Perry Homes’ Contractors Return to Woodridge Village, But Undo Some Previous Work, Add to Sediment-Laden Runoff

After pulling all construction equipment from the Woodridge Village site in December, Perry Homes’ contractors returned this week. They are still working on the S2 (second southern) detention pond. But the new work appears to undo some previous work, and make sediment-laden runoff worse.

Woodridge Still Far Short of Promised Detention Capacity

After about 15 months of working on the Woodridge Village site, Perry Homes still has only 23% of the detention capacity installed. And even that does not yet meet Montgomery County regulations (see below). None of the work this week focused on new detention ponds that would reduce flood risk for Elm Grove residents.

Perry Homes had promised to build three ponds on the northern section. But they have not started any of those yet.

And Far Behind Schedule

On October 17th last year, an attorney for Perry Homes, J. Carey Gray, promised the Houston City attorney that Perry would have S2 completed in no more than 45 days. It has now been 86 days since Mr. Gray sent his letter and the work is still far from complete. I’m sure this creates an embarrassment to the Mayor of Houston, especially considering that Perry Homes gave $5000 to his re-election campaign. It creates the appearance of trying to buy favors.

Still Does Not Comply With MoCo Regulations

I previously detailed seven Montgomery County regulations that Perry Homes’ detention ponds did not meet. Perry Homes did not:

  • Put 30-foot wide maintenance roads around the ponds.
  • Place backslope interceptor swales around the ponds.
  • Have effective erosion control measures in place.
  • Implement protective measures for their overflow spillway.
  • Prevent increases in downstream flood levels.
  • Prepare a geotechnical report (that they shared with Montgomery County) showing groundwater levels at detention pond sites.
  • Ensure complete drainage of the detention pond.

Detention Pond Falls Short of Promised Capacity

Calculations for the capacity of the detention ponds begin from the bottom of the pond – when empty. When partially filled with water, the calculation begins from the top of the water. The bottom 2-3 feet of S2 has retained water for months, indicating that part of the pond is below the water table. So you can subtract about 20% of capacity that LJA Engineering promised and that Rebel Contractors initially built.

Adding Maintenance Road, Subtracting Backslope Swales

The flurry of work this week centered around creating the maintenance road that regulations demand. Or perhaps Perry is just building up the lip of S2 to compensate for the water it holds. Both are potentially good things.

However, workers also started filling the backslope interceptor swales they previously built. This created a sharp slope next to neighboring residents’ property and increased runoff toward the residents during last night’s rain.

Contractors placing dirt along the southern edge of the S1 pond to build a road earlier in the week.
Elm Grove Trail on left. Woodridge Village on right of silt fence. Note how land is being sloped toward Elm Grove.

An interceptor swale collects water above slopes and diverts it to the bottom of a detention pond through pipes so runoff does not create erosion on the slopes that lead to the pond.

Perry Homes has given no reason why they started filling in the swale they previously built that complied with MoCo regulations.

Looking west from Village Springs Drive. In the foreground, you can see how workers built a road and filled in the interceptor swale between it and Elm Grove on the left.
Still looking west. From this drain pipe, you can better see the grassy swale previously created to drain water into the detention pond (right) and to keep it out of Elm Grove (left).
Reverse shot, looking east. Here you can see how workers filled in the swale and created a road three to four feet high. Residents worry about the effect.
Looking east near the entrance to Taylor Gully from the road, the change in drainage toward Elm Grove (right) becomes very apparent. Picture taken Friday afternoon before rain. Road was uncompacted except for the weight of the small bulldozer spreading dirt (see first picture above).

Same Changes Between S1 and Sherwood Trails

The same changes appear along the southern edge of S1, north of Sherwood Trails, though the road does not appear as high and there also appears to be a shallow swale.

Looking west along the southern edge of Woodridge Village S1 detention pond, toward Woodland Hills from Fair Grove.

No Effective Erosion Control Yet

Perry Homes has also failed to put effective erosion control measures in place in Woodridge Village. For instance, most pond banks do not yet have grass planted on them.

The new road covered up what little grass had grown around the ponds. And raw dirt now fills the former interceptor swale.

A one-inch rain last night swept sediment into the pond, which emptied into Taylor Gully and Caney Creek before joining the East Fork of the San Jacinto.

