11/20/2024 – The Texas General Land Office (GLO) confirmed funding approval from the U.S. Department of Housing and Urban Development (HUD) for seven Harris County Flood Control District (HCFCD) projects.
In June of last year, HCFCD submitted two projects lists to GLO for $825 million in HUD Community Development Block Grant disaster relief (CDBG-DR) funding and flood mitigation (CDBG-MIT) funding.
Since then, HCFCD has worked with GLO to finalize the HUD applications. HCFCD presented an update to Commissioner’s Court in early October, 2024. Today, GLO provided an update to the update.
CDBG-DR Projects
According to an email from GLO spokesperson Brittany Eck received today, seven DR projects have received funding approvals to date. They include:
Eck also said that five more CDBG-DR projects are under final quality-control review. “We are making sure the project submissions are complete and meet all federal eligibility requirements so that there are not issues or concerns down the road.”
Disaster Relief projects have the tightest deadlines. So, all parties focused on those first.
CDBG-MIT Funding Still Under Review
“Seventeen CDBG-mitigation projects are still in various stages of preliminary review,” said Eck.
“We are working back and forth on requests for more information required by HUD on many of the projects,” said Eck. “We continue to work very closely with the HCFCD team to make sure they have all available resources needed to complete the applications. Overall our team is very pleased with the progress being made and the relationship continues to be strong.”
Only two mitigation projects have not yet been submitted for preliminary review.
Channel Conveyance Improvements (C147-00-00-E002) in the Sims Bayou Watershed.
Tremendous Progress
“HCFCD has made tremendous progress on these funds,” said Eck. “However, the rate of approval may not yet demonstrate the progress being made behind the scenes.”
She added, “This process, especially considering the amount funds being administered is an extremely lengthy federal process. Additionally HCFCD has needed to combine projects due to functionality and the GLO is working closely with them to ensure eligibility in the most efficient timeframe imaginable.”
Kingwood Projects Not Mentioned in This Update
Eck did not comment on the status of two Kingwood projects. I can only assume they are still under review. She did not mention any that had been eliminated.
Two additional stormwater detention basins upstream from Taylor Gully on Woodridge Village property acquired by HCFCD and the City of Houston.
Woodridge Village detention basin photographed on 10/25/24. Project paused pending outcome of HUD financing approval.
In its October update to Commissioners Court, HCFCD said the Woodridge Stormwater Detention Basins were originally below the funding line for CDBG-DR.
“The original engineering analysis indicated that only Woodridge Basin Compartment 1 was needed for the Taylor Gully mitigation,” said the update. “As the analysis has progressed it indicates that Compartment 2 (or a portion of it) may also be needed. Due to other projects potentially reducing in budget from the initial estimates, there may be funding available to include the Woodridge basin in the Taylor Gully project.”
That word “may” in the last sentence worries me.
HCFCD did not propose the Kingwood Diversion Ditch project for HUD consideration. HCFCD called the diversion ditch one of the two most important projects in Kingwood. That funding will have to come from somewhere else.
Posted by Bob Rehak on 11/20/24
2640 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/11/20241025-DJI_20241025151115_0018_D.jpg?fit=1100%2C619&ssl=16191100adminadmin2024-11-20 18:32:292024-11-20 18:32:31GLO, HUD Funding Approved for 7 HCFCD Projects So Far
Correction 10/28/24 – The table showing maintenance dollars/square mile has been updatedwith maintenance dollars/stream miles, a more appropriate metric for maintenance dollars.
10/21/24 – Today is the first day of early voting. Knowing where maintenance dollars go may affect how you vote on Harris County Flood Control District’s (HCFCD) proposed 63% maintenance-tax increase.
Before you vote, you should know that maintenance dollars spent per stream mile in different watersheds vary by 28:1. And that the San Jacinto, Spring Creek, Little Cypress Creek, Luce Bayou and Cedar Bayou watersheds are among those that receive the fewest maintenance dollars per stream mile. They all fall in the bottom third.
Why HCFCD Requested Tax Increase
HCFCD says it needs the additional tax revenue because:
Money available for maintenance has remained flat for many years, while…
Assets needing maintenance have grown, especially since the 2018 flood bond.
Assets include flood-mitigation features, such as stormwater detention basins and channels. HCFCD has built many new ones with capital improvement funds from the bond.
What They Don’t Tell You in Flood-Tax Meetings
HCFCD has been holding in-person and virtual meetings throughout the county to explain the need for its proposed tax increase. But the one I attended did not offer any explanations for the magnitude of the tax increase.
Neither could/would HCFCD personnel answer my questions about the allocation of tax dollars among watersheds.
How, when, where, why, and on what basis will the new tax revenue be spent? My fear: another Equity Prioritization Framework for maintenance-tax dollars.
Where Money is Already Going
When looking at the data, it seems we may already have an equity prioritization framework for maintenance dollars – in practice if not in policy. To date, flood-bond dollars have gone disproportionately to watersheds where more than 50% of residents qualify as low-to-moderate income (LMI). See the eight highlighted in gold below.
Maintenance $/stream mile from Hurricane Harvey through 3Q24. Gold watersheds have majority LMI population.
The San Jacinto River watershed, Spring Creek, Little Cypress Creek, Cedar Bayou and Luce Bayou all fall predominantly within the Republican-led Precinct 3. And they all fall to the bottom of the list.
I suspect the highlighted watersheds above float higher because, as LMI-majority watersheds, they have received a disproportionate share of capital-improvement spending.
As a generalization, maintenance money follows capital-improvement spending. So, we can probably expect to see a continuation of that trend.
Other Factors Affecting Maintenance Spending
But ranking maintenance allocations is not as clearcut as ranking overall spending. In addition to watershed size, everal other factors also influence the need for maintenance. They include:
Degree of development (Undeveloped areas require less maintenance.)
Age of assets (New assets require less maintenance than older ones.)
Severity of flooding (Larger floods erode more.)
