Professor Emeritus William Dupré, Ph.D., of the University of Houston’s Department of Earth and Atmospheric Sciences filed a 36-page report with the TCEQ on sand mining in the San Jacinto River Basin. Dupré has broard experience with geologic hazards and risk assessment. He submitted his report in support of the petition filed with the TCEQ by the Lake Houston Area Grassroots Flood Prevention Initiative to establish best management practices (BMPs) for sand mining.
The first issue that Dupré identified is flooding. “With one exception, all sand mines in the San Jacinto River Watershed are located partially or completely within the regulatory floodway, an area delineated by FEMA as having the highest potential for flooding (and erosion) along major waterways. “[T]he floodway is an extremely hazardous area due to the velocity of flood waters which carry debris, potential projectiles and erosion potential…”. (Montgomery County Flood Plain Management Regulations, 2014, p.25)
Floodway Constriction
Dupré notes that partitioning large areas of the floodway from rising floodwaters by levees and dikes can result in increased flooding of adjacent areas.
A good example: sand mines on the north side the San Jacinto West Fork and I-45 have walled off half the floodplain, forcing floodwaters onto neighboring property on the south side.
Sand mines have walled off more than 200 acres west of I-45 and north of the San Jacinto West Fork. See below.The high dikes force floodwater to the other side of the river rather than allowing it to spread out on both sides.The concentration of water in a smaller area also increases the velocity and erosion. For close-up of area inside red circle, see image below.This shows how high the dike around the sand mine is.
Levee Failure Can Flush Pollutants into Waterways
“Flood-induced breaches in levees can also add to the problems of flooding, erosion, and sedimentation downstream,” Dupré says, flushing sediment and other pollutants into adjacent land, wetlands, and waterways. See two examples below.
In the top row, river migration eroded the pit wall which allowed the contents to drain into the West Fork near North Park Drive. In the bottom row, the entire contents of a mine pit drained into the West Fork near Bennett Estates.
In-Stream Mining Disrupts River Habitat
A. Google Earth image of point bar on the west Fork of the San Jacinto River; B. Same bar 5 months later showing un-permitted (i.e. illegal) In-stream “bar-scalping.”
“Since the passage of Section 404 of the Clean Water Act Amendments of 1977, some states have heavily restricted or banned in-stream mining, as have many countries,” writes Dupré. “These restrictions are mainly based on the significant environmental problems associated with this type of mining.”
Such mining can create major disruptions of riparian habitats by increasing the amount of sediment put into suspension. “Major channel modifications can also occur, including upstream incision (headcutting) and downstream erosion and deposition.”
BMPs Can Make Compliance with Regulations More Efficient
In his paper, Dupré next examines applicable regulations and suggests several BMPs to supplement them. He recommends that:
All APO’s should develop and make available to regulators and the public a Comprehensive Mine Plan and an Environmental Assessment Report on potential impacts before permits are issued.
Likewise, all APO’s should develop and make available to regulators and the public a Reclamation Plan before permits are issued and file a performance bond ensuring reclamation before a production permit is granted. Such permits should have significant civil and criminal penalties for non-compliance.
New mining should be minimized or restricted in delineated floodplains and floodways and channel migration zones (areas most like to be eroded by lateral migration and river avulsion).
Mines should be “prohibited within the adopted regulatory floodway unless it has been demonstrated through hydrologic and hydraulic analyses that the proposed encroachment would not result in any increase in flood levels…. A development permit must be secured from the Flood Plain Administrator prior to the placement of fill or other encroachment in the floodway….” (Montgomery County Flood Plain Management Regulations, 2014).
Stockpiles should be located outside the floodway, because of the high potential for erosion (and resultant sediment pollution) during frequent flooding.
Conclusion
Dupré acknowledges that aggregate mining clearly provides valuable material and employment to the state and nation.
Nonetheless, Texas is one of the few states where sand and gravel mines remain largely unregulated. Issues related to flooding, erosion, and sedimentation create many unintended (and undesirable) environmental and economic impacts associated with sand and gravel mines – especially in the San Jacinto River watershed. “I believe there is a clear need for the requirement for BMP’s to better protect the public and the environment,” says Dupré.
TCEQ Public Comment Period Rapidly Coming to a Close For Sand Mining BMPs
On November 11, the TCEQ held a public hearing on a joint proposal between TACA and the Lake Houston Area Grassroots Flood Prevention Initiative to establish best management practices for sand mining in the San Jacinto watershed. The public comment period closes on December 11, 2020 – in just 12 days.