Massive Pollution

Boater Josh Alberson took the dramatic picture below this afternoon where Caney Creek joins the East Fork. The East Fork water looks natural, but the water coming from Caney Creek via Taylor Gully is clouded with sediment. Woodridge Village is the only large source of exposed earth up Taylor Gully at this time. (Alberson verified that this sediment-laden runoff was NOT coming from the Triple PG mine up White Oak Creek.)

Water from Taylor Gully (right) merging with East Fork water (left) on Saturday afternoon, 1/11/2020, after a 1-inch rain last night.

Posted by Bob Rehak with images from Josh Alberson, Edythe Cogdill and Nancy Vera

865 Days since Hurricane Harvey and 114 since Imelda

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

MoCo Commissioners to Consider Resolution Opposing Lowering of Lake Conroe; Interferes with Recreation

Tuesday, January 14, Montgomery County Commissioners will consider a resolution to OPPOSE the continued seasonal lowering of Lake Conroe. The lowering provides a buffer against flooding for people on Lake Conroe, Lake Houston and communities between them during the rainiest period in the spring and the peak of hurricane season. It was designed primarily to help flood victims downstream of Lake Conroe until flood mitigation measures could be put in place.

But the lowering also represents an inconvenience for boaters on Lake Conroe. Further, they claim it potentially harms their home values. See the text of Precinct One Commissioner Mike Meador’s resolution below.

“Interferes with the Recreational Use of the Lake”

Text of Resolution to be considered by MoCo Commissioners on Tuesday, January 14.

What Interference is Really Like

Lake Conroe homeowners who claim their property values have been damaged by lowering the lake a foot or two should see what flood damage is really like.

A little fixer upper on the West Fork in Forest Cove. What an extra 80,000 cubic feet per second going through your living room will do.
Kingwood Village Estates, a senior complex, had to be evacuated. Twelve people later died – six from injuries sustained during the evacuation and six from the stress of losing their homes and everything they own. Residents ranged in age from 65-95.
This home was more than two miles from the West Fork and had to be gutted to the ceiling.
Six of nine buildings at Kingwood College were destroyed. Thousands of students had to be relocated for more than a year while the buildings were disinfected from sewage contamination.
Sand Creek home more than 2 miles from the San Jacinto West Fork during Harvey after Lake Conroe Release.
Evac photo along Hamblen Road the morning after the Lake Conroe release.
Union Pacific Railroad Bridge over West Fork knocked out for months.
US59 southbound lanes were undercut by scouring, partially the result of the Lake Conroe release. TxDoT spent $20 million and 11 months repairing them. During that entire time, the average commute increased an hour each day for people trying to cross the river in rush hour.
To play video, click here. 110 homes out of 250 in Kings Forest flooded. This video shows the trash piles days after Harvey. All of these homes were more than two miles from the West Fork. Thousands of other homes between these and the river had their recreational value destroyed.
River Grove Park was covered with more than 4 feet of sand. Most it closed for almost a year. Parts of it are still unusable including the boat dock, which is the only public ramp in Kingwood.

And then, consider Kingwood High School which flooded to the second floor. Four thousand students had to be bused to another high school an hour away for seven months. Students from the two schools shared the same building but in different shifts.

Kingwood High School after the Lake Conroe release.

How You Can Help

Send me your best Harvey pics. Use the Submissions page of this web site. Understand that you give ReduceFlooding.com the right to publish your images. Let’s show Commissioner Meador how the Lake Conroe release interfered with recreation in our community.

Posted by Bob Rehak on 1/10/2020, with grateful thanks for the contributions from dozens of residents too numerous to mention

864 Days since Hurricane Harvey

West Fork Mouth Bar Dredging Set to Start As TWDB Considers Grant to Extend Program

On December 30, 2019, the City of Houston issued a Notice To Proceed (NTP) for debris removal services. Specifically, that means the large silt deposit at the confluence of the West Fork of the San Jacinto River and Lake Houston. The area is commonly known as the “mouth bar.” See below.

Mouth Bar of the San Jacinto West Fork looking upstream. Picture from 12/3/2019.

Mechanical, Not Hydraulic Dredging

The City hired DRC Emergency Services, LLC (DRC) under an existing contract to begin mechanical dredging of the mouth bar “this week,” according to Houston Mayor Pro Tem Dave Martin.