Type of asset (Is it a concrete channel or grass-lined? Concrete costs more to repair.)
Size of watershed. (Larger watersheds convey more water, creating greater damage/erosion.)
Political factors also likely influence the allocation of dollars. For instance:
Commissioner Rodney Ellis lives in the Brays Bayou watershed.
Right now, HCFCD is juggling projects to raise the LMI percentage of HUD applications totaling $825 million. HUD requires 50%. HCFCD is trying to get the percentage to 70%.
All told, if you vote for the maintenance-tax increase, understand that you may not see as much benefit from it as other parts of the county…if you see any benefit at all. Nothing in the wording of the ballot item guarantees a fair share to each watershed.
Posted by Bob Rehak on 10/21/2024and updated 10/28/24
2610 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/10/Maint-per-SqMi-copy-e1729548059767.png?fit=1100%2C692&ssl=16921100adminadmin2024-10-21 17:52:402024-10-28 19:54:44Before You Vote, Know Where HCFCD Maintenance Dollars Go
10/20/24 – My latest FOIA request revealed some surprising details about Harris County Flood Control District (HCFCD) spending in the San Jacinto Watershed and how it contrasts to the Brays Bayou Watershed.
For several years, I have tracked HCFCD spending by watershed and project phase on a quarterly basis. I have discovered tremendous disparities in flood mitigation funding across the county.
From high to low, the ratio varies by more than 1000:1. The types of activities also vary greatly from watershed to watershed. The Brays and San Jacinto Watersheds make illuminating examples.
San Jacinto Watershed Vs. Brays
Out of the county’s 23 watersheds, the San Jacinto ranks in the bottom half of total funding since Harvey. Despite being the county’s largest watershed and having the most severe flooding, it comes in at #13 in terms of dollars received.
The San Jacinto Watershed received approximately $40 million between Harvey and the end of the third quarter in 2024. That’s less than 2% of the total $2.03 billion HCFCD has spent since Harvey.
Compare that to Brays Bayou where Commissioner Rodney Ellis lives.
Brays has received 10% of all the money spent by HCFCD since Harvey – $202.4 million out of $2.03 billion. That’s more than five times as much as the San Jacinto.
The totals show an impressive difference. But they don’t tell the whole story.
71% of Brays spending has gone into construction activities that actually reduce flood risk.
Meanwhile, the San Jacinto watershed received a fifth as much in total dollars. And one tenth as much went into construction that actually reduces flooding.
Data from FOIA Request
Details of San Jacinto Spending: Where Money Went
Drilling down even deeper into the data, I discovered that virtually all of the San Jacinto “construction” spending was classified as maintenance. In other words, the construction dollars went toward repairing the insufficient infrastructure that resulted in the county’s worst flooding. Very little went toward construction of new capital improvement projects.
On a sad note, HCFCD reported spending $230 on true capital-improvement construction in the San Jacinto Watershed. That’s not a typo. We’re not talking about thousands or millions. We’re talking about just a little more money than the default withdrawal from most ATMs.
That was for the Excavation and Removal (E&R) Project on the Woodridge Village property. HCFCD later cancelled the E&R project when it applied for HUD grants for Woodridge and Taylor Gully improvements.
E&R contracts give contractors the right to sell dirt excavated from detention basins in exchange for a nominal fee, usually $1,000. They make their money, not from HCFCD, but from developers, homebuilders and road builders who buy the dirt at market rates.
The single largest expenditure in the San Jacinto Watershed since Harvey was for the purchase of the Woodridge Village property itself for $13,994,735.
Spike in middle of graph is purchase of Woodridge property. Other spike in 2022 was dredging.
Here’s a breakdown of $40 million in spending against all significant projects.
Spending in San Jacinto Watershed Since Harvey
Amount 17Q3 – 24-Q3
Purchase of Woodridge Village
$13,994,735
Unspecified Maintenance Projects, most classified as construction
$8,303,416
County’s Share of Dredging (East and West Forks)
$7,278,626
SJRA’s San Jacinto River Basin Master Drainage Plan
$2,777,980
Bens Branch Conveyance Improvements (maint)
$1,788,949
Panther Creek Feasibility Study
$1,744,343
Kingwood Diversion Ditch Preliminary Engineering
$872,759
Baytown Storm Sewer Improvements Design Study
$810,869
Taylor Gully Preliminary Engingeering Study
$584,179
Atascocita Preliminary Flood Reduction Study
$541,186
Drainage Study for Watersheds East of Lake Houston
$298,534
Deer Park Project(s)/Design and Right of Way
$213,089
SJRA’s River Basin Sedimentation Study
$162,500
Indian Shores Partnership Project
$130,000
SJRA’s San Trap Location Study
$128,820
Redesign of Failed Sheet Pile Wall/Location Not Specified)
$118,799
Boggy Gully Study
$42,280
Lake Houston Gates Study
$23,547
USACE Support on West Fork Dredging
$9,265
$7.2 million of the HCFCD money spent in the San Jacinto Watershed since Harvey has gone toward studies. That’s almost twice as much as the $3.7 million spent on studies in the Brays Watershed during the same period.
The engineering studies are necessary to qualify for grants which might eventually lead to construction projects that mitigate flooding. But since the studies exist only on paper, they don’t actually reduce any flooding. At least, not until they qualify the area for funding.
Less than $2 Million Per Quarter with Two Exceptions
Here’s how San Jacinto Watershed funding breaks down over time.
Tall blip in middle contains Woodridge purchase. Blip in Q3 22 includes county’s share of dredging.
The thing that chaps me most about all this is Commissioner Rodney Ellis continually harping about how Kingwood gets all the money. He has convinced low-income people throughout the county that areas with high-dollar homes get all the money. The opposite is true according to the data.
Meanwhile, Ellis is pushing funding from just about everywhere else into the watershed where he lives.
