Tag Archive for: construction spending

HCFCD Construction Slowdown May Be on Verge of Turnaround

07/27/26 – New spending figures are available from Harris County Flood Control District (HCFCD) through the end of 2026 Q2. This quarter marks the end of Dr. Tina Petersen’s administration and the start of new Executive Director Marcus Stuckett’s. In that sense, it represents (pardon the pun) a watershed moment.

HCFCD spending data shows that Stuckett inherits a production pipeline that was not pushing flood-mitigation projects into and through construction at historically normal rates.

Eight years into what was supposed to have been a 10-year bond program, Harris County has spent only 37% of the dollars approved by voters while inflation in the heavy-construction sector of the economy has totaled more than 50%.

As a consequence, inflation is taking a huge toll on the Flood Bond’s purchasing power…and making residents live with higher flood risk longer than necessary.

But there’s also some good news: 6 HCFCD construction jobs on the Harris County Commissioners Court Agenda this week!

Let’s look at each of these points.

Construction Slowdown

Shortly after voters approved the flood bond in 2018, spending on flood-mitigation projects soared. But then, the team that sold the bond and defined hundreds of projects was pushed out by Democrats starting in 2021.

Precinct 2 Commissioner Adrian Garcia managed to get Dr. Tina Petersen appointed head of HCFCD at the start of 2022. And ever since, for whatever reason, project activity has plummeted. You can clearly see it in the rate of spending below – despite having billions of dollars available.

HCFCD spending since 2018 Flood Bond as of 26Q2. Far right reflects only 2 quarters. But even doubled, 2026 would represent a continuation of the long-term decline.

The gray area in the graph above represents construction spending. It has dropped almost by half since its peak during the previous administration. Construction is down to $90 million per year [annualized] from $160 million per year [actual].

As a result of the slowdown, Harris County could lose hundreds of millions of dollars in HUD Community Development Block Grants for Disaster Relief, whose deadlines are fast approaching.

Lower-than-Normal Construction Expenditures as Percent of Total

Typically, construction accounts for about 65% of most flood-mitigation projects, give or take 10%.

That number can vary even more depending on land-acquisition costs, environmental permitting, etc. There are always exceptions. But on average, 65% is considered a defensible rule of thumb for planning purposes by many flood experts; some suggest the figure may even be higher.

So, how has HCFCD spending compared? It falls far short of 65%. Looking at everything spent to date, only 46% has been on construction. But even that number may be deceptively high.

Construction spending on maintenance masks what’s happening on the capital-improvement side. So let’s also look at each sub-category.

As of 7/1/2026. Computed from HCFCD 26Q2 Bond Update.

HCFCD capital-improvement construction spending to date is just 37% of all capital improvement costs. And the Total percentage is buoyed up by construction spending on Maintenance.

Remember that only capital-improvement construction dollars actually reduce flood risk.

Only 37% of Bond Money Spent After 8 Years into 10-Year Bond Program

There’s another significant takeaway from last quarter’s update. HCFCD has spent only 37% of the bond money approved by voters – eight years into what was supposed to have been a 10-year bond program.

Sorting expenditures on the HCFCD Activity Page by “Fund Source” shows that only $932.69 million of the $2.5 billion bond has actually been spent to date. This excludes district and partner funds.

2018 Flood Bond Funds spent to date by watershed

54% Inflation in Heavy Construction Sector Since Start of Flood Bond

But all the data above illustrates only part of the problem. Cumulative inflation in the heavy-construction sector of the economy totals 54% from mid-2018 (when voters approved the Flood Bond) to mid-2026. (Source: Federal Highway Administration’s National Highway Construction Cost Index, considered by many as a good analog for flood-control work).

This inflation has progressively eroded the purchasing power of flood-mitigation construction budgets.

A Bad Institutional Hangover

Problems moving projects into and through HCFCD’s production pipeline in a timely way has resulted in:

  • Inflation gobbling up a large percentage the bond’s purchasing power
  • Fast-approaching deadlines jeopardizing hundreds of millions of dollars in federal funding
  • People living with higher flood risk longer than necessary.

Yet Commissioner Adrian Garcia defended former HCFCD Executive Director Dr. Tina Petersen to the bitter end… against the interests of his own constituents. It will be interesting to see if this affects his re-election campaign this Fall.

