8/5/2026 – In 2020 – three years after Hurricane Harvey – the San Jacinto River Authority (SJRA) applied for $500,000 grant from the Texas Water Development Board (TWDB) to study Joint Reservoir Operations between Lake Conroe and Lake Houston. They hoped they could reduce flooding through better coordination of releases from the two dams.
March 2026 Public Input Session in Humble
Earlier this year, SJRA held a public input session at the Humble Civic Center where it outlined the goals of the study and listened to dozens of downstream residents still harboring PTSD from flooding and angry about delays.
At the event, SJRA said it would present its conclusions this FALL in The Woodlands. Now, five months later, the schedule has slipped to Spring 2027. See the screen capture below from SJRA’s website.
Matt Barrett, PE, SJRA’s Water Resources and Flood Management Division Manager, offered this explanation for the delay in an email.
Barrett said, “We are budgeting more time for reviews due to the number of partners involved. A couple other items that impacted the schedule and may delay the report are the modeling for the pre-release analysis, as well as required coordination with the ongoing Lake Houston Gates Project. We also expect a fair amount of stakeholder engagement.”
At the July SJRA Board Meeting, General Manager Aubrey Spear said that the Joint Operations study could not be done before the gate design was completed. Spear said he would have more information at the October SJRA Board Meeting. Mr. Sprear’s comments about the study begin at about 14:30 into this video and last for about 3 minutes.
Mr. Spear addressing SJRA Board Members at their 7/23/26 meeting.
Houston City Council Member Fred Flickinger said today that the part of the Gates project that the SJRA needs to finish its work should be ready in 4-6 weeks.
Before Mr. Spear concluded his remarks at the SJRA Board Meeting, he spent another minute addressing the status of SJRA’s long-delayed sand-trap study, which has been sitting on the shelf for more than four years.
No SJRA Study Results Implemented Yet
SJRA has conducted a number of studies since Hurricane Harvey. They include a:
Study for building regional detention basins on Birch and Walnut Creeks, (far upstream on Spring Creek).
Yet nine years after Harvey, to my knowledge…
No drainage recommendations from any of these studies have ever been constructed.
The 661-page Birch and Walnut Creek study took so long that recommendations could not be implemented. By the time it was finished, the land had been sold to developers. A large solar farm was already built on one of the parcels needed when the SJRA Board reviewed the results and decided to take no action.
I hope the same does not happen with the Joint Ops study. Downstream residents desperately need something actionable this time from the SJRA.
One expert familiar with the issues involved told me, “Frankly, there’s no reason this study could not have moved forward long ago. It’s about procedures and operations. If the design of the gates changes, just update the procedure manual.”
Plea for Downstream Involvement
At every SJRA Board meeting, one or more residents from Lake Conroe speak during the public comments to oppose any pre-release. Downstream residents rarely if ever appear. So, the “no pre-release” mantra goes unchallenged. The SJRA Board needs to hear opposing points of view if downstream residents ever hope to see recommendations from the Joint Ops study implemented.
Posted by Bob Rehak on 8/5/2026
3263 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/08/SJRA-Board-Meeting.png?fit=1646%2C914&ssl=19141646adminadmin2026-08-05 17:02:142026-08-06 08:54:08SJRA Announces More Delays on Joint Reservoir Operations Study
7/2/26 – Political fragmentation can increase flood risk many ways. It is one of the least appreciated, but most significant factors in flooding – particularly in rapidly urbanizing watersheds like the San Jacinto River Basin.
Floodwater doesn’t respect jurisdictional boundaries. When many different jurisdictions make drainage decisions independently, it rarely, if ever, optimizes results. Here are 10 reasons why.
1. Upstream Communities Often Don’t Bear Downstream Costs They Create
A city or county may approve new development because it receives the tax revenue while the flood impacts occur miles away. For example:
Community A approves thousands of acres of development.
Runoff increases.
The additional water flows into Community B.
Community B pays for larger channels, detention basins, buyouts, and disaster recovery.
Thousands of individually compliant projects can collectively overwhelm streams.
This is sometimes called the “Death by a Thousand Cuts” problem.
4. Transportation Agencies Optimize Roads – Not Watersheds
Road departments may prioritize:
Minimizing bridge costs
Minimizing culvert costs
Reducing construction expenses.
Flood managers may want:
Larger openings under bridges
Fewer hydraulic bottlenecks
Preservation of natural floodways.
If transportation and flood agencies are not coordinated, roads can become unintended dams during major floods.
