Tag Archive for: northpark

Northpark Entry Plan Balances Flood Mitigation, Saving Trees, Cost

Social media has been abuzz this week about the Northpark Drive entry to Kingwood. As contractors removed trees from the north side of the road to make room for a detention pond, many people complained.

But it’s important to remember why we’re improving Northpark: to accommodate increased traffic and to create a reliable, all-weather evacuation route. In that regard, the Lake Houston Redevelopment Authority (LHRA) must balance three conflicting needs: flood mitigation, saving trees and cost. Let’s look at how each relates to the objectives.

Reliable, All-Weather Evacuation Route

During Harvey, Hamblen Road, Kingwood Drive and Northpark were all blocked by rising floodwaters. That forced many people to try to snake out of Kingwood through Porter…if they could get there. Many couldn’t.

For decades, we’ve also worried about the possibility of a train disaster that could block off Kingwood’s exits. The longer trains that Union Pacific runs now can block multiple exits simultaneously. The longest trains stretch for more than three miles. And if there were a derailment or toxic spill, it would be difficult getting people to safety.

Raising the elevation of Northpark between Bens Branch and the Kingwood Diversion Ditch eliminates the first problem. And building the bridge over the tracks at 494 eliminates the second.

Finally, widening the road will enable more vehicles to evacuate faster.

Flood-Mitigation Enhancements

All that extra concrete to expand the road, however, reduces rainwater infiltration and increases runoff. To keep the road from flooding, engineers calculated they needed 22 acre feet of stormwater detention capacity near US59.

The solution: build two permanent ponds, one each on the north and south sides of 59 where the groves of trees were. TxDoT already owned the land. So it was available at no cost.

Looking N toward Kroger Center. Clearing for N pond completed. Clearing for S pond (bottom right) begins next week.

Water will permanently fill the ponds, just like those at Kingwood Drive. The difference between the normal water surface elevation and the lip of the ponds will equal 22 acre feet. The size of the ponds will keep that gap at an aesthetically pleasing level.

Looking S. Note the protective fencing around the remaining trees. Additional trees may be stored temporarily in the foreground.

Said another way, the ponds will look like decorative enhancements but serve a vital purpose that few realize.

The outline you see in the photo below will match the perimeter of the pond.

No more trees will be cut for this pond. The area cleared represents the final outline of the pond.

The layout below shows how the ponds should look when completed.

For a more legible, high-res version, click here.

Saving Trees

According to Ralph De Leon, project manager, “Enough trees will remain to form a pleasing backdrop for the pond, screen the visually noisy area behind them, and create a good first impression for visitors.”

From 30 feet, you can barely see the shopping center behind the trees. From ground level, it will be completely screened.

It’s important to remember that when KSA revised the Kingwood entries after TxDoT widened 59, many people wanted ponds at Northpark. They complained that KSA was neglecting Northpark compared to Kingwood Drive.

Many trees are being transplanted. But that’s an expensive proposition; the trees have grown since LHRA first prepared estimates two years ago.

“We’ve already identified the trees that will be saved,” De Leon continued. “Some will move to their permanent location immediately. Others will be stored temporarily at staging locations until the road construction gets further along. Then they’ll be moved to their permanent positions.”

The landscape architects, contractor, and LHRA are evaluating each tree individually. Their objective is to save as many as possible. But dollars pose a constraint.

Cost Limitations

De Leon also says “The cost to move each tree is roughly $11,000. We can’t afford to move the truly huge trees. They cost up to $100,000 per tree. And we just don’t have a budget for those.”

Machines like these will move trees that range from 4″ to 17″ in diameter. Photo courtesy of Davey Tree Company.

To maximize aesthetics, the Redevelopment Authority will relocate a mix of trees, such as oaks and pines.

The trees that will move have already been inventoried and tagged.

Update on Water-Line and Utility Conflicts

In my last Northpark post, I pointed out two conflicts holding up construction of the median farther east – one with a water line to a new church near Russell-Palmer Road and a second with CenterPoint.

