HCFCD 2026 Q1 spending

Showdown Over Slowdown at HCFCD

6/8/2026 – In their 6/11/2026 meeting, Harris County Commissioners will revisit the future employment of Harris County Flood Control District (HCFCD) Executive Director Dr. Tina Petersen, PhD, PE. The immediate issue: slippage of 11 CDBG-DR projects that could cost the county $322 million if they miss their deadlines on February 28, 2027.

Roughly 84% of the time for those has elapsed with less than 4% of their budgets expended.

GLO Data as of 6/3/26

Despite deadlines only a little more than eight months away, the projects typically take 1-2 years to construct.

HCFCD also expects to miss deadlines on 13 of 18 CDBG Mitigation Projects (CDBG-MIT) worth another $362.7 million dollars. But that deadline is 3/31/28.

Precinct 3 Commissioner Tom Ramsey PE has sounded the alarm for months about this problem. So, has the Texas General Land Office (GLO), which administers HUD funds in Texas.

Predictably, the parties involved are offering their own versions of how we reached this point. Dueling press releases today differed starkly.

The GLO says HCFCD promised it “shovel-ready” projects.

On the other hand, HCFCD calls them “complex, large-scale flood risk reduction projects under strict federal timelines, evolving program requirements, construction market pressures, and funding structures that were not originally designed for this level of accelerated delivery.”

Unusual 5-Part GLO Press Release

The GLO issued a five-part press release, unusual in its detail. There was:

  1. The press release itself
  2. An open letter to Harris County Judge Lina Hidalgo
  3. Photographs of 11 projects supposedly under construction, only three of which were actually moving dirt.
  4. Timeline of critical events during the life of the CDBG-DR Program (the one with the most pressing deadline).
  5. A list of “Failures” by HCFCD.

The GLO press release summarized the letter to Hidalgo. It quoted GLO Commissioner Dawn Buckingham as saying Harris County needed “Shovels, Not Scapegoats.”

The press release also said that, “We have grave concerns about Harris County Flood Control District (HCFCD) not meeting its benchmarks…” It went on to say that if the county didn’t change its business processes…

“…there is likely zero chance of successfully meeting the grant timeline established by the U.S. Department of Housing and Urban Development.”

Dawn Buckingham, GLO Commissioner

Buckingham stated that the GLO spent more than $5 million of its own grant funding to teach HCFCD about grant requirements and provide technical support with grant applications. The GLO claims its team conducted more than 750 meetings “to provide staff support to Harris County to ensure these projects are completed on time in accordance with the federal deadline, yet there are still too few shovels in the ground.”

Commissioner Buckingham concludes her letter by saying, “It’s time to … finish the job. Shovels, not scapegoats.”

Click here for the:

Later in the day, GLO also provided an update on reimbursable expenditures to date associated with CDBG-DR and MIT projects.

Page 15 of 18 shows that with roughly 84% of time elapsed, HCFCD has spent only about 3.9% of available DR funds.

Page 11 of 18 shows that HCFCD has spent only 4.4% of available MIT funds.

HCFCD Paints Rosy Picture Despite Obstacles

The GLO press release this morning emphasized that in 2023 projects were supposed to have been shovel ready. HCFCD’s press release this afternoon never mentions “shovel ready.” Instead it paints a nightmare picture of impossible complexity before claiming it has, ta da, a “plan” to solve the problem.

HCFCD will unveil its new plan to commissioners on Thursday. According to HCFCD, it “protects federal funding, maintains and strengthens our commitment to communities, and ensures residents receive the flood risk reduction benefits these programs were designed to deliver.”

HCFCD had planned a press conference tomorrow to explain the plan to reporters, but cancelled it late today.

Proposed Solution

While details of the plan have not yet been divulged, in principle, GLO, Commissioners, and HCFCD agree on the following outline. It involves:

1) Putting all CDBG-DR and -MIT projects in one giant “budget bucket,” including some funds still at Harris County Housing and Community Development.

2) Billing everything possible from that giant bucket against the DR budget before the 2/28/27 deadline.

3) Billing the rest against the MIT budget, which has a 3/31/28 deadline.

This approach at least kicks the can down the road past the next election. However, Buckingham cautions that the 2/28/27 deadline is firm. Without taking a position on Petersen’s employment, GLO does warn that HCFCD and the County need to move much faster.

Thursday’s Decision on Petersen

GLO’s list of Harris County “failures” is unambiguous. Ramsey can elaborate on them at length and provide examples. Despite extensive support provided by GLO, they include:

  • Missed deadlines
  • Reprioritizing projects repeatedly
  • Submitting incomplete or inaccurate documentation that failed to adhere to federal grant regulations
  • Failing to respond to GLO requests regarding federal grant processes
  • Significant employee turnover and loss of experienced staff capacity
  • Failure to achieve timely engineering design, environmental clearance, procurement, vendor contracting and construction starts…

HCFCD’s own spending data shows that its slowdown cuts across project phases, types of projects, and funding sources. For the graph below, you can see that problems go far beyond CDBG, GLO and HUD.

The downturn coincides with a change in management at HCFCD.

HCFCD 2026 Q1 spending
HCFCD spending over time. Petersen took over in 2022 after Democrats started pushing out the previous management team in 2021.

Changing Horses in Midstream

Petersen supporters argue that it could be dangerous to change horses in midstream, especially now that the immediate crisis seems to be solved with the “one big bucket” plan, at least temporarily.

But her opponents argue that staying with the status quo carries the larger risk. They argue that poor performance during a crisis may be a reason for change, not a reason against it.

In my opinion, the real question is not whether you’re midstream, but whether the current horse is still the best one to get you across.

Posted by Bob Rehak on 6/8/2026

3205 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.