- Athletic fields and structures – 70%
- Concrete masonry 65%
- Rough electrical – 80%
- Rough mechanical – 80%
- Rough plumbing – 90%
- Insulation – 75%
- Windows – 65%
- Interior metal studs – 85%
- Exterior paint – 50%
- Curtain wall – 65%
- Exterior storefront – 90%
- Concrete paving, parking lot and driveways – 95%
- Gas service – 90%
- Water service – 80%
- Sidewalks – 45%
- Interior gypsum board – 65%
- Interior paint 20%
- Ceramic tile – 10%
- Sorters Road storm drain – 90%
- Rough grade – 75%
Aerial Photos from 3/13/22
Here’s what that looks like. Aerial photos show the exterior of the main building and athletic facilities rapidly nearing completion.









Compare with Previous Updates
To see how the project has progressed, compare these previous posts.
- June 2020
- August 2020
- September 2020
- January 2021
- March 2021
- May 2021
- July 2021
- August 2021
- November 2021
- February 2022