Kingwood Middle School: November Construction Update
Construction of the new Kingwood Middle School appears on schedule for opening with the next school year in 2022. Compared to my October update, no new major milestones have been reached. Everything just looks a little further along.
Kingwood Middle School Construction Sequencing
Construction started on the west and is moving toward the east. As subcontractors finish one phase such as foundations or structural , the next group picks up the baton and works on roofing, exterior walls, windows, etc.
The most visible change between October and November: progress on exterior walls and roofing.
I took all the pictures below on Saturday, November 6, 2021.
Next Steps for KMS
Next steps will be to dry-in the structure by completing the exterior walls, windows and roofs. The other trades will then start working on interior walls, electrical, wallboard, paint and flooring – all the things that could be destroyed by blowing rain.
I put two kids through the old Kingwood Middle School who became happy, healthy, successful adults. As I look at these pictures, fond memories of plays, recitals, teacher conferences, and athletic contests come to mind. Each month, as the old school comes closer to demolition, I become increasing nostalgic. We will soon witness the end of one era and the start of another in Kingwood.
Architectural renderings on the Humble ISD site inspire confidence that the next generation of Kingwood Middle School students will have an even better learning environment than the last.
And cross your fingers! Despite double the impervious cover now on the site, I have received no reports of flooding from neighbors.
Posted by Bob Rehak on 11/11/2021