Precinct 1 Commissioner Rodney Ellis has placed an item on the Commissioners Court agenda for 1/10/23 with far reaching ramifications for flood control in Harris County. It would change the way every future project is prioritized using a formula that gives almost half the weight to population and building density. Meanwhile, it ignores the amount of damage, severity of flooding, danger to infrastructure, historical underinvestment, and the difficulty of accurately estimating population in flood zones. Ellis’ recommendation could be used to permanently deny projects to heavily flood-damaged areas like Lake Houston.
Text of Motion
In Agenda Item #250, Ellis seeks: “Request for approval to direct the Harris County Flood Control District (“District”) to assign prioritization scores using the adopted 2022 Prioritization Framework for the Allocation of Funds from the Harris County Flood Resilience Trust to all new flood risk reduction projects funded by the District when requesting Commissioners Court approval to initiate the project, and to transmit those scores as quartiles to Commissioners Court.”
So what is that framework and why do we need it?
History of Recent Efforts to Prioritize Projects
Before the 2018 flood bond, Harris County flood control looked primarily at clusters of repeat damage to define and prioritize projects. That damage also formed the basis for obtaining partner funding in many cases.
However, when the perpetually underfunded Flood Control District received the huge infusion of cash from the 2018 flood bond, a problem arose. Which of the many worthy projects would be launched first? There simply weren’t enough qualified contractors to handle all needs simultaneously.
The text of the 2018 flood bond approved by voters contained a sentence that said, “…Commissioners Court shall provide a process for the equitable distribution of funds…” (See Paragraph 14-G). That became the key to the answer…with some verbal legerdemain by Ellis that turned “distribution” into “prioritization” and “equitable” into “equity.”
20% Existing Conditions (Drainage Level of Service)
20% Social Vulnerability
10% Project Efficiency
10% Partnership Funding
5% Long Term Maintenance Costs
5% Minimizes Environmental Impacts
5% Potential for Multiple Benefits
Total 100%
Commissioners, including Ellis, repeatedly affirmed their intent to complete all projects originally identified as part of the bond. The framework simply prioritized their start dates.
Commissioners also talked a lot about prioritizing “the worst first.” It was a nice sound bite, but never defined. Were the worst areas those with the most damage, deepest flooding, poorest residents, highest risk, or some combination of the above? Notice that the formula above omits flood damage, the traditional way of prioritizing funds and “ground-truthing” flood-risk estimates.
At this point, all of the projects in the bond have started. Their natural lifecycles and complexity will determine their order of completion. So, the debate has shifted from the flood bond to other sources of funding and future projects.
2021 Changes Applied to Flood Resilience Trust
In 2021, Commissioners created a Flood Resilience Trust using Toll-Road funds to backstop potential shortfalls in flood-bond partner contributions. The weighting used to allocate funds from the Trust changed significantly.
25% Structures Benefitted
20% Flooding Frequency
20% Social Vulnerability
10% Cost Per Structure
10% Partnership Funding
5% Maintenance Cost
5% Environmental Impact
5% Secondary Benefits
Total 100%
Flood Control used this formula only to prioritize the use of backstop funds in the Trust. Note this version of the formula eliminated both damage and risk reduction from consideration.
2022 Changes
In April, 2022, Commissioners modified the 2021 weights within the Prioritization Framework – still only for Flood Resilience Trust Funds – as follows:
45% Project Efficiency
15% Resident Benefits
30% Structure Benefits
20% Existing Conditions
20% Social Vulnerability Index
5% Long Term Maintenance Costs
5% Minimizes Environmental Impacts
5% Potential for Multiple Benefits
This 2022 formula omits consideration of damage, risk reduction and partnership funding. But it gives weight to population density (project cost divided by # residents benefitted). This 15-page PDF explains how projects are scored within each category above.
2023 Proposal
Commissioner Ellis now proposes applying the 2022 Resilience Trust formula to ALL FUTURE HCFCD PROJECTS.