FM2090 at East Fork on May 1, 2024. The opening for the bridge is in the trees on the upper right.
5. Reservoir Operators May Have Different Missions
Sub-watersheds often include reservoirs managed by different organizations and/or for different purposes. For instance, one reservoir may prioritize water supply while another prioritizes flood control or recreation.
Without coordinated operating plans, releases can unintentionally compound downstream flooding. This has been discussed extensively regarding operations of Lake Conroe and Lake Houston, where coordinated releases can substantially influence downstream flood peaks.
The 400,000 CFS going over the Lake Houston Dam during Harvey included 80,000 CFS from Lake Conroe. It created a wall of water 11 feet high. The volume was five times more than the amount of water going over Niagra Falls on an average day.
6. Funding Responsibilities are Fragmented
One agency may pay for channel improvements, while others pay for maintenance, detention, environmental mitigation, and/or emergency response.
Projects that benefit everyone may stall because no single organization is responsible for paying for them. Coordination among agencies with different staffing, funding, and priorities can delay projects years. Economists call this a “collective action problem.”
For instance, according to Harris County Flood Control District (HCFCD), only half of the Taylor Gully/Woodridge project has started because the Texas Water Development Board has reportedly not yet approved the Taylor Gully portion.
Meanwhile, a critical HUD funding deadline is fast approaching that may cost Harris County hundreds of millions of dollars. It’s an HCFCD project. But City of Houston bridges are involved.
School bus trying to go over Taylor Gully on the Rustling Elms bridge on May 7, 2019.
Aligning all these dominos takes years, especially when they involve grants from multiple agencies.
7. Floodplain Mapping Evolves at Different Speeds
One jurisdiction may adopt updated flood maps quickly while a neighboring jurisdiction may continue using older maps.
This means development can continue under outdated assumptions upstream while downstream communities build to newer, more conservative standards.
Again, the Taylor Gully/Woodridge project provides an excellent example. HCFCD contractors are now excavating dirt for a Woodridge Detention Basin. Some of that dirt is being hauled to a new development along Dry Creek at FM1485 in Montgomery County.
Technically, the dirt is being deposited outside the 100-year floodplain at that location, per HCFCD standards. But the Montgomery County floodplain map is still based on pre-Harvey (2014) data.
Where Woodridge dirt is going. Map last updated in 2014 before Harvey.From FEMA Flood Hazard Layer Viewer.Placement area for a portion of dirt excavated from Woodridge, shown in red circle abovenear Dry Creek.
Are we paying to solve a flood problem…or to relocate it?
8. Data are Often Not Shared
As we saw above, jurisdictions frequently use different:
Hydraulic models
Rainfall assumptions
LiDAR vintages
Land-use projections
Software platforms
When models don’t align across jurisdictional boundaries, flood analyses can become inconsistent.
9. Maintenance Responsibilities are Divided
Who:
Removes sediment?
Clears fallen trees?
Maintains detention ponds?
Repairs eroded channels?
If responsibility changes repeatedly across political boundaries, maintenance gaps develop that reduce channel capacity.
10. Emergency Response Becomes Harder
During large floods:
Counties
Cities
Drainage districts
River authorities
State agencies
Federal agencies
…must all coordinate their activities.
If communication is poor, evacuations, road closures, reservoir operations, and recovery efforts become less efficient.
The Cumulative Effect
Political fragmentation doesn’t usually create flooding by itself. Instead, it gradually amplifies flood risk by allowing many small decisions to accumulate or be deferred.
Fragmented decision
Watershed consequence
Different detention rules
More runoff
Different floodplain rules
More development in hazardous areas
Independent land-use decisions
Higher peak flows
Separate infrastructure planning
Hydraulic bottlenecks
Different maintenance standards
Reduced conveyance
Independent reservoir operations
Poorer timing of releases
Separate funding
Delayed mitigation projects
Each individual decision may appear reasonable within one jurisdiction. Collectively, they can increase both the frequency and severity of flooding across the river basin.
Why This Matters in the San Jacinto River Basin
The San Jacinto River watershed illustrates many of these challenges. It spans multiple counties and municipalities with varying drainage standards, development regulations, and infrastructure priorities.
Rapid upstream growth can alter runoff patterns that affect downstream communities, such as the Lake Houston Area. Indeed, it affects all of Houston and Harris County.
At the same time, reservoir operations, floodplain management, and mitigation investments are divided among numerous local, regional, state, and federal entities. Coordinating those decisions across jurisdictional boundaries is often as challenging as the engineering itself.