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/10/SJR-Basin-Pie-e1729480716722.png?fit=1100%2C654&ssl=16541100adminadmin2024-10-20 22:03:402024-10-21 09:38:30Details of HCFCD Spending in San Jacinto Watershed Since Harvey
10/15/24 – Even as Harris County Flood Control District (HCFCD) pleads with voters for a 63% tax increase, its spending continues to decrease – on both a quarterly and annual basis.
Come to the meeting Wednesday night at the Kingwood Community Center to learn more about HCFCD’s Proposition A on your ballot.
According to HCFCD data obtained via a FOIA request, HCFCD spending declined:
36% from the second to third quarter of this year ($67,983,033 to $43,179,077).
13% from 2023 to 2024 ($252,949,555 to $219,207,447 annualized. I estimated the annualized 2024 figure by adding the average of the first three quarters to their totals.)
See the first two graphs below.
Unless we see a dramatic turnaround in the fourth quarter of this year, spending will decline for four straight years since its peak in 2020.
Spending ramped up rapidly after Hurricane Harvey with the passage of the 2018 flood bond. But since 2020, it has declined precipitously and is now almost down to pre-bond levels. Why?
Possible Reasons for Decline
In fairness, the pandemic slowed many businesses, not just HCFCD. But the pandemic is behind us. And flood mitigation spending continues to fall.
The decline also coincides with a change in leadership at HCFCD and a change in direction from Commissioners Court.
The Democratic majority in Commissioners Court has burdened HCFCD processes with frequent changes to the “Equity Prioritization Framework.” The framework prioritizes projects that benefit low-to-moderate income (LMI) areas, not necessarily those with the most flood damage, the most severe flooding, the most frequent flooding or the highest flood risk.
HCFCD hasn’t yet even released flood-risk data requested by the Harris County Community Resilience Flood Task Force four years ago. If this were a poker game, I’d call that a “tell.”
Money Waiting to be Used
To its credit, HCFCD has secured enough matching partnership funding to more than double the $2.5 billion dollars approved by voters. But the District isn’t spending it.
It has taken two years to compile a project list for the U.S. Department of Housing and Urban Development (HUD) and Texas General Land Office (GLO), which administers HUD funds in Texas.
Meanwhile, $825 million dollars are waiting in the wings.
PowerPoint slide from April 2024
HCFCD keeps trying to get the LMI percentage of that $825 million up to 70%, even though HUD requires only 50%. And the deadline for those 13 Disaster Recovery Projects worth $290 million is rapidly approaching.
Roughly 37% of Bond Spent in 60% of Time
More than six years after the passage of the flood bond, HCFCD has spent only about $1.9 billion out of the $5.1 billion available through bond and matching funds. So, the District has used only 37% of the money committed in 60% of the 10 years originally projected for the bond program.*
Currently, LMI considerations heavily influence HCFCD spending. Brays, Greens, White Oak, Halls, Hunting and Sims Bayous all have a majority of LMI residents. Brays is the first bayou to top $200 million in HCFCD spending since Harvey. Greens has topped $175 million. And White Oak is a whisker short of $150 million.
Meanwhile, the San Jacinto watershed ranks 13th out of 23 watersheds. Yet it had the highest flooding in the county during Harvey.
San Jacinto at US59 circled in red. Note locations of areas on right that didn’t even flood.
Current Priorities Shifting a Bit
When looking only at the third quarter of 2024, the picture has somewhat improved for the San Jacinto. During the last quarter, the San Jacinto watershed ranked 7th, but still fell behind White Oak, Halls, Greens and Brays watersheds, all of which have LMI-majority populations.
HCFCD announced the completion of Project Brays more than two years ago. And yet HCFCD still spends more money there than in the San Jacinto watershed, which is the county’s largest … with the county’s worst flooding.
But alas, Commissioner Rodney Ellis lives in the Brays Bayou Watershed. So, we in the San Jacinto will have to wait to see if any money is left to improve Taylor Gully, Woodridge Village or the Diversion Ditch.
And those poor souls who live near Spring Creek, which had the second highest flooding? Well, they’ll have to wait too.
Strange how most of the waiting is being done in Republican-dominated areas. For instance, Jackson and Luce Bayous (both east of Lake Houston) barely register as blips on the graph above.
Tough Tax Questions
So, should you vote for the new flood tax? Not until you learn more.
HCFCD is pushing the 63% tax increase as a maintenance tax, even though nothing in the ballot language restricts the tax to maintenance.
Wednesday night, HCFCD will hold a meeting at the Kingwood Community Center from 6 to 7:30 PM. Be there!
Ask whether you will see any benefit from the tax.
Why does HCFCD need a 63% increase when it has trouble spending the money it already has?
Is HCFCD capable of administering a larger budget in a timely way?
Is there any guarantee the money will be spent here?
If capital improvement money is largely going elsewhere, shouldn’t we assume that maintenance money will follow it?
I’m going to see what they say before I make any recommendations. Hope to see you there.
Posted by Bob Rehak on 10/15/24
2604 Days since Hurricane Harvey
* A word about data. The data provided by HCFCD includes maintenance spending, not just capital improvement expenditures from the bond. So $1.9 billion is an estimate. If it varies, it would vary downwards, making the disparity in the percentages greater.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/10/Spend-by-Quarter-since-Harvey.png?fit=1934%2C1132&ssl=111321934adminadmin2024-10-15 17:46:282024-10-16 15:40:26HCFCD Spending Drops Even As It Seeks Massive Tax Increase
Harris County Flood Control District (HCFCD) spending data obtained via a Freedom of Information Act Request shows that countywide:
Spending now tops $2 billion since Hurricane Harvey back in 2017
It modestly rebounded between the first and second quarters of this year
More money is now going to land acquisition and construction compared to other phases of the project lifecycle, while less money is going to upfront studies
On a per watershed basis, watersheds with a majority of Low-to-Moderate Income (LMI) residents still get far more than those with a minority of LMI residents.
