HCFCD Report Puts May 2024 Flood in Historical Perspective

A report issued by Harris County’s Meteorologist Jeff Lindner puts the May 2024 flood into historical perspective.

Significant flooding occurred along the West and East Forks of the San Jacinto River as well as the lower San Jacinto River below Lake Houston.

While rainfall occurred over a 7-day period, the most intense rainfall in Harris County fell on Thursday, May 2nd. Lindner’s report starts by covering the rainfall totals and intensity during different lengths of time. Then, he discusses the resulting flood heights and impacts.

Rainfall distribution in May 2024 flood
Locations of 7-day rainfall totals between April 28 and May 5. Upstream areas received twice as much as Lake Houston.
Total Rainfall in 7-Day Period

Total rainfall amounts for the seven-day period averaged 10.0-17.0 inches across the extreme northern and northeastern portions of Harris County. Southern and central Montgomery County were also affected as well as northern Liberty County.

A maximum 7-day rainfall of 16.8 inches was recorded on the East Fork of the San Jacinto River at FM 1485.

The table below indicates maximum rainfall for Harris County gages.

Maximum rainfalls for different periods from 5 minutes to 7 days.

Using Atlas-14 Rainfall Exceedance Probability Tables, Lindner says rainfall during the 7-day time period ranged from:

  • 5- to 10-year events on the San Jacinto West and East Forks as well as below Lake Houston
  • 2- to 5-year events on Cedar Bayou.
  • 2- to 10-year events along Luce Bayou.

Maximum 2-Day and 3-Hour Rainfall Totals

The max rainfall for those same watersheds during the peak 48-hours ranged from 2- to 10-year events.

During the peak 3-hour time period, however, gages on Willow Creek, Spring Creek, Luce Bayou, Cedar Bayou, and the San Jacinto recorded 25- to 50-year rains. The short, high-intensity rains resulted in deep street and flash flooding.

North of Harris County, the rainfall got much more intense.

Locations of Heaviest Rainfall

The majority of the heavy to excessive rainfall occurred across areas north and northeast of Harris County. This was across the headwaters of the West and East Forks of the San Jacinto River, Luce Bayou, and Lake Creek.

Rainfall amounts over the 7-day period averaged 15.0-18.0 inches over southern Walker and northern Montgomery County which drain into Lake Conroe. They averaged 15.0-20.0 inches across eastern Walker County, northern Montgomery County, and San Jacinto County which drain into the East Fork of the San Jacinto River.

“No two storm events are exactly the same with respect to the location, duration, and maximum totals of rainfall.”

Jeff Lindner, Harris County Meteorologist

Comparisons with Other Storms

The May 2024 rainfall had some similarities to the October 1994 flood. Nearly 30 inches fell across Lake Creek and the northwest portions of the Spring Creek watersheds in 1994. In 2024, the highest totals occurred farther to the north – from north of Lake Conroe to northwest of Lake Livingston.

In those locations, the rainfall exceeded 1994. That resulted in near record inflows for both Lake Conroe and Lake Livingston.

Comparison of maximum rainfall totals in different time periods for different storms. Note especially the totals for 1-hour and less.

Flooding in Historical Perspective

Rainfall is only a starting point when investigating flooding. You must also look at rainfall distribution, intensity, longevity, previous heavy rainfall, ground saturation, already swollen watersheds, and convergence of peak flows.

Much of the upper portions of the San Jacinto basin stretch across parts of Montgomery, Walker, and San Jacinto Counties. In April, they experienced rainfall 150% to 500% above normal.

Rainfall on April 28th-29th primed already wet soils for maximum run-off. Then, those same areas received additional excessive rainfall on May 1st-2nd. The second episode generated widespread and significant flash flooding and run-off into the rivers and creeks that drain to Lake Houston.

Second Highest Peak on East Fork

The East Fork exceeded the expected elevation of a 500-year storm. At FM1485, only Harvey exceeded the May peak.

San Jacinto East Fork peaks at FM1485.

Five-hundred year flooding on a 20-year rain resulted when peaks from different rounds of rainfall piled on top of each other from different watersheds.

