Progress to Date on West Fork Dredging

Note: This post contains a correction to Matt Zeve’s title; he is Deputy Executive Director at Harris County Flood Control.

The Army Corps of Engineers today released this graphic showing the extent of West Fork dredging progress to date. Dredging will extend from River Grove Park on the west King’s Harbor on the east.

Graphic courtesy of the US Army Corps of Engineers. For a larger, high-res version, click here.

Original Schedule Included Months of Prep

The Corps expected the project to take 270 days or 9 months. The clock started ticking on July 21, 2018, when the Corps awarded the job to Great Lakes Dredge and Dock and its subcontractor Callan Marine.

Great Lakes subcontracted part of the job because it was time sensitive and Callan had a dredge that could start quickly. In fact, Callan began sooner than Great Lakes. Both companies spent considerable time on site assembling the dredges. Welding more than six miles of 24 inch HDPE dredge pipe and maneuvering it into place also required upfront time. Then both companies had to calibrate dredging rates with three booster pumps. Make no mistake; this is a huge undertaking.

Two months after the contract award, the first dredge moved downriver to its starting position on September 19th. A month later, on October 25th, the second dredge moved downriver. So out of the the 9 months, it took two and three months respectively just to start the dredging. Then we had three floods between December 7 and January 7 that caused pauses in the action.

Slow but Steady Progress

Backing out floods and prep time, we need to evaluate the progress shown above on a SIX month “actual-dredging” timetable, not the nine months budgeted for the entire job. Visually, it appears that they are roughly half completed and roughly half of the six months has expired. That’s reassuring. Especially knowing that the dredging has proved more difficult than expected. Crews periodically must stop to remove roots and aquatic vegetation from the dredge cutter heads.

Nagging Uncertainty Remains about Mouth Bar and Upstream

The questions readers keep asking, though, are “Will we be able to save all of that investment in upfront time?” And “Will we be able to start dredging the mouth bar before the start of next hurricane season starts on June 1?”

Corps bids showed that mobilization and demobilization cost 25% of the total job, roughly $18 million. Starting the mouth bar project as soon as the current project completes could save that money. It’s enough to do a lot more dredging. Maybe even open up the boat launch that the County hopes to build at its new Edgewater Park near US 59.

New Congressman Dan Crenshaw Jumping In

Dan Crenshaw, the Lake Houston Area’s new US Congressman seems to be jumping into flooding issues with both feet. He announced today that he has been appointed to Congressional Budget and Homeland Security committees. The budget committee assignment should put him in a good position to help accelerate flood mitigation measures.

Crenshaw has already met with Harris County with Flood Control District Deputy Executive Director Matt Zeve and Professional Engineer Ian Hudson to get an update on projects in Texas’s Second Congressional District. Those include both cleanup projects and flood mitigation projects. Crenshaw also met on Monday with Houston City Councilman Dave Martin, in which they discussed the importance of these projects. I also hear he is meeting the Army Corps and developers of the new high-rise project proposed for Kingwood.

New Congressman Dan Crenshaw (center) with Matt Zeve of Harris County Flood Control (r) and Ian Hudson (l).

Said Crenshaw, “Our district has been through so much because of Hurricane Harvey. I’m grateful for all the hard work our local and federal officials have done to prepare us for the next storm. I’m excited to get to work to ensure the people of TX-02 are able to make a full recovery and put Harvey in the rearview mirror.”

Something tells me that Crenshaw will bring the zeal of a SEAL to this job.

Posted on January 23, 2019 by Bob Rehak

512 days since Hurricane Harvey

Governor Abbott Extends Hurricane Harvey Disaster Declaration

Last week, Texas Governor Greg Abbott extended the disaster declaration for the 60 counties affected by Hurricane Harvey in 2017. The extension enables government agencies to work together under special rules designed to enable mitigation efforts and speed them up. See the wording in the third paragraph from the bottom. Below is the exact text of the Governor’s press release:

Governor Greg Abbott Extended The State Disaster Declaration In January For Texas Counties Affected By Hurricane Harvey

January 18, 2019 | Austin, Texas | Proclamation

TO ALL TO WHOM THESE PRESENTS SHALL COME: 

WHEREAS, I, GREG ABBOTT, Governor of the State of Texas, issued a disaster proclamation on August 23, 2017, certifying that Hurricane Harvey posed a threat of imminent disaster for Aransas, Austin, Bee, Brazoria, Calhoun, Chambers, Colorado, DeWitt, Fayette, Fort Bend, Galveston, Goliad, Gonzales, Harris, Jackson, Jefferson, Jim Wells, Karnes, Kleberg, Lavaca, Liberty, Live Oak, Matagorda, Nueces, Refugio, San Patricio, Victoria, Waller, Wharton and Wilson counties; and