Spending in the San Jacinto Watershed continues to lag despite high flood risk
Spending has fallen off a cliff in some watersheds.
For details, see below.
Modest Rebound Compared to 1Q24
The chart below shows HCFCD spending in 27 quarters since Hurricane Harvey. It shows a dramatic uptick between 2018 and 2021, followed by an even more dramatic decline through the first quarter of 2023. Since then, spending has averaged slightly more than $60 million per quarter, about half of the peak in 2021.
What accounts for the lower totals recently?
Changes in leadership and personnel turnover at HCFCD
Numerous changes in “equity” allocation formulas that required reprioritization of projects
Lengthy delays at Harris County Community Services involving more than $750 million in U.S. Department of Housing and Urban Development funds.
COVID
Inflation during COVID forcing a re-evaluation of the Bond project list
The 2018 Flood Bond was considered a 10-year project. We are now almost 6 years into the bond, which was approved on the first anniversary of Harvey, but the money is only about 40% spent. That means projects are moving slower than originally anticipated. And that gives inflation a chance to gobble up a higher percentage of them.
More Money Now Going to Land Acquisition and Construction
On a positive note, more projects are moving off the drawing boards and into construction. You can see this trend most clearly by comparing two pie charts that show spending broken down by project phase. The first shows spending since Harvey and the second shows spending during the last quarter.
Looking back at the last 27 quarters, HCFCD spent 76% of its funds on right-of-way acquisition and construction. But during the last quarter, those combined percentages jumped to 85% – up 9%.
Meanwhile, feasibility studies and preliminary engineering reviews fell from 8% to 3% during the comparable periods.
Perhaps we’re starting to mitigate more than ruminate.
Since HarveyDuring second quarter this year
The following table may make it easier for you to compare percentages if you are viewing this on a phone.
Spending in Watersheds with Majority LMI Populations
The percentage of LMI residents in a watershed helps determine eligibility for flood-mitigation grants from the U.S. Department of Housing and Urban Development (HUD).
Harris County has 23 watersheds. Of those, 8 have a majority of LMI residents.
Regardless, since Harvey, those 8 received almost as much money as the other 15 put together.
Since Harvey
Looking only at the last quarter, that trend has moderated somewhat.
Second quarter this year only
But on a per watershed basis, the 8 LMI watersheds still each receive an average of 5.5% of the budget. Meanwhile, the 15 other watersheds each receive an average of 3.7%.
This is largely a function of the weighting given to LMI-majority projects in Harris County’s equity prioritization project scoring formula.
Spending by Watershed: A Study in Extremes
Comparing bar graphs of spending by watershed shows extreme differences between the highs and lows that are getting wider.
Since Harvey, difference between high and low equaled 100 to 1.
Note also the disappearance of the middle ground.
During second quarter, difference between high and low equaled 375 to 1.
During the second quarter, the entire San Jacinto Watershed – the county’s largest – received less than $400,000 of support…while moving up from 13th place to 11th.
Harris County watersheds in the upper San Jacinto River Basin include Spring, Cypress, Willow, Little Cypress, Luce and San Jacinto. They all funnel through the Lake Houston Area.
Since Harvey, they have received about 20% of HCFCD spending. But they drain an area about 50% larger than where the rest of the other 80% of the money went.
And as we saw in May, that can have a huge impact on flood damage.
Harris County and the Houston area are receiving $863 million from the U.S. Department of Housing and Urban Development (HUD) via the Texas General Land Office (GLO) for disaster relief and flood mitigation. So, on Thursday, April 25, 2024, GLO Commissioner Dr. Dawn Buckingham met with a group of Lake-Houston-Area leaders to discuss the area’s flood mitigation needs.
The meeting, arranged by State Representative Charles Cunningham, also included Director Tina Petersen of the Harris County Flood Control District (HCFCD); Director Thao Costis of Harris County Community Services (CSD); Humble Mayor Norman Funderburk; and Dustin Hodges, Chief of Staff for City of Houston Council Member Fred Flickinger.
(L to R) Dustin Hodges; Tina Petersen; Thao Costis; Dr. Dawn Buckingham; Rep. Charles Cunningham; Norman Funderburk; Alice Rekeweg; Scott Elmer, HCFCD; and Kathleen Jordan.
Projects Vie for Funding
As reported on 4/23, Buckingham was in Houston to discuss Disaster Relief and Mitigation projects totaling $863 million. But there are more deserving projects than money to fund them all. So Buckingham, her team, HCFCD and CSD met with area leaders to discuss needs.
The GLO administers the distribution of HUD funds in Texas. Among Lake Houston Area projects discussed for funding were:
No commitments were made at the meeting, but the mood was positive and everyone left smiling.
Buckingham is still collecting information. She listened attentively, asked probing questions and left with a better understanding of the area’s needs.
Splitting the Woodridge Basin into two phases helps ensure that at least one compartment will get funded and provide enough mitigation to let the Taylor Gully Channel Improvements move forward.
Other Topics
Several other topics came up toward the end of the hour-long meeting. They included sedimentation, dredging, and the need for sand to nourish beaches along the Texas coast. The GLO needs sand to replace eroding beaches…and this area needs to remove sand collecting in streams and Lake Houston.
That raised the tantalizing possibility of collaboration for mutual benefit and solving two problems at once.
More news to follow.
Posted by Bob Rehak on 4/26/24
2432 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/04/Buckingham-Meeting.jpg?fit=1100%2C413&ssl=14131100adminadmin2024-04-26 11:38:552024-08-01 16:41:46Area Leaders Meet with GLO Commissioner Buckingham
City of Houston District E Council Member Fred Flickinger addressed a group of local executives at the Kingwood Country Club this morning. He covered a wide range of topics, both in his talk and during Q&A. They included the status of five flood-related topics for the Lake Houston Area:
New Gates for the Lake Houston Dam
Seasonal Lake Lowering
Additional dredging in Lake Houston
Kingwood Diversion Ditch expansion
Last weekend’s flooding on Northpark Drive
Flickinger addressing the Kingwood Executive Group at the Kingwood Country Club on 4/24/24
Floodgate Construction Could Start in ’25 or ’26
Within two sentences of standing up, Flickinger got straight to the subject of flooding and new, bigger floodgates for the Lake Houston Dam. He said, “Obviously, the big thing is getting additional gates. That is currently pending a FEMA review and approval.”
