Guide to Lake Houston Area Floodplain Regulations

Guidelines for floodplain development can bewilder even professionals. Overlapping jurisdictions often have different guidelines.  And guidelines often change, as Houston’s just did. Houston now manages the 100-year and 500-year floodplains differently. Cities also have building codes that include more requirements.


Site of the proposed new marina and high rise development. Shot from over the West Fork shortly after Harvey. Note sand deposited by Harvey. 25 and 50-story high-rises would be built on the narrow strip between the lake and the Barrington at the top of frame.

Overview

People ARE generally allowed to build and place fill in floodplains. However, they must follow local floodplain guidelines and obtain permits that restrict what they can do. They must also submit environmental surveys, mitigate wetlands, and provide hydrologic and hydraulic studies. In Houston, they may move earth from one location to another within a floodplain, but not add to the total volume. The general rule of thumb: zero negative impact on the conveyance of the river.

If a development destroys wetlands, wetland credits must be purchased from a mitigation bank. Mitigation banks place conservation easements on some of our most valuable wetlands. By helping to finance conservation of those areas, destruction of less valuable wetlands elsewhere may be permitted. Generally but not always, the mitigation credits must be within the same watershed. However, this is not always the case. Extenuating circumstances may exist.

KSA once considered placing East End Park in a mitigation bank as a way to help finance its long range parks plan. The conservation easement would ensure that the character of the park never changed. And the money raised would have provided needed improvements to other parks at no cost to residents.

Federal Guidelines and How They Relate to Local

FEMA establishes minimum standards for a community to enroll in the National Flood Insurance Program (NFIP). By enrolling and administering floodplain regulations, it allows their residents the opportunity to purchase Flood Insurance through the NFIP. You must at least build at FEMA’s base flood elevation (BFE). But communities can and do set higher standards. And each may have different guidelines.

Engineers and regulators often talk about “freeboard factors.” Freeboard, a nautical term, means “the height of a ships side between the waterline and the deck.” In a flooding context, freeboard means minimum elevation above the BFE. You often see it described as “BFE + 1 ft.” Or 2 feet. Or X feet. Think of it as a safety margin. Any freeboard above the BFE is considered a local community’s higher standard.

To provide a context, below are links to some of the floodplain management orders/ordinances.

Houston Guidelines

HOW Ordinance is Executed

Note Chapters 9 and 13. They changed on September 1, 2018. Changes address building code issues for FEMA X zones. Zone X includes the 500 year flood plain. Many such areas flooded during Harvey.

Humble Guidelines

Flood Damage Protection Ordinance

Harris County Guidelines for Unincorporated Areas

Main Website

Laws

Cheat Sheet: Quick View of Changes Implemented in January

Montgomery County For Unincorporated Areas

Floodplain

Drainage Manual For Commercial Developments Greater than 15,000 SF 

Army Corps

If a development affects a major waterway like the San Jacinto River, its wetlands, its flow, or endangered wildlife, the Army Corps will also review studies submitted as part of the permitting process. They would look at applications from the point of view of the EPA and Clean Water Act, especially Section 404.  Section 404 of the Clean Water Act (CWA) establishes a program to regulate the discharge of dredged or fill material into waters of the United States, including wetlands. … For most discharges that will have only minimal adverse effects, a general permit may be suitable. This is the major focus of the permitting process now underway for the high-rise development in Kingwood.

TCEQ

The Clean Water Act also contains a section 401.  It specifically focuses on how States and Tribes can use their water quality standards in Section 401 certifications to protect wetlands. States and Tribes can review and approve, condition, or deny any Federal permits or licenses that may result in a discharge to waters of United States within their borders, including wetlands. States and Tribes make their decisions to deny, certify, or condition permits or licenses primarily by ensuring the activity will comply with applicable water quality standards. In addition, States and Tribes look at whether the activity will violate effluent limitations, new source performance standards, toxic pollutants restrictions and other water resource requirements of State or Tribal law.

Jurisdictional Divides

The Houston ordinance only applies to Houston’s jurisdiction. Houston does not influence neighbors and cannot control or force their policies on other jurisdictions. That is important since Kingwood is surrounded by Humble, unincorporated Harris County (Atascocita and Huffman), and unincorporated Montgomery County.

The Key

Understand that if a developer/individual meets the requirements identified in the floodplain ordinance(s), they can develop in the floodplain (including the floodway). Floodplain administrators must follow the law. However, they try to discourage dangerous floodplain development by “working to rule.” By strictly following all rules with no wiggle room, floodplain administrators can drag permitting processes out. A knowledgeable floodplain administrator can find problems with plans, surveys, and engineering reports for years. By requesting revisions, they can make life so difficult for applicants that it affects the economics of their developments. Eventually they may decide that a project falls into that great black box called “too hard to do,” and walk away.