Many watershed professionals therefore advocate managing flood risk at the “watershed scale” rather than at the city or county scale.
That approach emphasizes common hydrologic assumptions, coordinated land-use planning, cumulative-impact analysis, shared data and models, aligned reservoir operations (where feasible), and funding mechanisms that reflect both where runoff is generated and where flood damages occur.
It does not eliminate flooding, but it can substantially reduce the extent to which fragmented governance makes floods worse.
Posted by Bob Rehak on 7/3/2026 with the help of ChatGPT for research.
3230 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2026/07/Dry-Creek-FM1485-Flood-Map-copy.jpg?fit=1100%2C710&ssl=17101100adminadmin2026-07-03 13:33:102026-07-05 22:12:3610 Ways Political Fragmentation Can Increase Flood Risk
8/4/2025 – The San Jacinto River Authority (SJRA) has unveiled a ten-year flood-mitigation plan for the river basin. For the most part, it’s built around continuations of previous efforts. Regardless, it’s interesting to see what SJRA hopes to focus on in the future.
The plan contains eight main elements:
Spring Creek Watershed Flood-Control Dams Feasibility Study
Upper San Jacinto River Basin Sedimentation Study
Lake Conroe/Lake Houston Joint Reservoir Operations Study
San Jacinto River and Tributaries Sediment Removal and Sand Trap Development
Previously, the SJRA identified two potential sites for flood-control dams in the upper Spring Creek watershed. The sites included properties along Birch and Walnut Creeks. One of the sites subsequently was sold for a solar farm. However, SJRA believes it only needs a small portion of that property. It has budgeted money to buy that property and relocate some of the solar panels.
Matt Barrett, SJRA Flood Management Division Manager said, “We believe it is still a feasible site if we can identify a project sponsor to own and maintain the dam/reservoir.”
Currently, SJRA is seeking partners who could help fund land acquisition, construction and maintenance.
As with many of these items, SJRA emphasizes that it only has money for planning, coordination and project leadership, but not actual execution. For that, it must rely on grants.
Upper Basin Sedimentation Study
SJRA started this project several years ago also. The presentation shows them wrapping up their sedimentation study next year. They intend to rank order and develop an implementation plan for all projects that they have identified to date.
When last I checked, the City planned to adjust the number of gates to fit available funding. Once the release capacity has been locked down, engineers can develop:
An inflow forecasting tool for Lake Houston
Gate operations policies
Feasibility of pre-releases at either or both reservoirs
Risk evaluations in different weather scenarios.
SJRA hopes to complete this project by 2028.
Sediment Removal and Sand Trap Development
This project started in 2020 and identified a test site near the Hallett mine on the San Jacinto West Fork. SJRA wanted the site to be near a mine so miners could remove accumulated sediment from the sand trap once it filled up.
However, after the site was identified, the recommended site was subsequently cut off by a “pit capture.” The river is now flowing through the Hallett pit rather than around it.
The question in my mind is whether the pit walls can be hardened or vegetated somehow to let the exposed pit function as the sand trap.
SJRA hopes to work with a consultant to simplify the design and reduce costs for all involved. They see project completion in 2028.
Waller County Flood Mapping
SJRA hopes to obtain a grant from the Texas Flood Infrastructure Fund to update Waller County’s flood maps to Atlas 14 standards. This project could go through 2029 and cost $7 million.
Upper-Basin Dual-Purpose Reservoir
This is one of the most exciting elements of the 10-year plan. This feasibility study would determine the most viable location for a new lake/reservoir in the upper river basin that could mitigate flooding and supply water.
The study will look at a number of constraints and work with stakeholders, such as the US Forest Service.
Depending on the feasibility of the ultimate recommendation, it could replace a number of preliminary recommendations from the River Basin Master Drainage Plan developed several years ago. The study would go through 2029.
A new dual-purpose reservoir could be sited north of Lake Conroe or in the East Fork Watershed.
Rain/Stream Gage Installation
SJRA, working with counties, precincts, and other local governments, has identified 48 locations for rain/stream gages across the upper river basin. SJRA has incorporated all of them in the Regional Flood Plan.
As funding becomes available, they would be constructed. SJRA projects this project could last through 2032.
Miscellaneous
In the latter phases of the 10-year plan, SJRA is reserving some money for miscellaneous projects that arise through 2035. They might be small scale follow-up studies or facilitation of major construction projects – when/if they come to pass.