He continued, “We have about $150 million secured for those. Much of that has come via Rep. Dan Crenshaw’s office. Also the State, thanks to Representatives Dan Huberty and Charles Cunningham, and Dave Martin, my predecessor. Stephen Costello [the City’s Flood Czar] has also all done great work. They’ve all really done yeomen’s jobs getting money for the dam gates.”
Looking S.New gates will be built in the earthen portion of the dam to the left of the four small gates you see now.
“We’re looking at construction probably in late 2025 or sometime in 2026,” said Flickinger. “That’s obviously the biggest key to reducing flooding.”
Flickinger also said that he believes the current Mayor remains committed to the project.
Seasonal Lake Lowering
Regarding lowering Lakes Houston and Conroe, Flickinger said the City and SJRA have moved to an event-driven strategy rather than a seasonal one. Automatically lowering the level of Lake Conroe twice a year to reduce flood risk in the Lake Houston Area generated pushback from Lake Conroe residents.
For some time now, the politically divisive strategy has been replaced by an “as-needed” lake-lowering policy in one or both lakes depending on where and when rain falls.
However, the “as needed” policy requires precise forecasting. And several times lately, rain has shifted at the last minute. Ironically, that supports the need for bigger gates that release water faster. They can create extra storage in Lake Houston while still reducing the lead time needed, so forecasters can be absolutely certain of the need to lower the lake.
After all, that’s the drinking water supply for more than 2 million people. You don’t want to lower it needlessly if it won’t be refilled right away.
More Dredging on Tap
Flickinger next addressed the need for more dredging. He said that the City is currently removing another 800,000 yd³ of sediment between Kings Point and FM1960.
“Again, funding for that largely came from Rep. Dan Crenshaw’s office,” he said. “Some people in the government questioned whether that was Harvey-related sediment. But we got the funding! And dredging has started. So that’s a really good thing.”
Diversion Ditch/Walnut Lane Bridge
“The next issue with flooding,” said Flickinger, “is really the Kingwood Diversion Ditch.” The ditch cuts south from St. Martha’s Catholic Church to River Grove Park through the western portion of Kingwood.
“The Walnut Lane Bridge has about a fourth of the surface area below it that the Kingwood Drive and North Park Bridges have. Because of that, it works somewhat like a dam. Crenshaw just secured $4 million to address that, but we have got to have a cost/benefit ratio of one or greater, which will be a challenge. So, we’re working on that.”
Looking north along Diversion Ditch. Notice how it narrows under the Walnut Lane Bridge.
“And that money probably won’t become available for another six months. Hopefully, we can get that cost/benefit analysis to where we need it by then and use that money to rebuild the Walnut Lane Bridge. It’s a huge deal that affects Trailwood, Forest Cove, and even people who live along Bens Branch.”
“Part of the water from Ben’s branch is actually supposed to go to the lake via the Diversion Ditch,” said Flickinger. (That’s how the ditch got its name.) However, Flickinger noted that when the Diversion Ditch backs up, water goes down Bens Branch instead.
“And we’re getting more and more of that because of the development in Montgomery County…That’s part of why Kingwood High School flooded.”
Northpark Flooding
Last weekend, Northpark Drive flooded near the construction zone.
At the time, I conjectured that one or more of the drains may have been blocked. Flickinger revealed the cause this morning.
He said the drain was never tied into the new drainage system.
“It turns out that they had a change in foremen on the job, and one of the drains was not connected to the storm sewer.”
Houston City Council Member Fred Flickinger
“That is what caused that big fiasco. Now our office is going to contact the construction team every time we have a significant rain event and ask them to double check, so we don’t have any issues obstructing stormwater,” said Flickinger.
“Anytime you’ve got construction, there’s a certain amount of mess associated with it. But obviously, we don’t need somebody causing flooding by forgetting or blocking something.”
Looking E along Northpark on Sunday morning, 4/21/24 at area where drain was not tied in.
Before Flickinger had to leave for a meeting downtown, it became clear to everyone in the room that flooding was one of his primary concerns.
For someone who’s been in the job less than four months, he was very aware of the complex intricacies and interdependencies of the Lake Houston Area’s drainage problems. And that was very encouraging news!
Posted by Bob Rehak on 4/24/24
2430 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2024/04/COH-CM-Fred-Flickinger-at-KWCC.jpg?fit=1100%2C733&ssl=17331100adminadmin2024-04-24 13:32:152024-04-24 13:32:16Flickinger Provides Updates On Gates, Dredging, Northpark, More
4/23/24 – In a transmittal to Harris County Commissioners Court today, Harris County Flood Control District (HCFCD) updated commissioners on how it hopes to spend $863 million in U.S. Department of Housing and Urban Development (HUD) funds.
Two projects in the Kingwood Area remain funding priorities: Taylor Gully Channel Improvements and Woodridge Village Stormwater Detention. However, the stormwater detention, currently listed as an alternate backup project, is being split up into two smaller projects to help improve funding chances for the most critical component. See more details below.
Ins and Outs of Funding
The HUD money comes in two “buckets” with different requirements – Disaster Relief ($322 million) and Mitigation ($541 million). Both buckets fall under HUD’s Community Development Block Grant Program (CDBG). CDBG’s flexibility lets people and communities design and implement strategies tailored to their own needs and priorities.
When I last reported on the CDBG lists, the Lake Houston Area had one project in each bucket.