Words of Wisdom

A regulator told me today that the more people who protest a permit, the harder they are to ignore.

If you have concerns about the high rise development in Kingwood, make sure you register them with the Army Corps (which is currently reviewing the permitting from a CWA 404 perspective). The deadline: January 29.

Comments and requests for additional information should reference USACE file number, SWG-2016-00384, and should be submitted to:

  • Evaluation Branch, North Unit
  • Regulatory Division, CESWG-RD-E
  • U.S. Army Corps of Engineers
  • P.O. Box 1229
  • Galveston, Texas 77553-1229
  • 409-766-3869 Phone
  • 409-766-6301 Fax
  • swg_public_notice@usace.army.mil
Posted By Bob Rehak on January 9, 2019
498 Days Since Hurricane Harvey

Army Corps Permit Evaluation Process

The post about the proposed high-rise development in the floodplain/floodway of the San Jacinto River received thousands of views and hundreds of comments. I’ve also received lots of advice including two presentations by concerned residents. The presentations linked below discuss the Corps’ permit evaluation process.

Warning: NOT for the feint of heart. Together they contain more than 300 pages! Frankly, permit evaluation is far more complex than I imagined.

Site of proposed marina after Harvey. Fresh sand deposits reached almost five feet in height. River Grove Park is beyond this, to the right of the giant sand bar which the Army Corps just dredged through. The drainage ditch it blocked drains the western third of Kingwood.

Plea for Expert Advice

I’m publishing the presentations here because thousands of engineers, project managers, and lawyers with technical backgrounds live in the Lake Houston area. With your help, I’m hoping we can sort through the material and determine a productive response to the Corps’ Public Notice.

As you review these, keep in mind what the Corps wants: “to solicit your comments and information to better enable us to make a reasonable decision on factors affecting the public interest.” The Public Notice goes into great detail about the scope of the project but focuses largely on the environmental impact of introducing “68,323 cubic yards of fill material into 42.35 acres of wetlands and an estimated 285 cubic yards of fill material into 771 linear feet of streams adjacent to the West Fork San Jacinto River.”

Key Elements of Solicitation

Other key points to consider in the Public Notice include:

  • “A preliminary review of this application indicates that an Environmental Impact Statement (EIS) is not required. Since permit assessment is a continuing process, this preliminary determination of EIS requirement will be changed if data or information brought forth in the coordination process is of a significant nature.”
  • They say, “Our evaluation will also follow the guidelines published by the U.S. Environmental Protection Agency pursuant to Section 404 (b)(1) of the Clean Water Act (CWA).”
  • “The TCEQ is reviewing this application under Section 401 of the CWA and in accordance with Title 30, Texas Administrative Code Section 279.1-13 to determine if the work would comply with State water quality standards.”
  • “The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts, of the proposed activity on the public interest.”
  • They then define the public interest as: “All factors, which may be relevant to the proposal, will be considered: among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shore erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs and, in general, the needs and welfare of the people.”

Background Information on Corps’ Permit Evaluation Process

The first presentation sent to me describes the Corps permitting process and requirements to the Society of American Engineers.

The second goes into additional detail about the Corps regulatory program and how they make decisions. They developed it for a TxDOT conference.

I pray that people, their property, and their safety count for as much as birds and fish in this process. However, I’ve talked to several birders lately who are abuzz about eagle spottings near the project site.

All of us are smarter than any one of us. Please help!

Submit Comments

Remember comments are due by January 29, 2019. If no comments are received, the Corps will assume there are no objections to the project. To submit comments: Reference USACE file number, SWG-2016-00384, and send to: 

  • Evaluation Branch, North Unit 
  • Regulatory Division, CESWG-RD-E 
  • U.S. Army Corps of Engineers 
  • P.O. Box 1229 
  • Galveston, Texas 77553-1229 
  • 409-766-3869 Phone 
  • 409-766-6301 Fax 
  • swg_public_notice@usace.army.mil 

Posted by Bob Rehak on 12/30/2018

488 Days since Hurricane Harvey


Corps Finishing Touch-Up Dredging at River Grove, Moving Downriver

Good news for residents. Last week, the Army Corps of Engineers and its contractor, Great Lakes Dredge and Dock, finished dredging the area up to the boat dock at River Grove Park. However, because of the size of the hydraulic dredge, it could not quite finish the job. So on Monday, the contractor returned with mechanical dredging equipment to work in the tight drainage ditch area by the boat dock. See the photo below courtesy of Don Harbour.

Mechanical dredging equipment was able to maneuver into the tight location that the hydraulic dredge could not. Photo courtesy of Don Harbour, a local resident.

