Despite Heavy Rains, KMS Reconstruction Progressing Nicely
Since my last update, Kingwood Middle School (KMS) reconstruction has progressed nicely despite heavy rains and a tropical storm in the last month. My rain gage, a few blocks away recorded more than 11 inches of rain in the last 30 days – almost triple the average for September.
My last update on August 20 showed that contractors had erected most of the structural steel, but large parts of superstructure were still open. Today, almost the entire roof is on and most of the structure has been walled or glassed in.
It was barely 10 months ago, that this site was nothing but dirt, a dream, and a detention pond.
Photos Showing Status of KMS Reconstruction as of 10/3/21
Here are pictures of KMS reconstruction taken this afternoon with a drone.


Plans call for reconstructing the athletic fields on the site of the old school and building a permanent, larger detention pond where the circular drive in the foreground is.




Humble ISD still expects the school to open for the 2022 school year. For more information about the plans for the building, see the District’s web site. Find updates on other new construction from the 2018 bond here.
Posted by Bob Rehak on 10/3/2021
1496 Days since Hurricane Harvey