In Disaster Relief, the Woodridge Village Stormwater Detention Basin was “below the line.” That means it was an alternate on the backup list; a primary project would have had to have been canceled for it to receive funding.
In Mitigation, Taylor Gully Improvements were above the line, i.e., primary recommendations.
Extent of Woodridge excavation when paused before applying to HUD
Changes Outlined in Transmittal
The latest updated project lists feature five main changes. They affect both Lake Houston Area projects. But first, let me explain the others that are changing, because their financial impact affects everything else.
Transferred the Boudreaux Basin (Phase 1) from the DR list to Mitigation, so that it could benefit from the longer timeline for Mitigation projects. This project is between Willow Creek and SH99 at Huffsmith Kohrville Road. The transfer will free up another $38.6 million on the DR list.
Thus, you would think approximately $21.3 million was freed up on the DR list. That would theoretically let the Woodridge Stormwater Detention Basin move up from “below the funding line.” However, it remains below…at least for now.
Moreover the Woodridge Stormwater Detention Basin has morphed into two projects. One provides the detention required to help mitigate Taylor Gully now. The other provides an extra safety margin as a hedge against future developments.
Splitting the detention up into two smaller pieces gives HCFCD more flexibility and greater confidence that the most important part will get funded.
The Woodridge/Taylor Gully discussion in the document is a bit confusing unless you speak HUD.
“The second basin will provide additional regional stormwater detention. Splitting the project helps us ensure the compartment of the Woodridge basin that mitigates Taylor Gully can move forward,” said Crouser.
She concluded, “The ultimate goal is to eventually construct both compartments. This follows our traditional rationale for phasing projects when possible and practicable. Both compartments will be advanced to bid-ready state using local dollars. That will give us the maximum flexibility to advance the projects.”
Numbers for Harris County Flood Control District’s (HCFCD) first quarter are in. They show several spending trends.
Spending Decline Continues
They show that the pace of overall flood-mitigation spending continues to decline, though there are signs that it could turn around soon – depending on your basis of comparison.
Year over year, the totals show a pronounced decline. Annualized first-quarter spending is now less half of what it was at the post-Harvey peak in 2020.
All data for this and other graphs in this post was compiled from HCFCD spreadsheets in response to a FOIA request.
To underscore that trend, spending declined from $74 million to $51 million between the last quarter of 2023 and the first quarter of 2024 – a 31% decrease in one quarter. So I checked for seasonality.
Spending often drops between the fourth and first quarters, but it’s not consistent.
From the 7-year chart above, you can see that spending dropped five times after the holidays and increased two.
However, change the basis of comparison and you can see an encouraging sign. If you compare the first quarter of 2023 with the first quarter of 2024, the spending is up by 20% – from about $41 million to $51 million.
Where the Money Goes by Watershed
Harris County has 23 watersheds. The chart below shows the total of HCFCD spending in each since Hurricane Harvey. Variation between Brays on the high end and Galveston Bay on the low is more than 100 to 1.
From data supplied by HCFCD in response to FOIA request
Comparing the graphs above and below shows where the action shifted in Q1. Notice that Brays shifts from first to eighth place. White Oak moves from fourth to first. And Halls jumped from ninth to third.
To learn more about specific projects in each of these watersheds, click on a watershed’s link on HCFCD’s home page.
What Drives Investments in Some Watersheds and Not in Others
To a large extent: damage and political priorities. I compiled the chart below from Harris County Federal Reports. One of the first things you notice is that Brays is on the left and Galveston Bay is toward the right.
Data compiled from HCFCD Federal Reports
The next two charts show how prioritizing projects in low-to-moderate income (LMI) areas can skew spending in different watersheds. The first shows LMI funding since Harvey. The second shows LMI funding in the first quarter of 2024. Comparing them, you can see how higher and higher percentages of the total are going to watersheds with a majority of LMI residents.
In the longer run, about half the money has gone to watersheds with a majority LMI population. But currently, about two-thirds goes to LMI-majority watersheds.
Keep in mind that although you see two categories in these pie charts, the categories are not equal. The blue area contains eight watersheds and the orange area 15 – almost twice as many. Said another way…
Half as many watersheds now get twice as much money.
The eight LMI watersheds include: Brays, Greens, White Oak, Halls, Sims, Hunting, Vince, and Goose Creek/Spring Gully.
The government defines LMI as “below the average income for the region.” In the other 15 areas, a majority of residents make “above the average income for the region.”
Harris County uses an Equity Prioritization Formula to select projects it will fund. The formula places a premium the percentage of low-to-moderate income individuals who live in an area. The theory: low-income families are less able to repair their homes after a flood.
Other Variables Skew Funding
The deeper you dig into these numbers, the more you can see other variables that skew funding, too.
Dense building next to bayous can increase cost of land for mitigation projects by making buyouts necessary to widen channels or build stormwater detention basins.
Previous mitigation spending – Some watersheds received extensive mitigation before Harvey.
Spending by others, i.e., the Army Corps, which is not reflected here
Timing of studies – Some studies that would justify grants haven’t even been completed yet, whereas others completed before Harvey were shovel ready when the flood bond came along.
Land acquisition and construction represent the two largest component costs of flood mitigation. Some large projects haven’t reached those stages yet.
Building code variations – Newer codes generally stipulate safer standards, reducing flood risk and damage in newer areas at no cost to the public.
Frontier Program – The county sometimes acquires land in developing areas to prevent future flood damage. Prevention is always cheaper than correction, but that land can be expensive.
Speed of partnership funding – Just last week, Harris County, the City of Houston and GLO reached an agreement related to $322 million in Harvey Disaster Relief Funds. That will make more money available to watersheds that were heavily damaged during Harvey.
Protection of employment centers, such as the Medical Center, Downtown, the Ship Channel, etc.
Someday soon, I hope to do a series of posts on projects within each watershed and the specifics of why they were funded.