The Kingwood Service Association also requested the Corps to reduce the angle on the edge of the remaining side bar. Young people frequently played on the bar. Community leaders were concerned that a cave in near the steep edge could cause a bad accident.  

Contractors scraped back edge of sand bar to prevent cave-ins caused by curious kids.

As you can see from the edge of the bar in the photo above, the Corps has addressed that issue. 

This afternoon when I visited the park, I saw a survey boat checking to ensure the contractors had reached the proper depth.

Survey boat checks for proper depth while mechanical dredge stands by.

Multiple Activities Create Hazards for Recreational Boaters

The River Grove area today was busier than Santa’s workshop on Christmas Eve. However, the main focus of dredging activity will soon move east. Dredge #1, operated by subcontractor Callan Marine is now working close to the West Lake Houston Parkway Bridge. Dredge #2, operated by Great Lakes, is now operating just east of River Grove (see point #4 in photo below).

The river is busy. Stay off it for your own safety.

From the boat dock today, I saw five different clusters of activity in different areas: 1) survey boat, 2) mechanical dredge, 3) debris removal on far side of river, 4) Hydraulic dredge moving towards the country club, and 5) a back hoe removing vegetation from the triangular sand dune  in the distance.

Both dredges will continue to work their way east until they reach their respective goals. 

Latest Schedule

The Corps’ schedule originally called for completion in mid-April 2019. However, crews have been delayed by recent storms and floods, as well as greater than expected sedimentation in the river. Their most recent schedule calls for completion by April 30 and demobilization during the first two weeks of May.

Status of Mouth Bar Project Still Uncertain

Everyone I talk to hopes FEMA and the Corps will grant approval for a second project that addresses the huge sand bar at the mouth of the West Fork before this project reaches completion. If that does not happen, demobilization and remobilization at a future date would cost about $18 million. 

The “Mouth Bar,” a giant sand bar that blocks the West Fork of the San Jacinto, backing the river up into Kingwood and Humble. The mouth bar is not within the scope of the current Army Corps dredging project, but officials have been trying to get FEMA and the Corps to include it. Water depth is generally 1-3 feet around this bar. Max channel depth in places is just 5 feet.

Sources in Austin expected an announcement weeks ago on the mouth bar. Congressman Ted Poe requested a meeting with the head of the Army Corps to discuss the project. However, the  meeting originally scheduled for November 28th was delayed into next year. That means Congressman-elect Dan Crenshaw will inherit the battle. Meanwhile, Senator Ted Cruz has thrown the weight of his office behind the effort to dredge the mouth bar.

Corps to Meet with Super Neighborhood Council Wednesday Night

Eduardo Irigoyen, the project manager of the Emergency West Fork Dredging Project (the dredging currently underway), will meet with the Kingwood Super Neighborhood Council tomorrow night. The meeting at the Kingwood Community Center starts at 7PM. Mr. Irigoyen will update local leaders on the status of the Corps’ project. The meeting is open to the public, but seating is very limited.

Posted by Bob Rehak on December 18, 2018

476 Days since Hurricane Harvey

Additional Dredging on the Horizon in 2019

Reprinted verbatim from Council Member Dave Martin’s announcement:

The “Mouth Bar,” a giant sand bar that blocks the West Fork of the San Jacinto, backing the river up into Kingwood and Humble. Water depth is generally 1-3 feet around this bar. Max channel depth in places is just 5 feet.

Houston, TX – Council Member Martin would like to make District E residents aware that the City of Houston continues to make progress towards Harvey Recovery with both state and federal agencies. Over the last fifteen months Council Member Martin has been working diligently with Chief Resiliency Officer Stephen Costello, Mayor Sylvester Turner, Governor Abbott, Chief Nim Kidd, as well as the offices of Senator Ted Cruz and Senator John Cornyn towards several initiatives that would have a positive impact on the Lake Houston Area.

Most recently the Texas Water Development Board (TWDB) has completed the bathymetry study of the West Fork of the San Jacinto River for the City of Houston. Data from this study has been given to the Army Corps of Engineers (ACOE) to determine the amount of sediment that resulted from Hurricane Harvey. This information is useful because this study identifies underwater topography allowing the City to understand where the additional sediment brought in by Hurricane Harvey has been deposited in the river and lake as well as changes in depth.

The TWDB continues to survey the entire lake for the Coastal Water Authority (CWA), the agency that contracts with the City for management of the Lake Houston Spillway Dam. The schedule for the TWDB to complete their survey of Lake Houston is Summer 2019. In addition to conducting a bathymetric study the City of Houston is currently reviewing data collected by the ACOE during a recent Light Detection and Ranging (LIDAR) study which uses light in the form of pulsing lasers to measure the distance from the water’s surface to the bottom of the river and lake. Capacity losses due to sedimentation in the lake as well as East and West Forks of the San Jacinto River will be determined using the LIDAR data along with the completed bathymetric study once the TWDB has completed their survey and report.