If you want to weigh in on the subject, you can review presentations from the hearing here. TACA and the Lake Houston Area people are in substantial agreement on most points. However, they still differ on four key issues.
Where should the BMPs be enforced? On the main stems of the East and West Forks or on the smaller tributaries, too?
Should there be performance bonds for reclamation?
How far from rivers should the sand mines be set back for safety reasons?
Should compliance with best practices should be voluntary or mandatory?
If you have comments or questions for the TCEQ, please e-mail Outreach@tceq.texas.gov. Make sure to include “Sand Mining Rulemaking” in the subject line of your e-mail.
Posted by Bob Rehak on 11/29/2020
1188 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/11/image.png?fit=455%2C269&ssl=1269455adminadmin2020-11-29 12:08:222020-11-29 12:14:14UH Geology Professor Weighs in with TCEQ on BMPs Related to Sand Mining
Not long ago, Colony Ridge, the world’s largest trailer park, went to war with the City of Plum Grove. Now they are taking on Wayne Dolcefino, one of the nation’s leading. investigative journalists, too.
Somebody needs to tell Colony Ridge developer Trey Harris to give his employees some media training. When Dolcefino set his sights on Colony Ridge, several employees greeted him with hostile language. The word “threatening” comes to my mind. Surely they should know that this will only focus more media attention on their dubious business model.
Dolcefino Credentials
Dolcefino and his television shows have won:
Thirty Emmy Awards from the National Academy of Television Arts and Sciences
Five Charles Green Awards
An Edward R. Murrow award
A Jack Howard Award for investigative reporting
Numerous honors from the Associated Press and Texas Association of Broadcasters
An unprecedented three medals from the international journalism organization Investigative Reporters and Editors.
So it was ironic that Dolcefino titled his latest piece on the war between Plum Gove and Colony Ridge an “Unfair Fight.” If you want to see one of the nation’s top journalists at the top of his form, check out this story.
But Dolcefino goes way beyond those problems. Check out the revolving-door foreclosures, fake foreclosure auctions, and predatory lending practices that target the vulnerable.
Posted by Bob Rehak on 11/27/2020
1186 Days after Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/11/Liberty-County-Courthouse.jpg?fit=1200%2C684&ssl=16841200adminadmin2020-11-26 23:00:342020-11-28 10:31:10Colony Ridge Declares War on Investigative Journalist, Too
It’s easy sometimes to focus so much on problems, that we forget about progress. So let’s give thanks on this fourth Thanksgiving since Hurricane Harvey. We should truly take heart in what we have accomplished in flood mitigation so far.
This small strip is all that’s left of the once mighty mouth bar on the San Jacinto West Fork. Dredgers will use it as a base of operations in the next phase of dredging.
Engineers are now evaluating the benefit/cost ratios of each. They are also securing environmental permits.
Looking west across Lake Houston Spillway
Next step: FEMA will review the preliminary engineering results. Assuming the benefit/cost ratios justify the projects, FEMA and local partners will fund construction of the selected alternative. Another $47 million has already been set aside for that, but approval is not automatic.
Lake Conroe Lowering
A big thank you to the board of the SJRA which voted earlier this spring to continue its seasonal Lake Conroe lowering policy in the face of withering protests from Lake Conroe boaters. This policy provides an additional margin of safety to those in the Lake Houston Area until other mitigation projects can be completed.
Bens Branch Clean Out
During Harvey, 13 people died after Bens Branch flooded. The now complete Kingwood Drainage Analysis showed that it had been reduced to a two year level of service. That means sediment had reduced its conveyance to the point that it will flood on a two year rain.
Even before the study was completed, Harris County Flood Control started cleaning it out in phases to restore conveyance. From upstream:
HCFCD also repaired erosion in the Kingwood Diversion Ditch between Walnut Lane and Kingwood Deer Springs Drive.
HCFCD Diversion Ditch repairs in Kingwood
The City of Houston and Harris County Flood Control also cleaned out and repaired several severely clogged ditches in Forest Cove, Kings Forest, Elm Grove, and Kings Point/Fosters Mill. There may have been more than I missed.
Grants for Additional Crucial Studies Under Consideration
The Texas Water Development Board advanced for SJRA Grant Applications for consideration in the final phase.