The City of Houston has agreed to let the Redevelopment Authority’s contractor design a workaround for the water line that interfered with the placement of box culverts. Contractors left a gap big enough for two sections of culvert and a coffer dam to keep dirt from collapsing into the hole.

Because the culvert is tongue-in-groove, contractors also left enough room for a collar. That will allow the two new sections to slide into place. It will also prevent leaks in any gap that remains.

Regarding the CenterPoint gas line running down the center of the ditch at different depths, CenterPoint decided to move the whole line out of the culvert to the south side of the road. Inbound drivers may notice long lengths of welded blue pipe stacked up between Russell-Palmer and Kings Mill. That’s what that is for.

Next Steps

Contractors will start removing trees for the south entry pond at 59 during the week of 9/24/23. Here is the latest revised schedule. Check back often for more updates as they happen.

Posted by Bob Rehak on 9/23/23

2216 Days since Hurricane Harvey

New Design for Northpark Entry, Construction Schedule Update

Harper Brothers Construction has encountered another unexpected problem in the Northpark Drive expansion project. While attempting to place 5’x7′ culvert in the median, it uncovered a water line much closer to the surface than it should have been. While developing a solution with the City of Houston, crews will continue to focus on other areas of the project so as not to create excessive delays.

Those areas include:

  • A new water main near 494 and the UP railroad tracks
  • Clearing land for the new Northpark entry to Kingwood at 59.

For background detail and photos, see below.

Pics of Water-Line Conflict

This week, Harper Brothers discovered a water main where it should not have been. The contractor proposed water-line workarounds to the City, but the City has not yet agreed to a solution. The issue has to do with a water main running under Northpark to the new Parkwood Baptist Church east of Russell-Palmer. See the pictures below, courtesy of the Lake Houston Redevelopment Authority (LHRA).

Surprise water line under Northpark
Workers discover a surprise. Water line under Northpark not where it was supposed to be.
Surprise water line under Northpark
Water line should have been buried several feet deeper.
Surprise water line under Northpark
One workaround could require burying a parallel line deep enough to allow placement of culvert over the top of it.

Harper Brothers Construction suggested another workaround – splicing in a U-shaped pipe that would leave enough room for the culvert it is burying in the median.

But until the City and LHRA agree on a solution Harper Brothers may have to skip past the obstruction and then go back at a later date to fill in the gap.

Second New Water Main Farther West

In the meantime, crews have already started prepping for placement of another water line that parallels Northpark closer to Loop 494. See picture below near Public Storage.

Looking SE. Note area being cleared in foreground for new water main and feeder roads next to bridge.

While Northpark will expand inward for most of its length, the feeder road next to the new bridge over 494 and the railroad tracks will expand outward. And because the City doesn’t like to run water mains under a roadway, contractors must also relocate this water main. It’s a much bigger job because it feeds numerous businesses, not just one church.

LHRA actually had to purchase additional land for this portion of the project – enough to accommodate a two-lane feeder road on each side of the bridge.

In the photo above, you can see Harper Brothers prepping land for the new water main and feeder lanes.

Plans for New Entry

The contractor will also soon start clearing the triangular area on the north side of Northpark at 59. Note construction materials stockpiled in the foreground of the photo below. Most, but not all of this area, will become a decorative pond that’s actually a stormwater detention basin in disguise. The pond will hold approximately 11 acre feet of stormwater in the space between the top of the permanent water level and ground level.

A second pond on the south side of Northpark will provide a similar amount of stormwater storage to compensate for the increase in impervious cover caused by road widening.

But not all the trees will go away. TxDoT requires that any trees removed must be replaced with trees of an identical diameter.

Site of first detention pond. Pond will be framed by trees that remain between Northpark and shopping center on right.
Some trees will be relocated to the open area currently behind the grove.

Other trees will be relocated nearby, for instance, around the south pond which is more sparsely populated with trees.

South pond will have more room for transplanted trees around it.

In addition, the ponds when complete will have sidewalks and landscaping around them. TxDoT, LHRA and the Kingwood Service Association worked collaboratively on the designs for two years. A well will serve the area and feed an irrigation system to help ensure new plantings survive and thrive.