WHEREAS, the disaster proclamation of August 23, 2017, was subsequently amended on August 26, August 27, August 28 and September 14 to add the following counties to the disaster proclamation: Angelina, Atascosa, Bastrop, Bexar, Brazos, Burleson, Caldwell, Cameron, Comal, Grimes, Guadalupe, Hardin, Jasper, Kerr, Lee, Leon, Madison, Milam, Montgomery, Newton, Orange, Polk, Sabine, San Augustine, San Jacinto, Trinity, Tyler, Walker, Washington and Willacy; and

WHEREAS, on September 20, 2017, and in each subsequent month effective through today, I issued proclamations renewing the disaster declaration for all counties listed above; and

WHEREAS, due to the catastrophic damage caused by Hurricane Harvey, a state of disaster continues to exist in those same counties;

NOW, THEREFORE, in accordance with the authority vested in me by Section 418.014 of the Texas Government Code, I do hereby renew the disaster proclamation for the 60 counties listed above.

Pursuant to Section 418.017 of the code, I authorize the use of all available resources of state government and of political subdivisions that are reasonably necessary to cope with this disaster.

Pursuant to Section 418.016 of the code, any regulatory statute prescribing the procedures for conduct of state business or any order or rule of a state agency that would in any way prevent, hinder or delay necessary action in coping with this disaster shall be suspended upon written approval of the Office of the Governor. However, to the extent that the enforcement of any state statute or administrative rule regarding contracting or procurement would impede any state agency’s emergency response that is necessary to protect life or property threatened by this declared disaster, I hereby authorize the suspension of such statutes and rules for the duration of this declared disaster.

In accordance with the statutory requirements, copies of this proclamation shall be filed with the applicable authorities.

IN TESTIMONY WHEREOF, I have hereunto signed my name and have officially caused the Seal of State to be affixed at my office in the City of Austin, Texas, this the 18th day of January, 2019. 

GREG ABBOTT
Governor

To view a PDF of the signed document, click here.

Posted by Bob Rehak on January 22, 2019

511 Days since Hurricane Harvey

January Update on Lake Houston Area Flood Mitigation Projects

High-rise development in the floodplain has pushed Lake Houston Area flood mitigation projects out of the headlines lately. So here’s an update on where things stand from Stephen Costello, the City of Houston’s chief resiliency officer and Mayor Turner’s flood czar.

Extending Dredging to Include Mouth Bar

It’s becoming increasing unlikely that we’ll be able to piggyback on the current dredging project. The City and Federal Government are still arguing about how much of the mouth bar existed before Harvey.

The mouth bar almost totally blocks the West Fork where it meets Lake Houston. FEMA and the City of Houston have argued for almost a year over how much existed before Harvey.

Regular readers may remember that FEMA and the Corps stonewalled action on the mouth bar because of the Stafford Act. The Stafford act is the enabling legislation for FEMA. It bars using disaster relief funds to address pre-disaster issues such as deferred maintenance.

The two sides argued for almost a year about how much of the bar existed before Harvey and how much resulted from Harvey. They have finally agreed on a procedure to answer that question. It’s called the Stockton Protocol and was developed at Stockton University in New Jersey to answer similar questions after Superstorm Sandy.

The protocol involves analysis of core samples from the mouth bar. According to Costello, the City hired a geomorphologist to harvest the core samples last week. It should take two to three weeks to analyze the layers in them.

Mouth Bar Disposal Issues Drag Out, Too

Another issue regarding the mouth bar has to do with disposal of the dredged materials. The City and the Corps have tried to agree on and permit a site since October 11 of last year. Three issues come into play when evaluating such sites: volume, cost and environmental considerations.

Next phases of dredging (proposed)

The site must be large enough to accommodate the volume of dredged materials.

The site must also be close to help hold down costs. The farther the site, the higher the costs. The amount of booster pumps, diesel fuel, pipeline, and manpower needed all increase with distance.

Re: environmental considerations, the Corps would prefer a below-ground site such as an old sand pit. That reduces the chance that sand and silt will end up back in the river during the next flood. It also eliminates the issue of possibly reducing the volume of the floodplain. On the other hand, above ground sites are easier to find and one exists that is much closer than any abandoned mine.

At the moment, managers are trying to find the optimal solution given all three variables.