Would identify and create a plan for implementing potential sedimentation solutions in the Upper San Jacinto River Basin (Lake Houston watershed). It would evaluate the input, output, and storage of sediment for the entire basin as well as for sub-watersheds.
This sandbar formed overnight during Harvey and blocked the West Fork by 90% according to the Corps. Boats that drew 18 inches of water could not navigate upstream past this sandbar, which has since been removed.
Would provide for installation of rain and river/stream gages at three locations identified as critical by San Jacinto County to provide early warning information to the county during storm events.
Park Restoration
KSA restored two parks in Kingwood that were severely damaged by Harvey and Imelda. KSA repaired trails in East End Park after each storm. Some had to be relocated because of erosion of the river bank. The Eagle Point trail in East End will become a 2021 project. KSA wants to put down a geo-stabilizing system on top of approximately ten feet of sand deposited by the two storms.
Standing on five feet of sand deposited in East End Park wetlands after Harvey
At River Grove, the Army Corps of Engineers cut an opening through a massive 12-foot-high and quarter-mile-long sand bar blocking the boat ramp and the Kingwood Diversion Ditch. Then KSA excavated parts of the park out from under five feet of sand, created new playing fields, restored the boardwalk, and dredged the lagoon adjacent to the boardwalk.
Dredging of lagoon and boat dock at River Grove Park
Buyouts
Harris County Flood Control started buying out townhomes damaged beyond repair in Forest Cove. At last count, they had purchased 69 of 80. Four of the remaining 11 are in various stages of the buyout process. Owners of the rest had reportedly vanished after the storm, complicating buyouts. Those may need to be condemned before HCFCD can tear down the remaining townhomes.
Edgewater Park and Trails
Harris County Precinct 4 purchased land on the northeast corner of US59 and the West Fork to create a new park called Edgewater Park. Construction was supposed to have started more than a year ago on a park headquarters building, a boat launch, and rest rooms. The County fenced off the property, then delayed construction for unspecific reasons.
Tentative plans for a new Edgewater Park at Hamblen Road and Loop 494
As part of the project, the Houston Parks Board (a private charitable organization which works with the City Parks Department) proposed building a trail that would connect the Spring Creek Greenway with the Kingwood Trail Network. Unfortunately, the trail would have to go through the townhome-buyout area. And buyouts have been delayed.
Commercial Rebuilding
Merchants have totally restored the H-E-B shopping center at Kingwood Drive and West Lake Houston Parkway. Renovations should soon be announced at other centers. Kings Harbor has been restored and new building is underway. Kingwood Village Estates and other condo/apartment complexes have been re-built. And a whole new shopping center has gone in on the southwest corner of US59 and Northpark Drive.
A new CVS store is replacing the old Chase Bank at Kingwood Drive and West Lake Houston Parkway.
Schools Back and Better
Both Kingwood High School and the St. Martha School have been renovated and flood-proofed. Kingwood College is not only back, it’s expanding.
Woodridge Village Detention Completed
Perry Homes finally finished the detention ponds on its Woodridge Village site earlier this year. They don’t have enough capacity to hold a 100-year rain. But they sure work better than what they had in 2019 when the lack of detention contributed to flooding Elm Grove Village twice. Hopefully, they will suffice until the City and County can work out a deal to purchase the property and build enough detention to hold a 100-year rain.
Woodridge Village N2 Detention Pond, the largest of five now on the site, during a heavy rain in September.
Bridges
TxDoT replaced the southbound US59 bridge and re-opened it months ahead of schedule. Union Pacific replaced its ancient bridge over the West Fork with a modern replacement. Both bridges have supports wide enough to let trees pass through in future floods. That should hopefully avoid the logjams that back water up, flooding surrounding areas.
New Union Pacific Bridge completed in May 2020 allows trees to pass through during floods.
The City has also made several repairs to the West Lake Houston Parkway Bridge. They not only reinforced the supports, they leveled the road bed.
Community is Back and Better
More than three years after Harvey, the Humble/Kingwood Community is back and better. Because of dredging and ditch repairs alone, we are already safer than before Harvey, when we didn’t recognize many of the problems lurking around us.
Yes, some homes and businesses remain vacant. And much remains to do. But the future of the community is no longer in doubt. That’s thanks to the determination of residents to vowed to restore one of the most unique and livable communities in America.