Fifth Highest Peak on West Fork

West Fork flooding was less extreme. This was the fifth highest flooding on the West Fork since 1994. The May flood qualified as a 10- to 50-year storm based on gage readings at US59.

Five highest peaks on San Jacinto West Fork since 1994.

Fourth Highest Peak at Lake Houston Dam

The height of water going over the spillway at the Lake Houston Dam was the 4th highest peak since 1979.

Downstream at Highway 90, residents saw the 9th highest peak since 1979. Downstream areas saw between a 10-year and 50-year flood.

Third Highest Volume of Stormwater Flowing Into Lake Houston

The table below summarizes volumes of water in cubic feet per second flowing into Lake Houston from the various watersheds during different storms. This May’s event was the 3rd highest total since 1994. Only Harvey and October 1994 surpassed it.

Water flowing into Lake Houston in different storms since 1994. This May was 3rd largest volume.

House Flooding Estimates

Flood depths ranged from 6 inches to several feet in some of the lowest lying homes. The damage numbers below apply only to Harris County. The numbers were supplied by City of Houston and Harris County Engineering.

  • 20 homes flooded with an additional 16 having water in sheds, garages, or other non-living areas on the West Fork.
  • 32 homes flooded with an additional 8 having water water in non-living areas on the East Fork.

Upstream, the flood damage in Montgomery and Liberty Counties was much greater. However, I do not have final totals for those areas yet.

Maps, Tables Galore

Lindner’s report also includes 15 pages of rainfall intensity maps and tables for different watersheds and gages. It’s a treasure trove of information including high water marks. Click here for the full report. For future reference, that’s under the link to the Major Storms tab on the Reports Page. You can compare full reports on other storms there.

Many thanks to Jeff Lindner and his team. They keep hundreds of gages around Harris Country watersheds working to provide timely, life-saving information via the Harris County Flood Warning System.

Posted by Bob Rehak on 5/15/24

2451 Days since Hurricane Harvey

Most Projects To Address Lake Houston Flooding Still Not Started

After the floods of early May 2024 and as we got yet another flood warning (East Fork at FM1485), people are asking once again, “What can we do to reduce our flood risk?” Ironically, with a few exceptions, the answers are the same as those identified after Harvey. We just need to implement them. 

Few of the action items identified years ago have been implemented. Meanwhile, many underlying conditions that contribute to flood risk, i.e., insufficiently mitigated upstream development and sand mining, are accelerating. Sometimes it feels that as fast as we fix things up, others muck them up.

Could have Been Much, Much Worse

The Lake Houston Area narrowly escaped a disaster during the early May floods. A small number of homes flooded. However, a far larger number were almost seriously damaged. Had storms dumped a little more water in the wrong places, that flood could have easily destroyed thousands of homes. Water was lapping at their foundations.

Ironically, the amount of water that caused the flooding this May was about a third of what we received during Harvey. 

That should underscore how vulnerable people in the Lake Houston Area remain to flooding. So, let’s look back at what happened to recommendations that came out of Hurricane Harvey studies.

Recommendations from 2020 San Jacinto River Watershed Master Drainage Plan

After Harvey, Harris County Flood Control, Montgomery County, the San Jacinto River Authority and the City of Houston joined forces to identify ways to reduce flood risk in the San Jacinto River Basin.

In December 2020, they published a 3,600 page study called the San Jacinto Regional Watershed Master Drainage Plan.

Pages 36-38 of the executive summary contain recommendations. Page 38 identifies and quantifies the value of 16 recommended flood-mitigation projects.

Short-Term Strategies (Page 36)
  • Vision Group – to promote collaboration and momentum
  • Policy – standardizing minimum requirements for future development
  • Floodplain Preservation – to prevent increases in future flood risk
  • Flood Monitoring and Warning Enhancements – adding gages along major streams
  • Flood Response – enhancing communication, identifying and prioritizing flood prone areas, and developing public education strategies
  • Buyouts – to remove homes and businesses that flood frequently from the floodplain
  • Floodplain Re-Mapping – to inform people of changes to their risk. Water surface elevations in a 100-year flood have increased between .5 and 4.5 feet with the adoption of Atlas 14. 
  • Watershed Protection Studies – for each sub watershed to identify where we need local drainage improvements.
Long-Term Strategies (Page 37)
  • Adoption of “No adverse impact” Policy – to ensure upstream mitigation efforts don’t increase downstream flooding
  • Right of Way Acquisition – purchasing land for future flood mitigation projects
  • Utilities and Roadways – protecting evacuation routes and critical infrastructure during planning
  • Project Phasing to Overcome Funding Constraints – due to the high cost of mitigation projects.
16 Specific Channel and Stormwater-Detention Projects (Page 38)

See project rankings in table below along with projected costs.