Problems with Proposal
Flood Control would now use Ellis’ formula to decide which projects make the list, not just which go first.
Thus, the so-called “equity” formula once used to schedule projects could now be used to eliminate projects altogether.
Two thirds of the weight goes to density and social vulnerability. Only 20% relates to flooding.
The projects most likely to be eliminated would be outside the Beltway – in less dense areas that have traditionally received the least funding. In a post-bond, financially constrained environment, the weight given to density will put every project outside the Beltway at a disadvantage.
But the Ellis formula has many other problems, too. It:
Does not differentiate between types of structures while giving them almost a third of the weight. Thus, a mobile home counts for as much as a hospital or college.
Gives no weight to protecting critical infrastructure such as bridges, hospitals, grocery stores, wastewater treatment plants, etc.
Gives 20% weight to social vulnerability, but ignores the severity of flooding. Thus a low-income home with one inch of flooding counts as much as an entire condo complex swept away by 22-foot deep floodwaters.
Makes awards more subjective because HCFCD has no way of estimating how many people live in apartment buildings or homes. HCFCD can count buildings in satellite photos, but the number of residents benefitted will always be a guess. Census tracts do not follow floodplain boundaries.
Undermines efforts to prevent flooding, as opposed to correcting it after people are damaged. Prevention, such as HCFCD’s Frontier Program, is always more cost effective in the long run.
Forces Flood Control to judge projects before the District has engineering and cost data in hand that would help determine whether the projects are worth pursuing. That’s because “ALL FUTURE PROJECTS” include preliminary engineering projects.
Suggestions For Improvement
Below are several suggestions to improve the formula.
Define “worst first.” While the sentiment is noble, in practice, the term has no practical definition. (Ditto for equity.)
Incorporate measurements for severity of flooding and amount of damage. These really define worst.
Prioritize critical infrastructure such as bridges whose loss can jeopardize the economic vitality of the region.
Include partnership funds. They help stretch flood-mitigation tax dollars by almost a third. Even if people sometimes must wait longer to line up partner funding, partner funding helps more people in the long run.
Publish level-of-service data, used in the “existing conditions” calculation, for all streams in the county. It seems to be secret. I’ve been trying to get it for a year. Keeping it secret undermines trust in government. How do we know money is really going to the areas with the greatest risk?
Publish a 5-year Capital Improvement Plan similar to the City of Houston. Let people see what is coming, when, and for how much. That way we can hold HCFCD and Commissioners accountable. Plus, we can see their “formula” in action.
Be fair to all. The proposed formula is like playing cards with a stacked deck.
Posted by Bob Rehak on 1/7/23
1957 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/08/Ellis.jpg?fit=1200%2C809&ssl=18091200adminadmin2023-01-07 19:13:032023-01-08 10:27:15Ellis Trying to Change How All Flood-Control Projects Prioritized
The first leg of the three-mile route starts near the entrance to River Grove Park at the south end of Woodland Hills Drive in Kingwood. It used existing residential streets and new trails to snake its way to the Forest Cove Community Center. Then construction paused until demolition of the flooded townhomes on Aqua Vista, Timberline, and Marina Drives finished.
The second leg (dark purple below) follows existing streets through the old townhome site. However, contractors narrowed the streets to one lane. That accommodates bicycle and foot traffic, but limits most vehicle access.
Route of West Fork Greenway between River Grove Park and Edgewater Park.
The newest portion of the trail now extends from the Community Center to Hamblen Road via Timberline Pass, Timberline Drive, Aqua Vista and Burning Tree Court. The last street terminates at Hamblen, just west of the old Forest Cove Golf Course.
A final leg will extend west to Precinct 3’s Edgewater Park, paralleling Hamblen Road, but south of it (light purple).
Timing and Connections
Timing for the final leg has not yet been determined. Houston Parks Board eventually hopes to connect multiple waterways and adjacent hike and bike trail systems in the northern part of Harris County.