The LIDAR study allows the City to map changes in shoreline as well as make digital elevation models. It is this data that is assisting the City and ACOE in determining the amount of sediment that needs to be removed from locations along the West Fork of the San Jacinto River like the “mouthbar” that is located just south of the Deerwood Country Club. The LIDAR Study results will also be used by the Harris County Flood Control District (HCFCD) for the creation of new flood insurance rate maps because of the changing rainfall patterns published by the National Oceanic and Atmospheric Administration. The flood insurance map study will utilize updated LIDAR surveys of the entire county and will take several years to complete, however HCFCD is already hiring consultants to assist with this work.

On October 11, 2018, Council Member Martin met with Governor Abbott’s Executive Staff, TDEM, FEMA, and ACOE in Austin where a lengthy discussion was had about the amount of sediment deposit that will still remain in the San Jacinto River after the current emergency dredging project is completed. The current emergency dredging contract is not scheduled to be complete until the end of April 2019. At this meeting the City’s consultant estimated that after the completion of the existing dredging project that there will be approximately 500,000 cubic yards of additional sediment that needs to be removed from the river known in the community as the “mouthbar”.

This estimate however was based on a comparison between the LIDAR study completed by the ACOE this year and a bathymetric study completed by the TWDB in 2011. The important takeaway from this meeting in October is that FEMA agreed that the additional sediment qualifies as Harvey debris however, the estimate of 500,000 cubic yards was not a true amount directly associated with Hurricane Harvey. The City does not have survey data that is immediately pre and post-Harvey which would provide us a true amount of residual sediment that is a direct result of Hurricane Harvey. The City is currently waiting on the ACOE to complete its analysis of the City’s data.

At the meeting in Austin the ACOE indicated that an additional disposal site would be needed in order to remove the additional material. As a result the City of Houston has been proactive in identifying a site, thanks to the assistance of a local landowner that has property on the south side of the West Fork of the San Jacinto. The land owner has retained an environmental consultant to determine any possible wetland issues that may prevent use of the property for disposal. As of right now it appears the property is a viable site and a formal permit was filed with the ACOE this week.

In summary, the process to have the “mouthbar” removed from the West Fork of the San Jacinto River has been an arduous one. All parties from local, state, and federal agencies have been working together to accurately define the area needed for additional removal so that capacity can be restored to the river and reduce the effects of future flooding. The removal of the “mouthbar” cannot begin until the existing emergency dredging along the West Fork of the San Jacinto River is completed. Since this is a reality the City is doing all that it can to be proactive in securing land as well as permits for the “mouthbar’s” removal once the existing project is completed by the ACOE in April. This will allow the ACOE to keep equipment and crews in place without the need for demobilization and remobilization, saving roughly $18 million.

In observance of Thanksgiving the District E office will be closed Thursday, November 21 and Friday, November 22. The District E team will return to the office on Monday, November 26. Council Member Martin would like to wish all District E residents a safe and happy Thanksgiving holiday. For more information regarding this release, please contact Council Member Martin’s office at (832) 393-3008or via email at districte@houstontx.gov.

-end-

By Dave Martin’s Office on 11/21/2018

449 Days Since Hurricane Harvey

New Difference Map Confirms Buildup of West Fork Sediment Around Mouth Bar, Underscores Need for Removal

A new “difference map” published by the Texas Water Development Board (TWDB) shows the rapid build up of sediment in the West Fork of the San Jacinto River where it meets Lake Houston. Difference maps show changes in sediment levels over time.

When Stephen Costello, Chief Resiliency Officer for the City of Houston, presented this map at the Kingwood Town Hall Meeting on October 9, it was to describe three potential phases of West Fork dredging..

Having had several days to review and discuss this map, several other things became clear. See the map and legend below.

West Fork Difference Map. Brown/red/orange/yellow/green areas represent decreases in sediment since last survey. Blue, violet, pink and white represent increases.

Conclusion #1:

The worst sediment buildup in the West Fork is near the mouth…exactly where retired Lake-Houston-area  geologists Tim Garfield and RD Kissling said it was when they raised the alarm about the mouth bar month’s ago.

Conclusion #2:

The problem is much worse than even they suspected. This clearly shows the extent of the West Fork’s mouth bar.  Like an iceberg, the part you see above water is only a small part of the bigger picture.  Vast new sediment deposits extend down to FM1960.

Conclusion #3:

Even Harvey-strength currents could not cut through the mouth bar. Therefore, smaller floods won’t be able to either.

Conclusion #4:

The mouth bar creates a sediment dam in the river that will exacerbate flooding. If the mouth bar area is not dredged, it will cause higher-than-normal flooding on smaller-than-normal rainfall.