Top 16 Projects Identified in SJR Master Watershed Plan

Subsequent portions of the report describe each recommendation in each category in more detail. You can find all sections on the HCFCD website. They total hundreds of megabytes.

Not Much Has Happened in Last Four Years

Sadly, while elected officials have been busy chasing funding, not much has been accomplished on the ground in any of these three categories that would actually reduce flood risk. Said another way, we’ve seen little construction. We’ve seen most progress in the first category.

Short-Term Solutions:

Vision Group: The San Jacinto Regional Flood Planning Group was recommended to pull together recommendations for the State’s first flood plan. A draft was released last week. 

Policy: Montgomery County is revising its drainage criteria manual. But county commissioners have not yet adopted it. Neither MoCo, nor Liberty County have adopted the minimum drainage standards for areas draining into Harris County.

Floodplain Preservation is spotty. Non-profits, such as the Bayou Land Conservancy have stepped up. And some governmental agencies have discouraged floodplain development. But loopholes exist in regulations and enforcement is lacking in many places even if regulations exist.

Flood Monitoring and Warning Enhancements – SJRA installed several gages upstream from Lake Conroe, but more are still needed. In the last flood, they still couldn’t tell exactly how much water was coming in so that they could match releases to stabilize the lake level.

Flood Response: Harris County Flood Control stepped up its warnings and provided updated river forecasts two to three times a day. The SJRA did too. The Mayor had multiple press conferences in the Kingwood area before and during the flood. He worked with first responders to make sure people were kept out of harms way. That was a far cry from Harvey where a quarter of all the deaths in the county happened in Kingwood. And elderly people found themselves trapped by rising floodwaters in the middle of the night.

Buyouts – HCFCD bought out the townhomes along Marina Drive in Forest Cove that flooded repeatedly. And Montgomery County has also bought up many properties that flooded repetitively. But many more remain. 

Floodplain Re-Mapping – FEMA has yet to approve Harris County’s updated flood maps. They’re still approximately three years from completion.

Watershed Protection Studies – Some have been done. Other’s haven’t even started. It’s been spotty. Little has been done with the studies already completed. And no grants will be approved without studiers.

Long-Term Solutions:

“No adverse impact” is violated more than the Ten Commandments.

Right of Way Acquisition – has moved forward on several properties in the Cypress Creek watershed and Harris County bought the 270-acre Woodridge Village Property in Montgomery County from Perry Homes.

Roadways – Lake Houston Redevelopment Authority/TIRZ 10 is expanding Northpark Drive and building an all-weather evacuation route out of Kingwood. It includes a bridge over the UP Railroad Tracks. FM2100 and FM1960 are expanding in Harris County. But the Huffman-Cleveland Road is still cut off in Liberty County. The Grand Parkway has been completed. But FM1485 right next to it has been cut off by floodwaters twice already this year.

Project Phasing – is a standard practice in the industry. But projects associated with the flood bond are moving so slowly that inflation has cost us about 20% of the bond’s purchasing power. Where will the money come from to complete all the projects?

Specific Projects

Not one of these projects listed in the table above has started construction. None is even close. No land has been acquired for any. And yet, unlike studies, these things actually protect property when floodwaters rise.

Engineers looked into Project #2 (Walnut Creek Detention), but by the time they investigated, someone had already purchased the land and announced plans to build a solar farm on it. 

Where to Go From Here

Net: We’ve picked some of the low-hanging fruit. But we have a long way to go. Especially with construction projects that actually protect property.

As I interviewed people for this post, it became clear that different entities with different interests has hampered many mitigation efforts. We walk between competing, balkanized fiefdoms. 

No one anywhere speaks for all the people of this watershed.