The pictures below, taken on 1/3/23, show the state of the most recent construction.
Landscaping along new trail (formerly part of Aqua Vista Drive. The trail is half the width of the old street. It should accommodate both hikers and bikers.Construction on Marina Drive and Timberline Pass. Forest Cove Community Center and Pool in upper left.Looking East.Reverse angle.Looking south from over Forest Cove Pool.Looking west from the former turnaround at the end of Aqua Vista.Facing west at trail connecting old Forest Cove townhome complex with Burning Tree Court. The latter turns north (right) and terminates at Hamblen Road.
More News to Follow When Plans Become Clear
The Parks Board plans to use some of the areas in the old townhome complex for parking. The fate of other streets remains unclear. Likewise, Harris County Precinct 3 has not yet announced plans for the long-awaited Edgewater Park. Harris County Flood Control District which bought out the townhome properties said it plans only to let the area return to green space.
Edgewater Park and this trail were one of the first good things to come out of Harvey. I just hope I live long enough to see them finished! Eventually, they will make a tremendous community asset.
Posted by Bob Rehak on 1/6/23
1956 days after Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/01/20230103-RJR_5433.jpg?fit=1200%2C800&ssl=18001200adminadmin2023-01-06 14:45:262023-01-06 14:45:29Next Leg of San Jacinto West Fork Greenway Now Hike- and Bikeable
The excavation rate of a sixth detention pond on Harris County Flood Control District’s (HCFCD) Woodridge Village property increased during the last month of 2022. That brought the total for the year to 73,745 cubic yards of soil removed under Sprint Sand and Gravel’s Excavation and Removal (E&R) Contract.
The reported total at the end of November was 67,529 cubic yards. That means the total for December was 6,216 cubic yards, the most for any month since last July. Compare the previous totals below.
Weekly totals through November
Excavation under E&R contracts varies depending on demand for fill dirt. Sprint’s contract with Harris County Flood Control District lets it take dirt basically for free and then sell the dirt on the open market to make its money.
The work could more than double the stormwater detention capacity on the site that flooded Elm Grove and North Kingwood Forest twice in 2019.
According to HCFCD, E&R agreements provide an opportunity for making progress in advance of future basin construction. These agreements essentially provide a head start in the excavation process before the detention basin is designed and constructed. In these agreements, an excavation company agrees to remove soil from a basin site during an agreed upon time period for minimal compensation. This is a cost-effective way for the material to be removed and it also provides significant savings by minimizing trucking and disposal fees.
Pictures Taken 1/03/23
Looking west toward the site entrance on Woodland Hills Drive.Contractors appear to be leaving some existing concrete culverts in place that will allow the new pond to drain into the old one at the top of frame.Looking NE. The pond could eventually extend as far as the grove of trees in the distance.
HCFCD expects that Sprint will excavate the full 500,000 cubic yards stipulated in their contract. That will expand the current stormwater detention capacity by 166%. The property only needed 40% more to meet Atlas-14 requirements. So this will provide a considerable margin of safety.
Other improvements include:
A concrete-lined, low-flow channel within the existing channel to expand conveyance from 350 feet downstream of Creek Manor Drive to 1500 feet downstream of Mills Branch Drive. The concrete portion would be four feet deep and 20 feet wide.
A new clear-span bridge at Rustling Elms to replace the current bridge over two culverts.
1955 Days since Hurricane Harvey and 1204 since Imelda
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2023/01/20230103-DJI_0594.jpg?fit=1200%2C799&ssl=17991200adminadmin2023-01-05 11:53:522023-01-05 11:58:00Woodridge Village Excavation Rate Ticks Up
Ellis Trying to Change How All Flood-Control Projects Prioritized
Precinct 1 Commissioner Rodney Ellis has placed an item on the Commissioners Court agenda for 1/10/23 with far reaching ramifications for flood control in Harris County. It would change the way every future project is prioritized using a formula that gives almost half the weight to population and building density. Meanwhile, it ignores the amount of damage, severity of flooding, danger to infrastructure, historical underinvestment, and the difficulty of accurately estimating population in flood zones. Ellis’ recommendation could be used to permanently deny projects to heavily flood-damaged areas like Lake Houston.