Here’s what the finished ponds and landscaping should look like.

North pond (the first) shown on the left.

For the full entry landscaping plans, click here.

To see a video rendering of the ponds, click here and then click on the video in the lower right.

Clearing was to have begun on Tuesday morning after Labor Day. However, that may be delayed now. Late on Friday afternoon several logistical issues involved with relocating the trees became apparent.

CenterPoint Promises to Stake Out Problems Week of 9/3/23

Last week, we talked about 11 conflicts with CenterPoint along the Northpark Drive expansion project. CenterPoint has promised LHRA that it will send crews to “stake out” the problems next week. That is the first step in resolving conflicts.

Some of the CenterPoint conflicts that have culvert placement stalled.

It’s always something in construction! Stay tuned for next week’s exciting episode of “As Northpark Expands.”

For a look ahead at the next three weeks of construction activity, click here.

Posted by Bob Rehak on 9/2/23

2195 Days since Hurricane Harvey and 10 days before the peak of hurricane season

February Update on Northpark Drive Expansion

My posts earlier this week about repair of the Northpark Drive drainage ditch between Loop 494 and the Kingwood Diversion Ditch sparked a flurry of questions. People wanted to know when the Northpark Drive expansion project would begin. Last July, local leaders felt it would begin before the end of 2021. Obviously that didn’t happen. So I reached out to Stan Sarman, chairman of the Lake Houston Redevelopment Authority (LHRA) and Tax Increment Reinvestment Zone (TIRZ) #10 (Kingwood).

Sarman, an engineer by trade, said “I never thought it would take this long to obtain all the Right-Of-Way easements and approval of the plans by the City of Houston and Union Pacific Railroad (UPRR). Below is a summary of the information that was reported at the LHRA/TIRZ10 Board meeting on February 10th.”

“The 100% construction plans went to the City and UPRR,” continued Sarman. “We are now getting more comments from the City Public Works people. There is to be a meeting next week with our consultants and the City staff to work through the comments.” 

“The UPRR approval is not expected until late March, 2022, according to UPRR’s consultant. We have 6 or 7 easements remaining and we are close to getting across the finish line by the end of March.”

“The best estimate I have,” said Sarman “is to try and bid the job in April, 2022, and start construction in mid summer. We will keep the public informed of when we expect construction to start.”

The money is in the TIRZ budget, which the City approved. See pages 7-9 of Exhibit A in this PDF.

Northpark Drive Reconstruction Project Overview

Here’s a link to more information about the project on the LHRA website. Northpark Drive reconstruction consists of two projects right now.

T-1013 Northpark Drive Overpass Project (Western Phase)

The reconstruction of Northpark Drive into a 6-lane divided roadway, between IH-69 and Russell Palmer Road and an overpass over the UPRR train tracks and State Loop 494. Projected to take 30 months after start of construction.

T-1014 Northpark Drive Reconstruction Project (Eastern Phase)

The reconstruction of Northpark Drive into a 6-lane divided roadway, new bridges at the Kingwood Diversion Ditch and Ben’s Branch and a pedestrian tunnel near Glade Valley Road. Projected to take 24 months after start of construction.

Say Goodbye to the Ditch

A giant buried box culvert will replace the ditch down the middle of the Northpark and the extra lanes will go over the top of it.

Other features include:

  • Drainage will be sized to comply with new higher Atlas-14 requirements.
  • Dual 10-foot wide pathways on the north and south sides of Northpark Drive from Rock Creek Drive to Russell Palmer Road will facilitate bicycle and pedestrian traffic.
  • Enhanced lighting and landscaping.

This project can’t come soon enough for me. Coming inbound to Kingwood today from US59, I saw outbound traffic stacked up for more than a mile past Russell-Palmer Road! That’s an everyday experience as shown by this file photo taken last July 28.

Northpark Drive looking east at outbound traffic on left side of road. Taken July 28, 2021 from over the UP railroad tracks.

If traffic backs up this far in the middle of a sunny afternoon, imagine how far it would back up when thousands were trying to evacuate from a flood.

Posted by Bob Rehak on 2/19/22