SJRA Announces More Delays on Joint Reservoir Operations Study
8/5/2026 – In 2020 – three years after Hurricane Harvey – the San Jacinto River Authority (SJRA) applied for $500,000 grant from the Texas Water Development Board (TWDB) to study Joint Reservoir Operations between Lake Conroe and Lake Houston. They hoped they could reduce flooding through better coordination of releases from the two dams.
March 2026 Public Input Session in Humble
Earlier this year, SJRA held a public input session at the Humble Civic Center where it outlined the goals of the study and listened to dozens of downstream residents still harboring PTSD from flooding and angry about delays.
At the event, SJRA said it would present its conclusions this FALL in The Woodlands. Now, five months later, the schedule has slipped to Spring 2027. See the screen capture below from SJRA’s website.

Proffered Reasons for Delays
Matt Barrett, PE, SJRA’s Water Resources and Flood Management Division Manager, offered this explanation for the delay in an email.
Barrett said, “We are budgeting more time for reviews due to the number of partners involved. A couple other items that impacted the schedule and may delay the report are the modeling for the pre-release analysis, as well as required coordination with the ongoing Lake Houston Gates Project. We also expect a fair amount of stakeholder engagement.”
At the July SJRA Board Meeting, General Manager Aubrey Spear said that the Joint Operations study could not be done before the gate design was completed. Spear said he would have more information at the October SJRA Board Meeting. Mr. Sprear’s comments about the study begin at about 14:30 into this video and last for about 3 minutes.

Houston City Council Member Fred Flickinger said today that the part of the Gates project that the SJRA needs to finish its work should be ready in 4-6 weeks.
Before Mr. Spear concluded his remarks at the SJRA Board Meeting, he spent another minute addressing the status of SJRA’s long-delayed sand-trap study, which has been sitting on the shelf for more than four years.
No SJRA Study Results Implemented Yet
SJRA has conducted a number of studies since Hurricane Harvey. They include a:
- Sand trap study
- Sedimentation study
- River-Basin Master Drainage study
- Study for building regional detention basins on Birch and Walnut Creeks, (far upstream on Spring Creek).
Yet nine years after Harvey, to my knowledge…
No drainage recommendations from any of these studies have ever been constructed.
The 661-page Birch and Walnut Creek study took so long that recommendations could not be implemented. By the time it was finished, the land had been sold to developers. A large solar farm was already built on one of the parcels needed when the SJRA Board reviewed the results and decided to take no action.
I hope the same does not happen with the Joint Ops study. Downstream residents desperately need something actionable this time from the SJRA.
One expert familiar with the issues involved told me, “Frankly, there’s no reason this study could not have moved forward long ago. It’s about procedures and operations. If the design of the gates changes, just update the procedure manual.”
Plea for Downstream Involvement
At every SJRA Board meeting, one or more residents from Lake Conroe speak during the public comments to oppose any pre-release. Downstream residents rarely if ever appear. So, that mantra goes unchallenged. The SJRA Board needs to hear opposing points of view if we ever hope to see recommendations from the Joint Ops study implemented.
Posted by Bob Rehak on 8/5/2026
3263 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.