Some Good News This Thursday

There is some good news in all of this on the horizon. It looks like HCFCD’s new Executive Director, Marcus Stuckett, is making an immediate impact. This Thursday’s Commissioner’s Court agenda shows six CIP projects starting construction or going out for construction bids. They include:

  • Meyergrove Stormwater Detention Basin
  • Halls Bayou Channel Conveyance Improvements – Phase II
  • T.C. Jester Stormwater Detention Basins – Compartments 1A and 2
  • Lauder Stormwater Detention Basin – Phase 3A
  • Genoa Red Bluff Stormwater Detention – Basins Phase 2 – CDBG-DR/MIT
  • Kluge Stormwater Detention Basin – Phase 3 – CDBG-DR/MIT

Hopefully Stuckett can get construction projects moving again.

Posted by Bob Rehak on 7/27/26

3254 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

HCFCD Construction Spending Continues to Plummet

10/26/25 – Harris County Flood Control District construction spending has plummeted in recent years along with total spending. And a leading indicator – construction contract awards – doesn’t show much hope for improvement anytime soon.

Numbers Tell the Story

I’ve posted before about the decline in total spending. It ramped up sharply after voters approved the flood bond in the third quarter of 2018. But then it started dropping relentlessly. The decline largely coincided with a management change made by the Democratic-controlled commissioners court.

From HCFCD Activity page as of 10/25/25. *2018 included only one quarter. **2025 includes three quarters.

The last bar on the right includes only three quarters. But at the current rate, 2025 will equal about $166 million – down about a third from 2024.

Total spending includes many activities besides construction. But flood risk isn’t reduced until construction is finished. And we see a similar decline in construction spending that started when HCFCD management changed at the start of 2022.

From HCFCD Activity page as of 10/25/25. *2018 included only one quarter. **2025 includes three quarters.

But the graphs above only show activity in the rear-view mirror. Looking forward, the picture is equally bleak.

Approved Bids: A Leading Indicator for Construction

Few new projects have had construction contracts awarded in the past year. Of the 16 construction contracts awarded in the previous four quarters, 14 have been for maintenance to existing assets.

Only two, both in White Oak Bayou, have been for new capital assets – the Yale and Arbor Oaks Stormwater Detention Basins. See below.

Page 2 of HCFCD latest Bid Outlook, transmitted to Commissioners Court for 10/30/25 meeting.

All of the rest simply restore functionality. So…

The prospects for flood-risk improvement in the immediate future look bleak for the vast majority of the county.

HCFCD awarded the construction contract for Arbor Oaks in Q2 this year. But excavation had not yet started as of late September 2025.

Deadline Rapidly Approaching for Grants Totaling $321 Million

The Texas General Land Office (GLO) and U.S. Department of Housing and Urban Development (HUD) approved 11 projects for Community Development Block Grants in the Disaster Relief category (CDBG-DR).

The 11 projects including Arbor Oaks total $321 million dollars. But to get the money, HCFCD must complete the projects by February 28, 2027, to meet HUD’s deadline.

However, construction will need to be completed by December 2026 – thirteen months away – because it generally takes two to three months to administratively close out CDBG grants.

But according to HCFCD’s most recent bid outlook, flood control won’t even advertise eight of the 10 remaining projects until next year. And another slipped off the radar altogether.

CDBG-DR projects approved by HUD, but not yet bid by HCFCD. SWDB = Stormwater Detention Basin. CCI = Channel Conveyance Improvements.

Phase II of the Brookglen Stormwater Detention Basin received authorization to use government funds in August 2024. Yet HCFCD doesn’t even anticipate advertising it for bids until November 2025 – 15 months. That’s more time than HCFCD has to complete construction.

Little time remains to complete projects of this magnitude. And HCFCD has not explained how it will complete them before the deadline. HUD has already said they will not grant any more extensions.

This represents a real risk. Harris County residents could lose $321 million of Federal funding for important flood damage reduction projects.

Hidalgo Says Audit Revealed Contracting Irregularities

Meanwhile, according to a Houston Chronicle story published on 10/22/25, Harris County Judge Lina Hidalgo “called for renewed scrutiny of the Harris County Flood Control District after a recent audit found transparency issues in its contracting process.”