Google Earth shows that the area between the mouth bar and FM1960 comprises 1700 acres. According to the difference map, this area received an average of approximately 2 feet of sediment. This means the channel and lake lost 3400 acre feet of capacity in this area.

Conclusion #5:

The mouth bar must be removed immediately. It and adjacent shoal areas get higher with every passing day and storm as water becomes shallower. If the mouth bar is left in place, it will slow the river, causing the area upstream (that is now being dredged) to fill more rapidly than normal with sediment.

Difference Map Proves Mouth Bar Must Go NOW

The mouth-bar area was the focus of the Corps’ survey efforts. They have known for months that it is the major problem. As they stated in Galveston at a meeting I attended, it is the primary driver for backwater and upstream flooding. Their value engineering report also states that in the event of another heavy rainfall, there is a “near certain likelihood” that wide-spread flooding will occur impacting even more homes than before Harvey, due to the river’s inability to pass high volumes of water. See Page 2 for the words engineers almost never use without cause.

We’ve been lucky so far this hurricane season. But minor floods earlier this year on March 28/29 and July 4 proved how serious this problem is. Had the City not lowered the level of Lake Houston for July 4, homes almost certainly would have flooded according to Houston City Council Member Dave Martin.

This Week’s Holdups

At a meeting in Austin last week, the City, Army Corps, FEMA, County and State of Texas all agreed in principle that the mouth bar needs to be removed. Further, if it can be added to the current dredging project, taxpayers can likely save $17 million or more in mobilization fees for a second, separate project at a later date.

Only two hurdles remain: a disposal site for the dredged material and an environmental survey.

A large disposal site is already under review that is much closer to the area of concern than either of the two current sites.

The proposed disposal site’s proximity could save taxpayers tens of millions of dollars more.

However, the environmental survey could delay the project beyond April when current dredging is expected to finish. If so, that could also increase flood risk.

Trees on the mouth bar initially led the Corps to exclude the bar from dredging for two reasons: one was environmental, the other legal. According to the Stafford Act, the enabling legislation for FEMA, FEMA funds cannot be spent to fix things that existed before Harvey. The existence of the trees proved that at least part of the mouth bar existed before Harvey.

The “Mouth Bar.” Note the trees on the right end.

Let’s Get Real

If the trees on the island raise an environmental concern, leave the part of the island that existed pre-Harvey. Dredge the channel and other parts of the island first.

This area includes 3-5+ft of Harvey derived sediment which should qualify for FEMA disaster recovery funds under the Stafford Act based on the new TWDB map.

The longer we wait to dredge this island, the more vegetation will grow on it, the more resistant to erosion it will be, and the more expensive it will be to dredge.

Are the Army Corps and FEMA trying to save an invasive species that USDA wants to eradicate?

Close examination from a boat showed the trees in question to be Chinese tallow trees, an invasive species that the USDA has been trying to eradicate from here to Florida. It’s actually poisonous to local animals. If this tree costs taxpayers tens of millions of dollars in delays and opportunity costs, it will become the new poster child for government waste and folly…especially if Humble, Kingwood and Atascocita flood in the meantime. This is one delay I certainly wouldn’t want my name associated with. That’s the wrong way to go down in history.

This tree on the mouth bar which initially caused the Army Corps to exclude the bar from dredging is a Chinese tallow, an invasive species which the USDA is trying to eradicate. Note the heart-shaped, aspen-like leaves – the tell-tale identifier.

Posted by Bob Rehak on October 14, 2018

411 Days since Hurricane Harvey

Meeting in Austin to Include Mouth Bar in Dredging Scope Ends Well, But Two Hurdles Still Exist

On Thursday, October 11, Council Member Dave Martin attended a follow up meeting to discuss Harvey recovery needs in the Lake Houston area, including the mouth bar. Regulatory agencies including the Texas Department of Emergency Management (TDEM), the Federal Emergency Management Agency (FEMA), the U.S. Army Corps of Engineers (USACE), along with staff from Texas Governor Greg Abbott’s office and the City of Houston also attended the meeting. At one point, Texas Division of Emergency Management Chief Nim Kidd reportedly told people he wasn’t going to let them leave until they reached agreement. The meeting lasted nine hours…without lunch. But at the end of the day, we’re a big step closer to removing the giant sand bar blocking the mouth of the San Jacinto River. Here’s how things reportedly played out.

City Requested Expansion of Scope

The City of Houston asked FEMA to give the U.S. Army Corps of Engineers (USACE) an emergency directive to remove siltation caused by Hurricane Harvey at the mouth of the West Fork of the San Jacinto. Further, to expedite the project and save remobilization fees, the City requested that this work piggyback on the original State of Texas Assistance Request (STAR).