Of course, the volume issue will depend on how much FEMA agrees to remove – after analysis of core samples and after the federal government resumes business.

Rapidly Shrinking Window to Save $18 Million

Before this process started dragging out, taxpayers had a chance to save $18 million. That represents the cost of mobilization and demobilization of the current dredging program on the West Fork. Piggybacking the mouth bar project on top of the current project would eliminate that cost for Phase II because the people and equipment would already be on site and could just continue working.

The current project should end in late April or early May. Costello says the City is already starting to look at contingency plans in case the shutdown drags on or permitting the disposal site becomes problematic.

Contingency Plans Considered

DRC, the company engaged to clean up debris in the lake, also does dredging. DRC has already bid the job and agreed to work for the same price as the current dredgers.

The leading permittee for the disposal site has agreed to store the dredges on his property if necessary until Phase II kicks off.

Current Barriers to Reaching An Agreement

But in the meantime, huge questions remain about volume and cost. With core samplings not yet analyzed, it’s hard to determine how much material will have to be removed from the river. So it’s also hard to determine whether the available money will stretch far enough to remove everything FEMA approves. At this point, the City has committed $15 million and the State $50 million. FEMA remains the big question mark.

Next steps:

  • Analyze core samples and agree on volume to be removed
  • Agree on disposal site and permit it
  • Determine available funds
  • Develop a dredging plan optimized for all variables above
  • Execute the plan

Status of New Gates for Lake Houston Dam

New gates for the Lake Houston dam also remain in limbo. Costello met with FEMA in December and again in early January. FEMA questions the benefit/cost analysis presented by the City. The City originally estimated a 2.8 b/c ratio for the project. That put it high on everyone’s priority lists. However, that may come down. Costello still believes the ratio will come in above 1.0, the cutoff (because benefits still exceed costs). A consultant is currently reconfiguring the estimate.

Lake Houston Dam is primarily a spillway. Small floodgates can lower lake if given enough time. But that requires starting before weather predictions acquire a high degree of certainty, thus raising the risk of wasting water if the forecast changes.

Concern about Potential for Downstream Impact

FEMA also wants assurances that new gates will not negatively impact downstream residents. The City remains confident that downstream residents will not experience impacts. The purpose of the gates is to be able to pre-release water at a controlled rate before storms hit to minimize the volume going over the spillway. Also, the county is reportedly offering buyouts to vulnerable homeowners below the dam.

If the City cannot convince FEMA that the threat to downstream residents will not increase, the City will have to look for an alternative source of funding, such as adding a penny to water bills.

Next Steps on Additional Gates

Assuming Costello can convince FEMA that there will be no negative impact downstream, the next steps would be:

  • Final design
  • Permitting
  • Construction

Each phase could take six months to two years, depending on unforeseen obstacles, such as political headwinds and completion of the long-awaited San Jacinto River Basin Watershed Survey.

San Jacinto Watershed Survey Status

In March of last year, the SJRA proposed a new survey of the entire San Jacinto Watershed. Projects such as maintenance dredging, additional gates, and additional upstream detention, all depend on the outcome of this study.

To properly design gates, for instance, engineers need to know the volume of water they need to shed in a given period of time.

To properly design maintenance dredging, they also need to know how fast the river is and lake are silting up.

The estimated cost of this study was about $2 million. Consultants have been ready and waiting since last April for the green light. Unfortunately, FEMA went back and forth with the SJRA and its partners on this project for eight months. According to Costello, FEMA was ready to write the check in December when the Federal Government shut down.

Next Steps:

  • Deposit FEMA check
  • Execute study
  • Final report

Expect this one to take 18 months from the start date.

Need to Mitigate Mitigation Funding

The saga of this study epitomizes the need to improve disaster mitigation procedures. Flooding along the Gulf Coast is foreseeable. If we budgeted for it, we wouldn’t have to depend on Washington and could save years on these projects. Two million dollars is not a great amount of money when spread out among the two million people who would benefit.

It Took 6 Months to Win the War for Texas Independence

It’s taking twice that long for FEMA to cut a check.

Think we have lost our edge? We need to get proactive and self-reliant about these things if we want the region to grow. It’s already been a year and a half since Harvey. It will take another year and a half to complete the study. Three years before the serious work of actual mitigation begins! We can do better. We must demand that our leaders reform the way the mitigation business works.

As always, these represent my opinions on matters of public policy. They are protected by the First Amendment of the U.S. Constitution and the Anti-SLAPP statute of the Great State of Texas.

Posted by Bob Rehak on January 21, 2019

511 Days since Hurricane Harvey