Northpark Contractors Pouring Concrete Again
1/14/2026 – After the holidays, Northpark contractors placed rebar in many gaps along Northpark where concrete had not yet been poured. And today the concrete trucks were out in force, filling those gaps.
Contractors were also hard at work on drainage connections under Loop 494. Once those connections are completed, the last remaining segments of concrete can be poured and 494 will be complete.
That will leave the bridge over 494 and the Union Pacific railroad tracks to build. But before that can happen, UPRR needs to move the signals to the new crossings. See more below.
Concrete Pours
I took all pictures below on 1/14/26 at around 11 AM. Most of the new concrete being poured this morning was between Sherwin Williams and Dairy Queen.





Drainage Connections at Loop 494
At Loop 494, contractors were working on both the northwest and southeast corners to complete drainage and sanitary connections.

The current construction schedule posted on the TIRZ website, shows that contractors will demolish the existing east bound lanes (center-right above) on Friday and Saturday nights, 1/23 and 1/24.

Re-Alignment of Railroad Crossing Signals
Before contractors build new surface lanes across the tracks and build the bridge, UPRR must move and rewire its traffic signals which currently close across the old lanes (right above).

Ralph DeLeon, TIRZ project manager says that he hopes UPRR will be able to get to the cross-signal issue in early February.
Until the TIRZ resolves that issue and pushes the new surface lanes across the track, it cannot build the bridge. There would be no way for traffic to get across the tracks.
Remaining Gaps
In the meantime, Northpark contractors will have to focus on filling in the remaining gaps.

Once the drainage on both sides of Loop 494 is connected, contractors must clean out the ditch that runs from Public Storage behind the businesses north of Northpark down to Bens Branch. Then the drainage will be fully operational from east to west.
But contractors must also to finish excavating the lakes on either side of the entry above.

Note at the bottom of the picture above, the full 12 lanes that Northpark will become in this area compared to the current four.



For More Information
When complete, this will be the first all-weather evacuation route from Kingwood for 78,000 people.
For additional forward-looking information, consult the Lake Houston Redevelopment Authority website, including their 3-week look-ahead schedule.
For a history of the project to date, search on “Northpark” in the upper right corner of ReduceFlooding.com. Since 2018, I have posted more than 200 stories about this project.
Posted by Bob Rehak on 1/14/2026
3060 Days since Hurricane Harvey











