 24/02/02 Northpark Tree Transplantation Finished, Drainage Updates
- 24/01/13 Excavation of Northpark Detention Basins Starts
- 24/01/07 What Some Utilities Don’t Understand About the Northpark Expansion Project
- 24/01/04 Northpark Tree Moving Starts; Pond Excavation Next
- 23/12/03 Northpark Expansion Presses Forward While Fighting Entergy Obstacle
- 23/11/17 Contractors Strike Oil at Entry (Illegally dumped years ago)
- 23/11/05 City Approves Northpark Expansion Agreement with Union-Pacific.
- 23/10/26 Project moving forward on multiple fronts
- 23/10/12 Transplanting first tree
- 23/10/02 Clearing of south-side entry for second pond
- 23/09/30 Clearing north-side entry for first pond
- 23/09/23 How plan balances flood mitigation, costs, saving trees
- 23/09/02 New entry design, change in construction plans forced by utility conflicts
- 23/08/17 More drainage for Northpark
- 23/08/02 Ditch clearing stretches halfway to 59 in less than week
- 23/07/25 Northpark construction starts in earnest
- 23/04/13 Groundbreaking
- 22/02/19 Update on expansion project
- 21/07/28 Plan details
Posted by Bob Rehak on 10/4/24
2593 Days since Hurricane Harvey