Mechanical dredging differs from hydraulic dredging. With hydraulic dredging, contractors continuously pump sediment from the river to a placement area onshore via long pipelines. With mechanical dredging, they scoop it out of the river and dump it on barges. Then they ferry the barges to the placement area where trucks transport the sediment to its final location.

Hydraulic dredging takes less time once started, but the prep can take months. Mechanical dredging takes longer, but can start immediately.

The City will begin the hydraulic dredging with $6 million of FEMA money left over from Hurricane Harvey debris removal funds. The Texas Division of Emergency Management and Governor Greg Abbott allocated that money specifically for Lake Houston and approved the remaining funds for mouth-bar dredging.

Two-Phase Grant

Next week, another $30 million should become available to extend the program. SB500 earmarked that money for dredging of the San Jacinto East and West Fork Mouth Bars. The Texas Water Development Board (TWDB) will consider Harris County’s grant application. Approval is expected.

The grant application proposes removing sediment in two distinct phases:

  1. Near and at the mouth bar on the West Fork of the San Jacinto River
  2. In the East Fork of the San Jacinto River AND other locations in Lake Houston.
Mouth Bar on East Fork San Jacinto grew 4,000 feet since Harvey.

Phase-One Funding and Objectives

To complete Phase 1, Harris County proposed taking $10 million of the $30 million to provide a total $16 million for DRC dredging operations.

Phase 1 should remove a minimum of 400,000 cubic yards (CY) of material in eight to twelve months. The Army Corps of Engineers previously removed 500,000 cubic yards from the West Fork Mouth Bar for $17 million in about three months.


During Phase 1, the County will begin some activities for Phase 2. They include:

  • Hydrographic surveys of the West and East Forks, and Lake Houston
  • Development of plans and specifications
  • Identification and permitting of additional disposal sites
  • Competitive bidding

Since the TWDB grant money can only be used for dredging, Harris County will pay for the activities above out of the 2018 HCFCD Bond Program. The fund allocated $10 million for dredging in Lake Houston.

Phase-2 Funding and Objectives

The remaining $20 million from the $30 million TWDB grant will go toward Phase 2 dredging.

During Phase 2, Harris County, City of Houston (COH), HCFCD, SJRA, and Coastal Water Authority (CWA) will develop and execute a plan for the COH or CWA to assume all long-term dredging operations on Lake Houston.

The County does not intend to assume long-term responsibility for maintenance dredging of a City property, i.e., Lake Houston.

TWDB Meets Next Week to Approve Grant

The Texas Water Development Board (TWDB) will meet on Thursday, January 16, 2020, to approve the $30 million grant. “We are in the final stages of agency approval to continue dredging the lake and river,” said State Representative Dan Huberty. His amendment to SB500 last year dedicated the money for dredging this area. “By approving this amount, the legislature as a whole made a clear and concise statement that Lake Houston and the San Jacinto River are vital resources for the entire region and must be maintained.”

SB500 was a supplemental appropriations bill. The grant itself will technically come from the new Texas Infrastructure Resiliency Fund, created last year by SB7. Senator Brandon Creighton authored SB7.

Harris County Engineer John Blount submitted the grant application to TWDB in late December after receiving approval from County Commissioner’s Court.

“Due to the urgency of this issue, multiple entities worked together to craft a plan that could be executed immediately, allowing the first phase to begin as soon as possible,” said Huberty.

Kudos Go To…

“I would like to thank everyone who has worked to create the final grant program under the supplemental funds we received from the Legislature,” said Huberty. “It would have not been possible without Governor Greg Abbott, Lieutenant Governor Dan Patrick, Speaker Dennis Bonnen, former Appropriations Chairman John Zerwas, Senate Finance Chairwoman Jane Nelson, State Senator Brandon Creighton, Chief Nim Kidd, Mayor Sylvester Turner, Chief Recovery Officer Stephen Costello, Harris County Commissioner’s Court, Harris County Engineer John Blount, Harris County Flood Control District Executive Director Russell Poppe, Harris County Flood Control District Deputy Director Matt Zeve, Houston Mayor Pro Tem Dave Martin and many more.”

To View TWDB Board Meeting Live

Tune in to the live TWDB Board Meeting next Thursday, January 16, 2020 at 9:30 AM by visiting: http://texasadmin.com/tx/twdb/.

Posted by Bob Rehak on 1/8/2019

863 Days since Hurricane Harvey and 111 since Imelda