Although  not officially approved yet, regulatory agencies reacted favorably to adding this to the original STAR request. However, two hurdles still exist.

Two Hurdles Remain for Mouth Bar Project

Before the mouth bar can be removed, two more hurdles must be cleared:

  • Identifying and permitting a disposal site
  • Complying with environmental regulations.

TDEM agreed to complete this additional work under an emergency request similar to the one that jumpstarted the initial dredging.

Said Houston City Council Member Dave Martin, “All parties involved are ready to make this work.”

Humble Land a Possibility

Barry Madden, an Humble landowner, with substantial acreage near the river and the mouth bar, has already met with officials about using his property as a potential disposal site. If acceptable, the proximity could save millions of tax dollars. Madden already has “fill” permits in place. So there may really only be one hurdle to clear.

Property owned by Barry Madden just west of Kings Lake Estates and south of the San Jacinto West Fork

Thank You to…

As discussed at the Kingwood Town Hall Meeting on Tuesday, October 9, this mouth bar and other Lake Houston area projects could not happen without the continuing efforts of TDEM, in particular Chief W. Nim Kidd;  Governor Abbott’s Chief Operating Officer, Reed Clay; City of Houston, Mayor Sylvester Turner; Chief Resiliency Officer, Stephen Costello; and Chief Recovery Officer, Marvin Odum.

How You Can Help

Many residents continue to ask Council Member Martin what they can do to help. Council Member Martin encourages residents to send their thanks to several key officials for assisting District E. Please click here for their mailing addresses.

For more information, please contact Council Member Martin’s office at (832) 393-3008 or via email at districte@houstontx.gov.

Posted by Bob Rehak on 10/12/18

409 Days since Hurricane Harvey

Dredging Status: End of September

The U.S. Army Corps of Engineers has spread out across the West Fork of the San Jacinto River for its Emergency Dredging Project. Here is a visual status report from a trip up the river on Friday. I went from West Lake Houston Parkway past the US59 bridge to chronicle what has become an amphibious construction project.

The first dredge belonging to Callan Marine, a subcontractor to Great Lakes Dredge and Dock, has taken up position near the high tension power lines that connect Kingwood and Kings Lake Estates.

This is what the entire dredging assembly looks like.

It has been idling in the same position more than a week while pipeline and booster pumps are connected to it upstream.

Here’s what it looks like from the stern where dredged materials will enter the pipeline that takes them back to placement area #1.

This booster pump is required because of the distance to placement area #1 behind the apartments on Townsend near North Houston Avenue just south of the river.

Pilot boat shuttles pontoon with heavy equipment into place.

Heading upriver, more pipeline waits to be connected near the dredging command site.

At the command site, staff scurries to get the second dredge ready to launch before mid-October.

Dredge #2 owned by Great Lakes Dredge and Dock. This electric dredge will pump sediment to placement area #2 and require more booster pumps than the first dredge because of the length of the pipeline, almost five miles. Placement area #2 is on Sorters Road just south of Kingwood College.

Close up of the business end of the second dredge still at the dock. The rotating assembly stirs up sediment which is then suctioned into the pipeline and pumped to a placement area.Workers loading water into pipeline to get it to submerge. 

Pontoon with crane and pipeline welding equipment.  Sections of pipe waiting to be connected provide a convenient resting place for egrets and other water fowl.

The debris barges will offload their cargo here, where it will be transferred into these trucks and hauled away for processing or landfill.

Meanwhile, another crew scouts a route to placement area #2. Up the West Fork near Kingwood College, the river is so shallow, it may not be deep enough to float pipeline. If dredging in this reach of the river becomes necessary, it could delay the job and increase costs.

From this brief visual trip up the river, you can see that much prep work remains before full dredging can start. The second dredge has not yet launched and no pipeline has reached placement area 2. City officials have stated that the Corps hoped to be in full operation by mid-October. The 270-day clock for this project began ticking on August 19. Two hundred and twenty-nine days remain to the expected completion. Before the project is done, the Corps expected to move 1.8 million cubic yards of sand and sediment out of the river. 

Posted by Bob Rehak on September 30, 2018

397 Days since Hurricane Harvey

 

Dredging Almost Ready to Begin

The U.S. Army Corps of Engineers should begin dredging the West Fork of the San Jacinto River next week. The Corps expected to begin dredging this week, but a part failure for one of the dredges caused a slight delay. A replacement part is being remanufactured and shipped to the command site. The replacement part will help hold the dredge in place during operations and should arrive within days.

First dredge has been moved into river and is awaiting one final part.

With the exception of the replacement part, the first dredge is now virtually completed. It is 27 feet wide, 90 feet long and weighs 270 tons.

Second Dredge Also Now In the Water

A second dredge is also nearing completion. It is electrically powered and has also entered the river for final assembly. No pictures of it are available at this time. In the meantime, the rest of the operation is proceeding as scheduled.

