New Caney ISD’s West Fork High School Blocked Out; Access Being Enhanced

Although much finish work remains, contractors have finished blocking out New Caney ISD’s new West Fork High School. Walls, structural steel and roofs are up. Some windows are in. Now they are widening Sorters-McClellan Road. They are also building another access route through woods that will connect to Kingwood Place Drive, the street immediately west of the HCA Kingwood Medical Center.

Photos Taken 11/6/2021

I took all of the shots below on November 6, 2021, with the exception of the last one from November a year ago.

New Caney ISD West Fork High School Construction as of 11/6/2021. Looking NE from over Sorters-McClellan Road toward HCA Kingwood Medical Center and Insperity in top center.
Looking south from over Sorters-McClellan Road, which is apparently being widened in front of the high school and then some. Note the wetlands and cypress trees in the upper right.
Looking north from over detention pond at south end of campus. I-69 in upper right.
Fieldhouse, track and football field.
New access road through woods will connect with Kingwood Place Drive
Looking south. Note windows being installed in center.
Looking SE. Much sitework remains.
From a higher altitude, you can see the proximity to the San Jacinto West Fork. From the upper left, it curves around the large pond then becomes visible again to the left of the sand mine in the upper right.

Wetlands Gone Forever

From US Fish and Wildlife Service Wetlands Mapper. Green areas are/were freshwater forested/shrub wetlands. Blue/gray areas are freshwater ponds. High school site is in center of frame. Image taken shortly after clearing. Note large area of former wetlands where athletic fields will be.

I’m sorry to see the wetlands go, but now that they’re gone, I want to see them complete the drainage for this campus ASAP to make sure everything gets channeled into the detention pond. That will minimize the chance of flooding neighbors.

Progress in One Year

New Caney ISD has posted an update on construction that indicates the percentage of completion for each of the project components as of October 29.

It was just a year ago, that this site was virtually nothing but dirt. Contractors had just started pouring concrete for the first parking pad.

From Nov. 13, 2020.

New Caney ISD expects to finish construction by the summer of 2022.

General plan for New Caney High School #3

Posted by Bob Rehak on November 8, 2021