The Chronicle reported that Hidalgo said, “What we found was there was no paper trail. There was no qualifications, information, selection committee, evaluation scoring — no documentation whatsoever.”

The Chronicle story added, “Flood control initially promised to reform its contracting process by August 2024, but has since asked for multiple extensions.”

Sound familiar?

No Apparent Sense of Urgency

HCFCD had only four items on the agenda for the 10/30/25 Commissioners Court meeting. Not one of the four items had to do with any of the ten CDBG-DR projects above. One involved a contract name change; the other three involved small property acquisitions.

HCFCD has billions of dollars waiting to be used. But at this moment, not one new capital improvement project is being bid.

All open HCFCD bid opportunities as of 10/26/25.

And yet earlier this year, HCFCD’s executive director received a pay increase of $90,000 to $434,000.

Call me old fashioned, but I believe in “pay for performance.” I wonder what metrics Hidalgo used to recommend such a bump in pay. How can someone get paid so much to accomplish so little?

Posted by Bob Rehak on 10/26/25

2980 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Where the Flood Mitigation Money Has Really Gone: Part Two

At Harris County Commissioners Court yesterday, “equity” proponents from low-to-moderate-income (LMI) neighborhoods in Precinct 1 again complained they weren’t getting their fair share of flood mitigation dollars. In crying “foul” over a perceived lack of buyout dollars, they ignore the fact that the bulk of Federal mitigation spending is on construction projects that benefit their precinct.

The Federal Government is contributing $814 million to joint HCFCD/Army Corps projects that benefit Precinct 1. Only one joint project in Harris County does NOT benefit Precinct 1.

Part One of this series focused on Harris County construction spending for flood mitigation. It found that Precinct 1, which is 78% African-American and Hispanic, received 47% of all Harris County Flood Control District (HCFCD) dollars spent on construction. That left three other precincts to divvy up the remaining half. But Federal contributions for construction spending are even more lopsided as the chart above shows.

2018 Federal and Harvey Reports Yield Surprises

In Part Two, I examine Federal construction spending in Harris County on joint Army Corps/HCFCD projects. Some are Corps-led; others County-led. Regardless, they all involve Federal contributions. Close review of the latest Federal Report from HCFCD and other information obtained through the Freedom of Information Act reveals some startling facts.

  • Precinct 1 benefitted from more Federally-backed projects than any other precinct.
  • Only one Federal project did not benefit Precinct 1.
  • Sims Bayou, which lies mostly within Precinct 1, was the only one of six Federal projects completed before Harvey. And it was one of the few bayous in the County that did not widely flood.
  • The Lake Houston Area received no Federal dollars for flood mitigation prior to 2018.

Federal Investments Ignored by Precinct 1 Activists

The only joint project actually completed before Hurricane Harvey was in Precinct One. It involved the widening of Sims Bayou and creating additional detention ponds. Together, these actions almost eliminated flooding during Harvey. A huge benefit to Precinct 1. See map below.

Sims Bayou in Precinct 1 was one of the few bayous in Harris County that did NOT come out of its banks during Harvey. See green arrow. The San Jacinto watershed (red arrow) flooded along its entire length and received NO Federal dollars prior to Harvey.

Sims Completed and Did Not Flood Widely

On page 6 of its Final Harvey Report, HCFCD states, “Sims Bayou was one of the few channels in the entire county that did not suffer widespread and extensive overbank channel flooding largely due to the completion of the federal flood risk reduction project and three HCFCD regional detention basins. Water levels for Harvey were generally below the historical records of Tropical Storm Allison and averaged between a 2.0% (50-yr) and 1.0% (100-yr) level downstream of Martin Luther King Blvd and generally below a 10% (10-yr) annual exceedance probability from Airport Road upstream to the headwaters.”

Sims Project Saved Thousands of Homes from Flooding

Further, Page 19 of the final Final Report on Hurricane Harvey notes,”The recently completed … Federal Project and supplemental detention basins constructed by HCFCD reduced the number of homes flooded by about 6,500 along Sims Bayou.”

“Bottom line – the larger channel carried a lot more stormwater downstream away from subdivisions along the bayou and the large detention basins stored stormwater that would otherwise flow through subdivisions along the bayou.” 

The Harris County Flood Control District Federal Briefing (Page 102) from 2018 also shows that the Sims project removed more than 35,000 homes and 2,000 commercial structures from the 100-year flood plain.