Text of Motion
In Agenda Item #250, Ellis seeks: “Request for approval to direct the Harris County Flood Control District (“District”) to assign prioritization scores using the adopted 2022 Prioritization Framework for the Allocation of Funds from the Harris County Flood Resilience Trust to all new flood risk reduction projects funded by the District when requesting Commissioners Court approval to initiate the project, and to transmit those scores as quartiles to Commissioners Court.”
So what is that framework and why do we need it?
History of Recent Efforts to Prioritize Projects
Before the 2018 flood bond, Harris County flood control looked primarily at clusters of repeat damage to define and prioritize projects. That damage also formed the basis for obtaining partner funding in many cases.
However, when the perpetually underfunded Flood Control District received the huge infusion of cash from the 2018 flood bond, a problem arose. Which of the many worthy projects would be launched first? There simply weren’t enough qualified contractors to handle all needs simultaneously.
The text of the 2018 flood bond approved by voters contained a sentence that said, “…Commissioners Court shall provide a process for the equitable distribution of funds…” (See Paragraph 14-G). That became the key to the answer…with some verbal legerdemain by Ellis that turned “distribution” into “prioritization” and “equitable” into “equity.”
2019 Equity Prioritization Framework
In 2019, Ellis proposed (and the Court adopted) the “Prioritization Framework for the Implementation of the Harris County Flood Control District 2018 Bond Projects.” This framework ranked projects with a multi-factor index using the following weights:
Commissioners, including Ellis, repeatedly affirmed their intent to complete all projects originally identified as part of the bond. The framework simply prioritized their start dates.
Commissioners also talked a lot about prioritizing “the worst first.” It was a nice sound bite, but never defined. Were the worst areas those with the most damage, deepest flooding, poorest residents, highest risk, or some combination of the above? Notice that the formula above omits flood damage, the traditional way of prioritizing funds and “ground-truthing” flood-risk estimates.
At this point, all of the projects in the bond have started. Their natural lifecycles and complexity will determine their order of completion. So, the debate has shifted from the flood bond to other sources of funding and future projects.
2021 Changes Applied to Flood Resilience Trust
In 2021, Commissioners created a Flood Resilience Trust using Toll-Road funds to backstop potential shortfalls in flood-bond partner contributions. The weighting used to allocate funds from the Trust changed significantly.
Flood Control used this formula only to prioritize the use of backstop funds in the Trust. Note this version of the formula eliminated both damage and risk reduction from consideration.
2022 Changes
In April, 2022, Commissioners modified the 2021 weights within the Prioritization Framework – still only for Flood Resilience Trust Funds – as follows:
This 2022 formula omits consideration of damage, risk reduction and partnership funding. But it gives weight to population density (project cost divided by # residents benefitted). This 15-page PDF explains how projects are scored within each category above.
2023 Proposal
Commissioner Ellis now proposes applying the 2022 Resilience Trust formula to ALL FUTURE HCFCD PROJECTS.
Problems with Proposal
Flood Control would now use Ellis’ formula to decide which projects make the list, not just which go first.
Two thirds of the weight goes to density and social vulnerability. Only 20% relates to flooding.
The projects most likely to be eliminated would be outside the Beltway – in less dense areas that have traditionally received the least funding. In a post-bond, financially constrained environment, the weight given to density will put every project outside the Beltway at a disadvantage.
But the Ellis formula has many other problems, too. It:
Suggestions For Improvement
Below are several suggestions to improve the formula.