Thanks also go to local leaders such as Congressman Dan Crenshaw, State Representative Dan Huberty, State Senator Brandon Creighton, Precinct 4 Commissioner Jack Cagle, HCFCD, and Houston Mayor Pro Tem Dave Martin. We shouldn’t forget Mark Micheletti and Kaaren Cambio, two SJRA directors from the Lake Houston Area and others on the SJRA board who voted for lake lowering. Nor should we forget the Lake Houston Chamber of Commerce. And especially Guy Sconzo who led the area’s recovery task force before succumbing to cancer.
My apologies to anyone I left out. Or for any worthy projects that I omitted.
Despite the fact that we still have much left to do, we should not lose sight of our achievements to date. Understanding how far we have come will sustain us in the battles that still lie ahead.
Posted by Bob Rehak on 11/26/2020 (Thanksgiving)
1185 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/11/20201105-DJI_0089.jpg?fit=1200%2C900&ssl=19001200adminadmin2020-11-25 17:16:412020-11-25 17:50:20Giving Thanks for Flood Mitigation Projects Completed and Underway
UH Geology Professor Weighs in with TCEQ on BMPs Related to Sand Mining
Professor Emeritus William Dupré, Ph.D., of the University of Houston’s Department of Earth and Atmospheric Sciences filed a 36-page report with the TCEQ on sand mining in the San Jacinto River Basin. Dupré has broard experience with geologic hazards and risk assessment. He submitted his report in support of the petition filed with the TCEQ by the Lake Houston Area Grassroots Flood Prevention Initiative to establish best management practices (BMPs) for sand mining.
The first issue that Dupré identified is flooding. “With one exception, all sand mines in the San Jacinto River Watershed are located partially or completely within the regulatory floodway, an area delineated by FEMA as having the highest potential for flooding (and erosion) along major waterways. “[T]he floodway is an extremely hazardous area due to the velocity of flood waters which carry debris, potential projectiles and erosion potential…”. (Montgomery County Flood Plain Management Regulations, 2014, p.25)
Floodway Constriction
Dupré notes that partitioning large areas of the floodway from rising floodwaters by levees and dikes can result in increased flooding of adjacent areas.
A good example: sand mines on the north side the San Jacinto West Fork and I-45 have walled off half the floodplain, forcing floodwaters onto neighboring property on the south side.
Levee Failure Can Flush Pollutants into Waterways
“Flood-induced breaches in levees can also add to the problems of flooding, erosion, and sedimentation downstream,” Dupré says, flushing sediment and other pollutants into adjacent land, wetlands, and waterways. See two examples below.
In-Stream Mining Disrupts River Habitat
“Since the passage of Section 404 of the Clean Water Act Amendments of 1977, some states have heavily restricted or banned in-stream mining, as have many countries,” writes Dupré. “These restrictions are mainly based on the significant environmental problems associated with this type of mining.”
Such mining can create major disruptions of riparian habitats by increasing the amount of sediment put into suspension. “Major channel modifications can also occur, including upstream incision (headcutting) and downstream erosion and deposition.”
BMPs Can Make Compliance with Regulations More Efficient
In his paper, Dupré next examines applicable regulations and suggests several BMPs to supplement them. He recommends that:
Conclusion
Dupré acknowledges that aggregate mining clearly provides valuable material and employment to the state and nation.
Nonetheless, Texas is one of the few states where sand and gravel mines remain largely unregulated. Issues related to flooding, erosion, and sedimentation create many unintended (and undesirable) environmental and economic impacts associated with sand and gravel mines – especially in the San Jacinto River watershed. “I believe there is a clear need for the requirement for BMP’s to better protect the public and the environment,” says Dupré.
TCEQ Public Comment Period Rapidly Coming to a Close For Sand Mining BMPs
On November 11, the TCEQ held a public hearing on a joint proposal between TACA and the Lake Houston Area Grassroots Flood Prevention Initiative to establish best management practices for sand mining in the San Jacinto watershed. The public comment period closes on December 11, 2020 – in just 12 days.
If you want to weigh in on the subject, you can review presentations from the hearing here. TACA and the Lake Houston Area people are in substantial agreement on most points. However, they still differ on four key issues.
If you have comments or questions for the TCEQ, please e-mail Outreach@tceq.texas.gov. Make sure to include “Sand Mining Rulemaking” in the subject line of your e-mail.