The San Jacinto Gap
For now, let me discuss just one. The San Jacinto is Harris County’s largest watershed. It had the highest flooding in the County during Harvey. It also had a quarter of all the flood-related deaths during Harvey.
The San Jacinto had the eighth most damage, but ranks 13th in funding since Harvey. Of the twelve watersheds that received more funding, five had less damage.
Cypress Creek has received more than 4X the San Jacinto.
Little Cypress has received 3X more.
Addicks has received 2.5X more.
Clear Creek and Willow Creek have each received approximately 50% more.
And most of those watersheds have more affluent populations than the San Jacinto. So how do you account for the gap between severity of flooding and flood-mitigation funding?
For one thing, most of the San Jacinto watershed lies outside of Harris County. And some commissioners have flat out rejected spending money to build projects outside the county even though the 2018 flood bond permitted it.
Protecting areas like Humble, Atascocita and Kingwood will most likely require building upstream projects outside the county. Until the political winds change, funding for such projects will most likely have to come from the state or federal government.
The Texas General Land Office (GLO) is currently conducting a final review on more than $498 million in grant applications from Harris County Flood Control District (HCFCD) and Harris County Community Services Department (CSD). That’s out of a total allocation of $1,072,033,863 allocated to Harris County. And that means projects for almost half the Harvey money allocated to Harris County will soon go to Washington for a final review by HUD.
Additional applications for the rest of the money will soon follow the projects listed below. They will be submitted “on a rolling basis,” according to Brittany Eck, a GLO spokesperson.
The GLO administers all HUD funds in the state of Texas.
GLO Working Side by Side with Harris County
GLO has a “Strike Team” embedded at HCFCD headquarters, working side by side with both CSD and HCFCD to eliminate any delays on the HUD applications. The billion dollars allocated to the county falls into several different programs, each with different deadlines and complex rules.
“We are currently in the ‘Eligibility Phase,’ which is the most critical, but also the most time consuming. During this phase we must ensure that the projects proposed sync with HUD regulations in terms of LMI beneficiaries, environmental impacts and more,” said Eck.
No Performance Benchmarks Missed So Far
“It is important to note that Harris County has not missed a performance benchmark yet on the HUD applications. The GLO is working with Harris County to ensure all administrative paperwork is completed in accordance with federal regulations. This protects both Harris County and the State of Texas from incurring costly ‘findings’ during the post-project audit process.”
A finding during a post-project audit could potentially cause HUD to claw back part of its grant money. So it’s vitally important to ensure all regulations are followed to the letter.
Three Main Batches of Money
The three main pots of money include:
Harris County CSD – $208,152,174 in CDBG-MIT funds
HCFCD – $322,033,863 in CDBG-DR funds
HCFCD – $541,847,826 in CDBG-MIT funds
That brings the total of original allocations to $1,072,033,863.
Since this involves the government, it also includes acronyms. So let me explain some of the terms.
CDBG stands for Community Development Block Grants. These grants provide communities with resources to address a wide range of development needs, providing projects meet one or more of HUD’s three defined national objectives. Namely, a CDBG project must:
Benefit to low- and moderate- income (LMI) persons
Aid in the prevention or elimination of slums or blight and/or
Meet an urgent need (UN), especially one impacting public health and safety.
But what about the rest of those acronyms?
DR stands for Disaster Relief
MIT stands for Mitigation.
What’s the difference? According to HUD, CDBG-DR grants provide housing, infrastructure, and economic revitalization assistance to impacted areas. The CDBG-Mitigation (CDBG-MIT) program provides additional funding to lessen the impact of future disasters.
To learn more about HUD applications for the specific Harris County projects, see below.
Harris County CDBG-MIT
Harris County Community Services Department was allocated $208,152,174 in CDBG-MIT funds for infrastructure, planning, and project delivery.
The contract was executed on 08/31/2022. All projects in this batch of funding must close out by 8/31/27.
The $208 million breaks down into three subcategories.
Infrastructure programs – $154 million
Planning programs – $37.5 million
Project delivery – $16.7 million
Infrastructure Programs
Of 11 projects initially proposed in this category, the three largest in terms of dollar amounts – totaling $75M of the $154M – have been submitted for preliminary review.
$37,500,000.00
Pine Trails Subdivision Drainage Improvements Involves upgrading approximately 63,650 LF of drainage systems and developing two (2) detention ponds in Harris County Precinct No. 2. 66.97% LMI
$20,545,326.00
Ralston Acres Subdivision Drainage Improvements Involves upgrading approximately 15,250 LF of drainage systems and developing two (2) detention ponds in Harris County Precinct No. 1 and Ralston Acres Subdivision. Income Surveys TBD
$16,954,674.00
North Forest Subdivision Drainage Improvements Involves upgrading approximately 19,700 LF of drainage systems and developing one (1) detention pond in Harris County Precinct No. 1 and the North Forest Subdivision. Income Surveys TBD
As of 3/19/24
Planning Programs
Four projects – costing a total of $16.5M out of the $37.5 million – have been submitted for preliminary review out of the 23 proposed planning projects.
$500,000.00
Harris County Multi-Jurisdictional Hazard Mitigation Plan The Harris County Office of Homeland Security & Emergency Management is seeking to update the Harris County Hazard Mitigation Plan. The plan will develop strategies and action items to minimize vulnerabilities and damages and include 37 participating jurisdictions.
$12,500,000.00
Drainage Master Plan for Unincorporated Harris County The planning project will evaluate drainage infrastructure capacity status and deficiencies in Harris County’s unincorporated areas. It will also guide the identification and implementation of mitigation alternatives to reduce flood risk.
$500,000.00
Halls Bayou Watershed Flood Risk Analysis Study The scope of the Halls Bayou watershed study is to analyze the best available data incorporating the Halls Bayou watershed flood risk reduction-related project and to evaluate existing program benefits using the new Atlas 14 precipitation data to identify additional potential flood reduction needs within the watershed.