Posted by Bob Rehak on 1/7/23
1957 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
Next Leg of San Jacinto West Fork Greenway Now Hike- and Bikeable
The second leg of the Houston Parks Board’s San Jacinto River West Fork Greenway is taking shape nicely. Contractors have apparently finished concrete work and landscaping. It can now be hiked and biked.
Route of San Jacinto West Fork Greenway
The first leg of the three-mile route starts near the entrance to River Grove Park at the south end of Woodland Hills Drive in Kingwood. It used existing residential streets and new trails to snake its way to the Forest Cove Community Center. Then construction paused until demolition of the flooded townhomes on Aqua Vista, Timberline, and Marina Drives finished.
The second leg (dark purple below) follows existing streets through the old townhome site. However, contractors narrowed the streets to one lane. That accommodates bicycle and foot traffic, but limits most vehicle access.
The newest portion of the trail now extends from the Community Center to Hamblen Road via Timberline Pass, Timberline Drive, Aqua Vista and Burning Tree Court. The last street terminates at Hamblen, just west of the old Forest Cove Golf Course.
A final leg will extend west to Precinct 3’s Edgewater Park, paralleling Hamblen Road, but south of it (light purple).
Timing and Connections
Timing for the final leg has not yet been determined. Houston Parks Board eventually hopes to connect multiple waterways and adjacent hike and bike trail systems in the northern part of Harris County.
For instance, this project will connect to the Spring Creek Greenway across the old US 59 pedestrian bridge. When complete, it will create one of the longest urban hike-and-bike trail networks in the United States.
Photos of Newest Leg of West Fork Greenway
The pictures below, taken on 1/3/23, show the state of the most recent construction.
More News to Follow When Plans Become Clear
The Parks Board plans to use some of the areas in the old townhome complex for parking. The fate of other streets remains unclear. Likewise, Harris County Precinct 3 has not yet announced plans for the long-awaited Edgewater Park. Harris County Flood Control District which bought out the townhome properties said it plans only to let the area return to green space.
Edgewater Park and this trail were one of the first good things to come out of Harvey. I just hope I live long enough to see them finished! Eventually, they will make a tremendous community asset.
Posted by Bob Rehak on 1/6/23
1956 days after Hurricane Harvey
Woodridge Village Excavation Rate Ticks Up
The excavation rate of a sixth detention pond on Harris County Flood Control District’s (HCFCD) Woodridge Village property increased during the last month of 2022. That brought the total for the year to 73,745 cubic yards of soil removed under Sprint Sand and Gravel’s Excavation and Removal (E&R) Contract.
The reported total at the end of November was 67,529 cubic yards. That means the total for December was 6,216 cubic yards, the most for any month since last July. Compare the previous totals below.
Excavation under E&R contracts varies depending on demand for fill dirt. Sprint’s contract with Harris County Flood Control District lets it take dirt basically for free and then sell the dirt on the open market to make its money.
According to HCFCD, E&R agreements provide an opportunity for making progress in advance of future basin construction. These agreements essentially provide a head start in the excavation process before the detention basin is designed and constructed. In these agreements, an excavation company agrees to remove soil from a basin site during an agreed upon time period for minimal compensation. This is a cost-effective way for the material to be removed and it also provides significant savings by minimizing trucking and disposal fees.
Pictures Taken 1/03/23
Part of a Bigger Package of Improvements
Last month, HCFCD held a virtual public meeting to describe how this would eventually contribute to flood-risk reduction on Taylor Gully.
HCFCD expects that Sprint will excavate the full 500,000 cubic yards stipulated in their contract. That will expand the current stormwater detention capacity by 166%. The property only needed 40% more to meet Atlas-14 requirements. So this will provide a considerable margin of safety.
Other improvements include:
For more details and diagrams, see this post on the preliminary engineering recommendations.
Posted by Bob Rehak on 1/5/23
1955 Days since Hurricane Harvey and 1204 since Imelda