Just as bad, the business processes surrounding flood mitigation sometimes become bewilderingly complex. Many smaller counties, cities and MUDs don’t have the expertise to even apply for grants.

Even worse, some groups undermine improvements. For instance, we’ve dredged the mouth of the Kingwood Diversion Ditch at River Grove Park twice since Hurricane Harvey. And now it needs it again – as the West Fork flows through a sand pit. Even before floodwaters have receded, you can already see sediment poking up through the water. For decades the dredging interval was about once every eight years.

The people of a river basin are inextricably bound together by water. Yet our personal interests (What’s in it for me?) and political boundaries still divide us. 

We need to recognize that fact and develop better ways to design solutions. More on that in a future post. I’ll also discuss some things that the San Jacinto River Basin Plan did not address.

Posted by Bob Rehak on 5/14/24

2450 Days since Hurricane Harvey

Video of Mile-Long Sand Pit Leaking Into West Fork

Correction: This sand pit in this post was sold by Hallett to Riverwalk Porter LLC on January 23, 2024.

Last week, the West Fork San Jacinto rerouted itself through a mile-long sand pit at the five-square mile Hallett Mine in Porter. Some people reported problems understanding how all the images in that post related to each other and where the mine was. To help eliminate confusion, I returned to the site this morning show continuous video from one breach to the other. I’ve also included a wider map below.

Location of Mine and Path of Video

The map below shows the relationship of the pit “captured” by the river to the rest of the mine, Porter and Kingwood.

Arrow indicates location and direction of drone video.

Video and Still Shots of Captured Pit

Clouds were low and I was flying near the base of them. So, the video looks a bit hazy.

One-minute video shot morning of 5/3/24 while flying from south to north. First breach is exit from pit, second is entrance. Water flows toward the camera through the pit to the left of the channel.

Note several things as you watch the video.

  • Size of the entry and exit breaches. They’re impossible to measure precisely, but likely greater than 100 feet wide.
  • Depth of the pond that used to be filled with wastewater before the dikes broke. See exposed sides where vegetation did not grow.
  • Sand being washed downstream before the water receded.
  • Dune blocking the West Fork in the upper right near the end of the video.

Here are some still shots with more contrast that show those highlights and other aspects. I’ll arrange these in the reverse order, i.e., flying downriver in the opposite direction starting from the entrance breach..

Giant dune has totally blocked off West Fork and diverted it into pit (upper left). Local residents say dune is 5-8 ft. high. People on either side of it cannot see each other.

Water now takes the path of least resistance, flowing through the giant pond.

Note freshly deposited sand in pit. The island (right center) is reportedly a burial ground for Native Americans.
Note color difference in water and how pond water now flows downstream. Also note height of pond walls.

Have a cool, refreshing glass of Hallett.

This flows straight into Lake Houston.

Downstream Photos Taken on 5/13/23 at US59 Bridge

Looking S across West Fork toward Humble. Note ripples in fresh layers of sand under US59 Bridge.

The City of Houston is launching a new $34 million dredging program to remove another 800,000 cubic yards of sediment accumulating in the West Fork downstream from the bridge.

Hallett contends that sand cannot escape its pits and that this sand comes from river bank erosion on other tributaries such as Spring and Cypress Creeks.

Robin Sedewitz, Kingwood resident contributed the three photos and video below.

Note height of debris in bridge supports.

Trees swept downstream in the May flood are forming a dam on the south side of the old bridge.
Trees caught under the southbound lanes of US59.
30-second video by Robin Sedewitz panning from upstream to down showing accumulations of debris in bridge supports.

During Harvey, debris such as this got caught in supports for the old railroad bridge and dammed the river, backing water up into Humble and Kingwood businesses. The railroad ultimately built a new bridge that would let trees pass through. No trees got hung up on the new bridge supports during this flood.

Where to Report Problems

Harris County Flood Control now surveys the river after floods and removes debris. They just haven’t gotten to this debris yet.

If you see problems that need HCFCD’s attention, you can report them here.

The TCEQ regulates sand mines in the State of Texas. To report sand mine issues, visit: https://www.tceq.texas.gov/compliance/complaints/.

Posted by Bob Rehak on 5.13.24

2449 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.