Posted by Bob Rehak on 11/29/2020
1188 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
Colony Ridge Declares War on Investigative Journalist, Too
Not long ago, Colony Ridge, the world’s largest trailer park, went to war with the City of Plum Grove. Now they are taking on Wayne Dolcefino, one of the nation’s leading. investigative journalists, too.
Somebody needs to tell Colony Ridge developer Trey Harris to give his employees some media training. When Dolcefino set his sights on Colony Ridge, several employees greeted him with hostile language. The word “threatening” comes to my mind. Surely they should know that this will only focus more media attention on their dubious business model.
Dolcefino Credentials
Dolcefino and his television shows have won:
So it was ironic that Dolcefino titled his latest piece on the war between Plum Gove and Colony Ridge an “Unfair Fight.” If you want to see one of the nation’s top journalists at the top of his form, check out this story.
Colony Ridge’s land clearing practices, erosion, and lack of workable detention ponds, have contributed to sedimentation in the East Fork watershed. The developer’s wastewater treatment vendor has also been cited numerous times by the TCEQ for discharging raw sewage into area streams.
But Dolcefino goes way beyond those problems. Check out the revolving-door foreclosures, fake foreclosure auctions, and predatory lending practices that target the vulnerable.
Posted by Bob Rehak on 11/27/2020
1186 Days after Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
Giving Thanks for Flood Mitigation Projects Completed and Underway
It’s easy sometimes to focus so much on problems, that we forget about progress. So let’s give thanks on this fourth Thanksgiving since Hurricane Harvey. We should truly take heart in what we have accomplished in flood mitigation so far.
Detention
The San Jacinto River Basin Master Drainage Study is virtually completed. This lays the groundwork for mitigation projects throughout the 2900-square-mile, seven-county region. It identifies possible locations for upstream detention, one of the three main legs of the Lake Houston Area flood-mitigation strategy (dredging, detention, gates).
Dredging
Several dredging programs have been completed and more are underway.
Completed:
Approved, but Not Yet Completed:
Additional Gates
The City of Houston, Harris County, and Coastal Water Authority secured a grant from FEMA to study ways to increase the discharge capacity of the Lake Houston Spillway. That study is almost complete. It identified five alternatives for increasing the discharge capacity.
Engineers are now evaluating the benefit/cost ratios of each. They are also securing environmental permits.
Next step: FEMA will review the preliminary engineering results. Assuming the benefit/cost ratios justify the projects, FEMA and local partners will fund construction of the selected alternative. Another $47 million has already been set aside for that, but approval is not automatic.
Lake Conroe Lowering
A big thank you to the board of the SJRA which voted earlier this spring to continue its seasonal Lake Conroe lowering policy in the face of withering protests from Lake Conroe boaters. This policy provides an additional margin of safety to those in the Lake Houston Area until other mitigation projects can be completed.
Bens Branch Clean Out
During Harvey, 13 people died after Bens Branch flooded. The now complete Kingwood Drainage Analysis showed that it had been reduced to a two year level of service. That means sediment had reduced its conveyance to the point that it will flood on a two year rain.
Even before the study was completed, Harris County Flood Control started cleaning it out in phases to restore conveyance. From upstream:
Two more phases remain:
Rogers Gully Clean Out
Harris County Flood Control cleaned out a stretch of Rogers Gully in Atascocita that was several blocks long.
Other Ditch Repairs
HCFCD also repaired erosion in the Kingwood Diversion Ditch between Walnut Lane and Kingwood Deer Springs Drive.
The City of Houston and Harris County Flood Control also cleaned out and repaired several severely clogged ditches in Forest Cove, Kings Forest, Elm Grove, and Kings Point/Fosters Mill. There may have been more than I missed.
Grants for Additional Crucial Studies Under Consideration
The Texas Water Development Board advanced for SJRA Grant Applications for consideration in the final phase.
Upper San Jacinto River Basin Regional Sedimentation Study
Would identify and create a plan for implementing potential sedimentation solutions in the Upper San Jacinto River Basin (Lake Houston watershed). It would evaluate the input, output, and storage of sediment for the entire basin as well as for sub-watersheds.
Spring Creek Watershed Flood Control Dams Conceptual Engineering Feasibility Study
Would perform a conceptual engineering feasibility study of two potential dam/reservoir locations within the Spring Creek watershed.
Lake Conroe – Lake Houston Joint Reservoir Operations Study
Would develop a joint reservoir operations and communications strategy for Lake Conroe and Lake Houston.
