Northpark Making Good Progress Despite a Few Hiccups
4/25/26 – Since I last posted about the Northpark Drive Expansion Project in Kingwood eleven days ago, contractors have continued to push forward.
They have also virtually completed everything east of the bridge abutment all the way to the eastern terminus of the project near the Kingwood Diversion Ditch. Here’s an update on what is and isn’t complete in Phase I.
Eastern Part of Project Virtually Done
The entire project from US59 to the eastern terminus is about a mile. Eight-tenths of that mile is virtually complete – everything between Parkwood Baptist Church to the start of the eastern bridge abutment in front of the Quick Quack Car Wash.
In this segment of the project, I observed:
- Medians that need to be planted with grass in some areas
- One lane of traffic on each side of the median still blocked off
- Traffic cones still blocking off turn lanes where new traffic control lights have not yet been activated
- A few gaps in “multi-use pathways.” They’re those things that resemble sidewalks, but are wider.
Other than that, it’s clear sailing in wider lanes than existed before the project. See the pictures below all taken during the afternoon of April 24, 2026. The sequence goes from east to west beginning near Russell Palmer Road.







Bridge Construction
Things get a little hairier in the last 2/10s of a mile. The east abutment is coming along well. It appears to have reached its full height or close to it.

According to the new three-week look ahead schedule, contractors will begin paving up to the ramp next week.
Railroad Crossing
So far, that’s all great news. But Northpark contractors still are working out issues at the UnionPacific Railroad crossing near Loop 494.
On the south side of Northpark, two traffic signal poles still block completion of the new surface lanes. Of course, they’re needed to control traffic for now.


Zig Zag Continues
Traffic near Loop 494 continues to curve in and out around a) the eastern bridge abutment and b) where the western bridge abutment will eventually go between Whataburger and PNC Bank.


Entry-Pond Excavation
Meanwhile, excavation of the south entry pond at US59 continues.


Contractors will apply cement and line both ponds at the same time to save money. That should happen around mid-May, 2026.
Street Illumination and Hydro-Mulch for Ditch One
The street light crew is continuing installation of street light foundations and light poles throughout the project.
Ditch 1 reestablishment has been completed.

Contractors will seed the slopes with hydro-mulch during the week of 5/4/26, weather permitting.
For More Information
See the Lake Houston Redevelopment Authority/TIRZ 10 web pages associated with this project for plans, videos and construction timelines. They also include a new 3-week lookahead schedule.
You can also search this website for “Northpark” for links to close to more than 200 posts about the progress of the project.
Posted by Bob Rehak on 4/25/2026
3161 Days since Hurricane Harvey

















































