4.5 Miles of Pipe

Workers have welded and weighted 4.5 miles – or almost 24,000 feet – of 24-inch dredge pipe made from 40-foot sections. The pipe will pump sand and sediment back to storage pits (placement sites) on both the north and south sides of the San Jacinto river. Each string of pipe is 1000 feet long. Booster pumps will connect the strings to keep sediment moving up-river and uphill.

Dredge pipe being moved into the West Fork of the San Jacinto in preparation for the start of dredging. Each of these strings is 1000 feet long. They weigh hundreds of thousands of pounds. These 24-inch-diameter pipes will eventually move more than 1.8 million cubic yards of sediment to two placement areas. 

A tender boat moves dredging pipeline into place along the banks of the San Jacinto river. Approximately 4.5 miles of 1,000 – foot  sections of High Density Polyethylene (HDPE) Pipe is being positioned for use next week when dredging should begin.

Even though the start date has been delayed, the date for completion has not.

Dredging Safety Warning

Jet skiers and recreational boaters have been sighted in the vicinity of the dredge command site. Dredging safety officers are asking West Fork San Jacinto recreational boaters to stay clear of submerged pipes and dredge platforms.

Stay away from this section of the river for your own safety. Even though you may be able to see operators, they may not be looking out for you as they struggle to move equipment weighing hundreds of tons. Operators are focused on their job, not you.

As the operational tempo of this project increases, so will the risk of accidents. So please keep your distance.

Posted September 8, 2018 by Bob Rehak

375 Days since Hurricane Harvey

Army Corps Extends Bid Deadline Again; Opening Now Expected June 22

The U.S. Army Corps of Engineers extended the bid deadline again for its West Fork Emergency Dredging Project. The new bid deadline is Friday, June 22, 2018.

Discussions with potential vendors caused the delay for the FEMA funded project as both vendors and the Corps tried to nail down the exact volume of sediment to be removed. The Corps emphasized that it is restoring a 2+ mile stretch of the West Fork to pre-Harvey conditions. The pre-Harvey requirement comes with FEMA dollars which can only be used to return an area to the condition it was in before the storm.

At River Grove Park, this sandbar blocks the drainage ditch that empties the western third of Kingwood. It grew a quarter mile in length and 12 feet in height during Hurricane Harvey. More than 650 homes flooded in areas north of this sandbar. The Corps’ emergency dredging project will start here and extend past the West Lake Houston Parkway Bridge.

Projected Volume More than Doubles

Forecasted dredging material calculations increased from 748,000 to 1.8 million cubic yards of material that has shoaled. Shoaling is an area of shallow water, especially one that is a navigational hazard. In this case, shoals blocked the main channel of the San Jacinto as well as drainage ditches, such as the one at River Grove Park.

Completion Date Extended 90 Days to Accommodate Extra Volume

Because the volume of sediment to be removed has more than doubled, the Corps has also extended the completion date of the project from 180 to 270 days.

“We’ve encouraged bidders to submit questions and this allowed us to revise dredging quantities,” said Gary Stangeland, Interim Chief of Emergency Management at USACE Galveston District. “We were able to recalculate the volume of material needed and therefore extended the bid deadline and project finish date.”

Extending the project 90 days should allow the winning contractor enough additional time to remove the increased volume of materials.

The Corps’ contracting officers reposted the bid deadline date to a site used by vendors to receive notice on government opportunities. The site is accessible to the public at: Federal Business Opportunities website: https://www.fbo.gov

New Opening Date: Friday at 10 a.m.

“Our process is equitable and efficient as it allows for Corps’ Engineers to interact with vendors that will help us to restore the area to pre-Harvey conditions and help reduce future flooding risks,” said Jeff Neill, USACE Galveston District Contracting Chief, “We’ve publicly posted responses to bidders’ questions to www.projnet.org.”  Neill said bids will be opened on June 22, 2018 at 10:00 a.m., local time.

No New Placement Areas for Spoils Anticipated

The physical length of the emergency dredging did not change, just the estimates of the volume of materials within the original area of interest. No additional placement areas for the spoils should be needed, according to the Corps. Stangeland said the two placement areas already identified should be sufficient to store the recalculated increase in forecasted dredged material.

The opening was initially scheduled for May 29, 2018. Even with the delays, this project will be one of the first coming out of Hurricane Harvey that the Corps will complete.

Posted June 21, 2018, by Bob Rehak

296 Days since Hurricane Harvey

Mark Your Calendar: Meet U.S. Army Corps of Engineers Monday Night

On Monday, June 11, two representatives from the U.S. Army Corps of Engineers (USACE) will meet Kingwood residents to discuss dredging of the West Fork of the San Jacinto River. The meeting, sponsored by the Lake Houston Area Grassroots Flood Prevention Initiative, will start at 6:30 PM at the Kingwood Community Center. The emergency dredging will be one of the first flood mitigation projects related to Hurricane Harvey to be implemented in the entire Houston area.

