Tag Archive for: Russell Palmer

Northpark Bridge, Traffic Lights, 494 Detour, Pond Updates

7/24/26 – This week’s Northpark Drive expansion update includes news on the bridge, Loop 494, traffic lights and the entry ponds.

No-one ever said building the first all-weather evacuation route from Kingwood would be easy. But the Lake Houston Redevelopment Authority/TIRZ 10 took on the job which has entailed coordinating the work of multiple utilities and political jurisdictions and a railroad. They each have their own priorities and timetables.

Bridge Over Loop 494 and UPRR Tracks

The bridge over Loop 494 and the UnionPacific Railroad Tracks is one of the signature features of the Northpark Expansion project. It will enable the smooth flow of traffic during evacuations even when trains stall on the UPRR tracks or stoplights at 494 get knocked out.

The east ramp for the bridge by Dunkin’ Donuts is now totally paved and virtually complete. Work has shifted to building turn lanes under where the bridge will go and sinking piers for the bridge.

Rebar for bridge piers being hoisted into place.
Northpark Expansion Bridge
Eastern Northpark Bridge abutment. Cranes are drilling holes as crews prepare rebar cages to reinforce the concrete piers. Crews are also prepping a u-turn under the bridge at this location.
Northpark Expansion Bridge
Closer shot of prep work on U-turn lane. Note circular rebar cage top right.
Northpark Expansion Bridge
Drilling holes for the piers takes some serious equipment.

494 Detour

The intersection of Loop 494 and Northpark was shut down for several weeks while contractors installed north-to-south drainage across Northpark. However, they have completed that operation and repaved 494.

Surface lanes are now complete on 494 and curbs have been installed. Photo from a week ago.

But before they can remove the concrete traffic barriers that detour traffic, UPRR must be present to coordinate their crossing signals with other systems.

Everyone is reportedly scrambling to open the intersection before school starts next month.

Traffic Light Coordination

City of Houston, TxDOT, METRO, Harris County and Montgomery County all have signals. Transtar is the entity that manages/integrates each of the individual jurisdictions and signalized intersections onto a single monitoring system. Integration is one of the steps needed when they upgrade to a new system.

Farther east on Northpark at Russell Palmer Road, several weeks ago, a contractor realized the “pedestrian push-to-cross signal” on the north side of Northpark was not connected to the controller box.

According to Ralph De Leon, Northpark project manager, connection involved boring underneath the roadway, installing conduit, then running wire, etc. That’s done now. Now the City needs to run their diagnostics, inspect everything and only then can the signals become operational.”

De Leon described the complexity, “Signal boxes now have their own IP address. They are complex devices that run on software that generates endless codes/numerical signals. In terms of process, we bought the traffic signal control box, handed it to the City, they put it in their shop, loaded the software, programmed its computer, generated a logbook, then ran diagnostic after diagnostic.”

I noticed City crews working on stoplights at several places on Northpark today. So. we may be close. The new target date for fully functional signals at Russell Palmer is July 31.

Entry Ponds

Sunlight can break down pond liners unless water covers them. So, closing on the property that will hold the well that keeps the ponds full was necessary before the pond liners could be placed.

A sale-and-purchase agreement for land has now been signed by all parties. The earnest money was deposited yesterday and the title company is working on scheduling the closing.

Now, De Leon is working with KSA, which has agreed to operate the well long-term.

Posted by Bob Rehak on 7/24/2026

3251 Days since Hurricane Harvey

Northpark Entergy Saga: New Power Poles Slowly Going Up

In the latest episode of the Northpark Entergy saga, last week, Entergy finally began erecting new power poles outside of the Northpark Drive expansion right of way. While this is a huge improvement after four years of no Entergy activity, don’t get too excited.

In its quest to help develop an all weather evacuation route for 78,000 people, Entergy managed to erect four poles in five days. And there’s no sign of progress near Entergy’s transformer by the Exxon station at US59 either.

In other Northpark news:

  • The extra northbound turn lanes at 59 seem to be complete almost all the way back to Chick-Fil-A.
  • At Russell Palmer and Northpark, the crossover closure will take longer than expected.
  • Construction of the four decorative planting areas in the two stormwater retention-basins at US59 is now complete and contractors have filled in dirt behind the retaining walls.

See photos and details below.

Last of four decorative landscaping areas (right) is now complete and backfilled.
Entergy … La La, La La La!

On 4/2, I reported that Entergy had delivered new power poles to Northpark in preparation for moving their lines out of the City right of way.

Five days later and four years after first being notified, Entergy appears to have erected a grand total of four poles while others remain scattered on the ground.

The four Entergy power poles erected along Northpark during the week of April 1, 2024

Here’s what two look like from the ground.

See new poles on the right. Entergy has not yet placed equipment on any poles, nor has it relocated wires.

Meanwhile, many of the poles they delivered to the job site last week remain scattered on the ground.

Looking E. Northpark Drive (on right). UP Railroad Tracks out of frame on the bottom.

Moving the poles back will make room to construct turn lanes from Northpark onto Loop 494.

As I photographed Entergy’s underwhelming progress, I was reminded of what American ingenuity can achieve when companies put their shoulders into projects.

For instance, the transcontinental railroad took six years to build. Even more impressive is what the companies could achieve in a day…without modern equipment.

The Union Pacific once laid eight miles of track in a single day. Stung by the competition, “the Central Pacific concocted a plan to lay 10 miles in a day. Eight tracklayers put down 3,520 rails, while other workers laid 25,800 ties and drove 28,160 spikes in a single day.”

Compare that to Entergy’s four poles in four years. I guess that’s what happens when you give companies a monopoly in an area.

On February 6, the City of Houston gave Entergy an ultimatum to have the project completed by March 8. Tomorrow will be April 8.

Entergy appears to have put its A Team on the project. Speaking of A Teams, it only took three years to invent the atomic bomb, test it, deliver it, and conclude World War II.

But of course, Entergy is dealing with electricity and there are safety issues involved.

Entergy transformer at US59 still unmoved.

The Entergy transformer will require some study. To inspire public confidence, Entergy reportedly is putting its top engineers on the project.

Northbound Turn Lanes onto US59

On a happier note, traffic is now using new northbound turn lanes at US59, temporarily eliminating a huge bottleneck…until new pavement will go down for the existing lanes.

Looking W from 59 toward 494. North is left.

A new schedule posted by the Lake Houston Redevelopment Authority shows that most work in the next month will focus on underground utilities. Those include water lines, storm drains, and box culverts on both sides of the street.

According to the schedule, Harper Bothers Construction will also install the giant reinforced box culverts in the median of Northpark toward 59 for the rest of the month.

Before pavement goes farther east, more underground work is needed. Note culvert lined up in front of businesses.

Russell Palmer Crossover Work Delayed

The work near the Russell Palmer intersection must be taking longer than expected. Originally it was supposed to be finished by tomorrow morning at 5AM. But the new schedule shows it being completed by next Friday, 4/12/24.

A flashing sign along Northpark this morning warmed motorists to expect daily lane closures. However, there were none this morning. And contrary to earlier announcements, motorists were making it through the intersection.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/7/24