$3,000,000.00
The Evacuation Routes Study The Evacuation Routes Study aims to enhance transportation resilience in road-flooding-prone areas of Unincorporated Harris County.
As of 3/19/24
Project Delivery:
$16,652,174 of the $208,152,174 County allocation will be used to administer the funds for projects.
HCFCD Disaster Relief
HCFCD was allocated $322,033,863 in CDBG-DR funds for infrastructure projects.
HCFCD submitted 13 projects costing a total of $317,494,724.78 for CDBG-DR grants and is putting up local funds in the amount of $45,899,821 for those same projects. All of the applications have been officially submitted and are being reviewed for HUD eligibility completeness by the GLO.
The HCFCD/CDBG-DR contract was executed on 11/27/2023 and must be closed out by 3/31/2026. The 13 projects include:
$20,361,143.56
Arbor Oaks Stormwater Detention Basin To construct one 431-acre-feet stormwater detention basin within the White Oak Bayou watershed. 60.55% LMI
$20,247,760.00
Isom Stormwater Detention Basin To construct one 550-acre-feet regional stormwater detention basin within Halls Bayou. 74.23% LMI
$8,692,644.00
Lauder Stormwater Detention Basin To construct one 341.47-acre-feet stormwater detention basin within Greens Bayou. 78.10% LMI
$20,361,143.56
Brookglen Stormwater Detention Basin To construct one 33.45 acre-feet stormwater detention basin within Armand Bayou Watershed. 52.54% LMI
$25,390,047.00
Kluge Stormwater Detention Basin – Phase 3 To construct one 350 acre-feet stormwater detention basin within Little Cypress Creek watershed. 14.25% LMI but qualifies under Urgent Need
$77,899,107.00
Greens Bayou Mid-Reach Channel Conveyance Improvements To rehabilitate 19,008 LF of channel conveyance along Greens Bayou. 78.61% LMI
$18,878,499.00
Cypress Creek Channel Rehabilitation, Main Stem, Batch 5 To rehabilitate 7,500 LF of channel conveyance along Cypress Creek. 49.18% LMI, but qualifies under Urgent Need
$36,710,019.00
Dinner Creek Stormwater Detention Basin ‐ Phase 1 To construct two (2) detention basins, northwest and southeast of Dinner Creek. 52.36% LMI
$7,642,742.00
Barker Reservoir Channel Rehabilitation, Repair Package 2 To rehabilitate 18,528 LF of channel conveyance at 19 different sites along Barker Reservoir. 21.64% LMI but qualifies under Urgent Need
$9,742,750.00
Stormwater Detention Basin along Jackson Bayou To rehabilitate 2,025 LF of channel conveyance and construct one (1) 15 acre-feet stormwater detention basin within Jackson Bayou. 60.78% LMI
$23,496,000.00
Addicks Reservoir Channel Rehabilitation & Restoration, Repair Package 3 To rehabilitate 49,296 LF of channel conveyance at 49 sites along the Addicks Reservoir. 37.04% LMI but qualifies under Urgent Need
$23,844,000.00
East TC Jester Detention Basin – Compartment 1B To construct one 725 acre-feet stormwater detention basin within the Cypress Creek watershed. 36.14% but qualifies under Urgent Need
$12,293,732.00
Keegans Bayou Stormwater Detention Basin Near Old Richmond Road – Phase 1 To construct one stormwater detention basin within the Brays Bayou watershed. 56.71% LMI
As of 3/19/24
HCFCD CDBG-MIT
Harris County Flood Control District was allocated $541,847,826.00 in CDBG-MIT funds for infrastructure hazard mitigation projects.
Five projects – totaling $73 million – have been submitted for preliminary HUD eligibility completeness review out of the 19 mitigation projects originally proposed.
Halls Bayou Channel Conveyance Improvements Downstream of Hopper (HALLS HOPPER) Includes widening approximately 4,525 LF of the existing channel along the left (east) bank from downstream of Hopper Road to just upstream of Pinewood Village Park. 70.03% LMI
$10,427,946.00
Hahl North Stormwater Detention Basin (Hahl North) Includes construction of one 220 acres-feet of stormwater detention basin adjacent to Halls Bayou and the widening of approximately 2,100 LF of the existing channel along Halls Bayou. 73.65% LMI
$17,300,036.00
West TC Jester Stormwater Detention Basin Will create one 414 acre-feet stormwater detention basin in the Cypress Creek watershed. 36.13% LMI but qualifies under Urgent Need
$11,987,888.00
Taylor Gully Channel Conveyance Improvements Includes approximately 13,118 LF of stormwater drainage channel improvements in the affected stretch of channel. 20.92% LMI but qualifies under Urgent Need
$30,007,445.00
Boudreaux Stormwater Detention Basin – Phase 1 Will build one 458 acre-feet stormwater detention basin west of Holderrieth Road along Willow Creek. 33.59% LMI but qualifies under Urgent Need
Altogether, the HUD applications must benefit at least 50% LMI individuals according to HUD regulations governing these funds.
Taylor Gully looking S from the Montgomery County Line. Up to 600 homes flooded twice here in 2019, after Perry Homes clearcut 270 acres without installing the required detention basin capacity.One of the HUD applications seeks to improve the channel.
Even though some projects drop below the 50% threshold, as a group they meet the requirement. Those that fall below the threshold also qualify under HUD’s Urgent Need mandate.
Extensions Requested, But Not Yet Confirmed
GLO has requested extensions for all these projects. While HUD reportedly seems favorable, written confirmation has not yet been received. That places a premium on HUD applications that can be executed quickly.
Posted by Bob Rehak on 3/19/24 based on information provided by the Texas GLO
2394 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/05/20230124-DJI_0785.jpg?fit=1200%2C799&ssl=17991200adminadmin2024-03-19 16:42:062024-03-19 21:41:51GLO Reviewing HUD Applications for Harris County Projects Totaling Half Billion Dollars