Flood Early Warning System for San Jacinto County
Would provide for installation of rain and river/stream gages at three locations identified as critical by San Jacinto County to provide early warning information to the county during storm events.
Park Restoration
KSA restored two parks in Kingwood that were severely damaged by Harvey and Imelda. KSA repaired trails in East End Park after each storm. Some had to be relocated because of erosion of the river bank. The Eagle Point trail in East End will become a 2021 project. KSA wants to put down a geo-stabilizing system on top of approximately ten feet of sand deposited by the two storms.
At River Grove, the Army Corps of Engineers cut an opening through a massive 12-foot-high and quarter-mile-long sand bar blocking the boat ramp and the Kingwood Diversion Ditch. Then KSA excavated parts of the park out from under five feet of sand, created new playing fields, restored the boardwalk, and dredged the lagoon adjacent to the boardwalk.
Buyouts
Harris County Flood Control started buying out townhomes damaged beyond repair in Forest Cove. At last count, they had purchased 69 of 80. Four of the remaining 11 are in various stages of the buyout process. Owners of the rest had reportedly vanished after the storm, complicating buyouts. Those may need to be condemned before HCFCD can tear down the remaining townhomes.
Edgewater Park and Trails
Harris County Precinct 4 purchased land on the northeast corner of US59 and the West Fork to create a new park called Edgewater Park. Construction was supposed to have started more than a year ago on a park headquarters building, a boat launch, and rest rooms. The County fenced off the property, then delayed construction for unspecific reasons.
As part of the project, the Houston Parks Board (a private charitable organization which works with the City Parks Department) proposed building a trail that would connect the Spring Creek Greenway with the Kingwood Trail Network. Unfortunately, the trail would have to go through the townhome-buyout area. And buyouts have been delayed.
Commercial Rebuilding
Merchants have totally restored the H-E-B shopping center at Kingwood Drive and West Lake Houston Parkway. Renovations should soon be announced at other centers. Kings Harbor has been restored and new building is underway. Kingwood Village Estates and other condo/apartment complexes have been re-built. And a whole new shopping center has gone in on the southwest corner of US59 and Northpark Drive.
Schools Back and Better
Both Kingwood High School and the St. Martha School have been renovated and flood-proofed. Kingwood College is not only back, it’s expanding.
Woodridge Village Detention Completed
Perry Homes finally finished the detention ponds on its Woodridge Village site earlier this year. They don’t have enough capacity to hold a 100-year rain. But they sure work better than what they had in 2019 when the lack of detention contributed to flooding Elm Grove Village twice. Hopefully, they will suffice until the City and County can work out a deal to purchase the property and build enough detention to hold a 100-year rain.
Bridges
TxDoT replaced the southbound US59 bridge and re-opened it months ahead of schedule. Union Pacific replaced its ancient bridge over the West Fork with a modern replacement. Both bridges have supports wide enough to let trees pass through in future floods. That should hopefully avoid the logjams that back water up, flooding surrounding areas.
The City has also made several repairs to the West Lake Houston Parkway Bridge. They not only reinforced the supports, they leveled the road bed.
Community is Back and Better
More than three years after Harvey, the Humble/Kingwood Community is back and better. Because of dredging and ditch repairs alone, we are already safer than before Harvey, when we didn’t recognize many of the problems lurking around us.
Yes, some homes and businesses remain vacant. And much remains to do. But the future of the community is no longer in doubt. That’s thanks to the determination of residents to vowed to restore one of the most unique and livable communities in America.
Thanks also go to local leaders such as Congressman Dan Crenshaw, State Representative Dan Huberty, State Senator Brandon Creighton, Precinct 4 Commissioner Jack Cagle, HCFCD, and Houston Mayor Pro Tem Dave Martin. We shouldn’t forget Mark Micheletti and Kaaren Cambio, two SJRA directors from the Lake Houston Area and others on the SJRA board who voted for lake lowering. Nor should we forget the Lake Houston Chamber of Commerce. And especially Guy Sconzo who led the area’s recovery task force before succumbing to cancer.
My apologies to anyone I left out. Or for any worthy projects that I omitted.
Despite the fact that we still have much left to do, we should not lose sight of our achievements to date. Understanding how far we have come will sustain us in the battles that still lie ahead.
Posted by Bob Rehak on 11/26/2020 (Thanksgiving)
1185 Days since Hurricane Harvey