Some Details Known, Many Yet to be Revealed

The Corps finished survey work for the West Fork Dredging Project in April. Since then, Corps members have been busy evaluating their findings, determining project specifications, soliciting bids, and planning logistics. Initial estimates indicated they would move enough sand to fill the Astrodome two and a half times.

The Corps currently expects to open bids within a week of the Kingwood meeting and quickly make a selection. Bidders have been notified that they must start the project within five days. They must also staff the project so that they can finish within six months.

Bid documents indicate dredging will extend from River Grove Park to slightly past the West Lake Houston Parkway Bridge. Residents have raised questions about additional dredging in other areas, including near Lake Houston and on the East Fork.

The Corps has identified two disposal sites for the sand. Both are existing sand pits. The first is south of the river and east of US59; the second is north of the river and west of US59. Details pertaining to mobilization, removal methods, and the extent of dredging have not yet been revealed. At the time of bidding, two removal alternatives were under consideration: mechanical and hydraulic dredging.

Meet Two Corps Representatives

Featured speakers include two representatives from the Corps who will present details of the project and field questions from residents. They are Eduardo Irigoyen, the Project Manager, and Michael Garske, a hydraulic engineer and certified floodplain manager. Both are with the Corps of Engineers’ Galveston District office.

Eduardo Irigoyen, Project Manager

Eduardo Irigoyen, U.S. Army Corps of Engineers Project Manager

Eduardo (Eddie) Irigoyen currently serves as the Emergency Dredging Project Program Manager for the West Fork of the San Jacinto River, which is funded by the Federal Emergency Management Agency (FEMA).

Irigoyen has served as a Project Manager within the Corps since May 2015. He has extensive experience within USACE ranging from programs to construction management, operations and maintenance.

His current duties include managing the planning, scope, development, design, construction, and direction of several projects along the Texas Gulf coast.

Irigoyen is a native of Brownsville, Texas. He received a Bachelor of Science in Mechanical Engineering from The University of Texas at Brownsville in 2004.

Michael Garske, Hydraulic Engineer

Michael Garske, U.S. Army Corps of Engineers Hydrologist

Michael Garske has served as a Hydraulic Engineer and Certified Floodplain Manager for USACE since September 2014.

As one of the District’s lead hydraulic modeling engineers, he’s produced inundation mapping for White Oak, Brays, and Buffalo Bayou projects, helping local officials make accurate flood mitigation decisions.

He provided critical emergency modeling data during the Tax Day, Memorial Day and Harvey floods. He has also helped design dredging templates, ecosystem mitigation banks, and water storage systems; and demonstrated their effects on flood levels.

Garske grew up in Clear Lake. In 2014, he earned a Bachelor of Science degree in Maritime Systems Engineering and an Associate of Arts degree in Maritime Administration from Texas A&M University-Galveston.

Boating Safety Measures During Project

Boaters need to be aware of dredging activities. Ultimately, the project will restore navigation on the river to pre-Harvey conditions and allow the boat launch at River Grove Park to reopen. However, until completion of the project, boaters need to avoid work sites and dredging lines for their own safety.

Agenda Including Other Speakers

The meeting will start at 6:30 p.m. at the Kingwood Community Center 4102 Rustic Woods and last until 8. It will include:

  • Mark Micheletti, one of the two new SJRA board members from Kingwood, giving updates about SJRA flood mitigation projects.
  • Bill Fowler, co-chair of the Lake Houston Area Grassroots Flood Prevention Initiative and a real-estate tax expert, will talk about revised valuations from the Harris County Appraisal District.
  • Bob Rehak, host of ReduceFlooding.com, (or a representative from Harris County Flood Control) will give a brief overview of the upcoming Harris County flood bond.
  • Irigoyen and Garske will make brief presentations and take questions from the audience. Please attend and show the Corps your appreciation for their hard work and long hours on this project.
  • A representative from FEMA will also be there to answer questions about how communities can extend projects like dredging over the long term.

The meeting is free and open to the public, so please plan to attend.

Do Not Confuse This with Flood Bond Meeting

Please note: there has been some confusion between this meeting and the Harris County Flood Bond meeting because of their dates. The County Flood bond meeting, originally scheduled for June 14, is being rescheduled for July so that County Judge Ed Emmett can attend. A new day for that meeting has not yet been determined. The meeting with the Army Corps will happen as planned on Monday evening, June 11.

Posted June 8, 2018 by Bob Rehak

Thanks to Dianne Lansden and Jacque Havelka for Planning this Meeting