$29 Million Construction Contract for Woodridge, Taylor Gully Project Approved
3/26/26 – A $29,387,654 bid from Bryce Construction & Design, LLC has been approved by the county purchasing agent to construct the Woodridge and Taylor Gully flood mitigation projects in Kingwood. See Item 45 on the agenda. Here is their bid transmitted to Commissioners Court. It was the low bid.
To streamline approval of US Housing and Urban Development Department Community Development Block Grants (CDBG), several months ago Commissioners Court approved a proposal to let the County Purchasing Agent approve CDBG projects. They all have tight deadlines.
The contractor will mobilize within two weeks according to Emily Woodell, a Harris County Flood Control District (HCFCD) spokesperson. We should see dirt flying this Spring.
History of Project
Up to 600 families in Kingwood flooded twice in 2019 when Perry Homes’ contractors cleared approximately 268 acres for Woodridge Village just north of the Harris County line. Then they sloped the land toward Taylor Gully. Many of the families had just recovered from the first flood on May 7th when they flooded again in September before the stormwater detention basins had been built.
Subsequently, in 2020, Harris County and the City of Houston purchased the land so that it couldn’t be developed and flood Kingwood again. Before the purchase, Perry Homes built five stormwater detention basins on the Woodridge property. However, Montgomery County regulations at the time required much less detention capacity that Harris County – about 40% less.
That was because Harris County had already adopted Atlas 14 and because Montgomery County averaged rainfall estimates across the entire county, even though annual rainfall increases as you move south toward the county line.
Elements of Solution
So, Harris County Flood Control set out to study what it would take to properly reduce flood risk using Atlas 14 data near the county line. The studies recommended:
- More upstream detention
- Increasing conveyance of Taylor Gully
- Replacing a culvert bridge at Rustic Elms with a clear-span bridge

The project limits of the proposed Taylor Gully Channel Improvements stretch from the Montgomery County boundary on the west to approximately 700 feet upstream of the confluence with White Oak Creek – a length of approximately 12,630 linear feet.
This portion of the project includes replacing the bridge at Rustling Elms.

HCFCD also plans to finish one more large stormwater detention basin upstream from Taylor Gully in Montgomery County.

HCFCD started work on the pond in January 2022 under an Excavation and Removal contract with Sprint Sand & Clay. The contract to remove up to 500,000 cubic yards of soil would have more than doubled the previous detention capacity on the site and more than made up for the 40% Atlas 14 shortfall.
However, HCFCD paused the Sprint contract when it applied for a U.S. Department of Housing and Urban Development (HUD) grant. That’s because HUD rules stipulate that a project cannot change during the grant application period.
HCFCD later terminated the contract in November 2023 when it became clear the project would qualify for the grant. At that point, Sprint had already removed 160,000 cubic yards, an amount equivalent to approximately 100 acre feet. So if the figures in the construction drawing are accurate, the capacity of the basin will quadruple compared to what you see below.

Expected Impact
Contractually, work must finish within 552 days from the notice to proceed – approximately 18 months. That would make a great 2027 Christmas present for a lot of Kingwood families.
Under HUD’s Community Development Block Grant for Mitigation, all work must finish and billing must be completed by March 31, 2028. That should be doable.
The project will give Taylor Gully a 100-year level of service.
HCFCD
That means it should only come out of its banks in a hundred-year storm.
The improvements would reduce water-surface elevation (WSE) along Taylor Gully up to 6.9 feet in places and 4 to 5 feet on average for a 100-year storm event.
Also, this project will remove approximately 276 structures from a 100-year flood plain. Without the project, area residents would continue to flood in lesser storms.

That means we should NOT see many more scenes like the one above until Noah’s comeback tour.
Thanks to Precinct 3 Commissioner Tom Ramsey PE, for continuing to push this project when things seemed bleak.
Posted by Bob Rehak on 3/26/26