The Sims project received $390 million: $125 million from HCFCD and $265 million from the Army Corps.

In contrast, the Federal Briefing lists $0 in federal funding for the San Jacinto watershed.

Hunting Bayou and Achieving “Social Justice” in Precinct 1

At least one Army Corps project in Precinct One won Corps support because of the presence of LMI neighborhoods. Yet “equity” proponents contend the Federal government discriminates against them.

Page 79 of the Federal Report indicates Hunting Bayou (entirely within Precinct 1) received $98 million from the County and $68 million from the Corps, in part because of social justice factors. That’s another $165 million.

Residents claimed in their plea for funds that:

  • “Residents in the Hunting Bayou watershed deserve the same level of potential flood risk reduction as those who live in other parts of Harris County.
  • “The economically disadvantaged Hunting Bayou residents struggle severely to recover from house and business flooding.”
  • “The Corps’ economic analysis is an important factor in prioritizing competing projects for annual Federal funding, but it is biased against economically disadvantaged communities like in Hunting Bayou.”

Prior to 2018, had Hunting Bayou residents received the same level of support as those in the more affluent Lake Houston Area, they would have received NO support from the Federal government.

Three Other Precinct 1 Watersheds Receive Major Federal Support, Too

Three other watersheds in Precinct 1 have received major federal and county commitments for construction of flood mitigation measures. Because they are in various stages of completion, I show total cost estimates below to facilitate comparison.

  • Brays Bayou which flows through precincts 1, 2 and 3 will receive a total of $480 million; half from the county and half from the Corps. See page 60.
  • White Oak Bayou flows through Precincts 1 and 4. There, the County and Corps are excavating 9.7 million cubic yards of detention basins. That’s more than 5 times the volume of sediment removed from the San Jacinto to date. Estimate: $124 million, $90 million of it at Federal expense. See page 68.
  • Clear Creek flows through Precincts 1 and 2. Estimate: $249 million, $98 from local and $151 million from the Corps. See Page 91.

One Lone Exception

The Federal government partnered with HCFCD on only one project in Harris County that did not directly benefit Precinct One: a detention pond in Precinct 4 on Greens Bayou near 249, Beltway 8 and Cutten Road. This $58 million project received $43 million from the Corps. See Page 97.

The Corps does have other projects in Harris County, such as the Addicks and Barker reservoirs. However, HCFCD plays no active role in those. Likewise for the San Jacinto dredging project. This analysis looks only at joint projects that involve Harris County and the Corps.

Federal Construction Versus Buyout Dollars

Because Mr. Ellis’ surrogates base their arguments on buyouts, we need to put those in perspective.

Buyouts are tiny compared to construction spending. In Harris County, they represent just 6.6% of Federal construction spending for flood mitigation.

Page 120 of the 2018 Federal Brochure deals with buyouts. It shows approximately two dozen buyout projects completed in Precinct One. However, few if any appeared active at the time of publication in 2018.

In the entire county, FEMA was funding only $57.1 million in buyouts.

But the Army Corps contributes 19 times more than that in construction dollars for projects that benefit Precinct 1.

The numbers below represent Federal contributions only:

  • Sims – $265 million (In Precincts 1, 2)
  • Hunting – $68 million (In Precinct 1)
  • Brays – $240 million (In Precincts 1, 2, 3)
  • White Oak – $90 million (In Precincts 1, 4)
  • Clear Creek – $151 million (In Precincts 1, 2)
  • Total Estimated Federal Contribution to Joint Construction Projects that benefitted Precinct 1: $814 million
  • Total Estimated Federal Contribution to Joint Construction Projects NOT benefitting Precinct 1 (Greens): $43 million
  • Total Estimated Federal Contribution to Joint Projects in Lake Houston Area before 2018: $0

And Commissioner Ellis’ surrogates complain about discrimination! Maybe that’s why they get so much money.

Note that HCFCD does not break out spending “by precinct” for bayous that flow across precinct boundaries; they list only project totals. The list of bayous above represented ALL the HCFCD/Corps projects in the 2018 Federal Report.

Note also: Video of the commissioners meeting still had not been posted at the time I posted this story.

Posted by Bob Rehak on 6/26/2019

666 Days since Hurricane Harvey