Batches 1 and 2 of Cypress Creek Major-Maintenance Projects Completed, More to Come

Harris County Flood Control District (HCFCD) has essentially completed Batches 1 and 2 of Cypress Creek major maintenance projects, according to District spokesperson Karen Hastings. On 9/12/22, I photographed the freshly repaired and reseeded channel K131-00-00 (Spring Gully) at Cypresswood Drive, one of the last projects in Batch #1. See the pictures below.

Looking NW at K131-00-00 (Spring Gully) across Cypresswood Drive in foreground. Location is about a block west of TC Jester.

Such projects typically involve desilting. That involves removing accumulated sediment that reduces the conveyance of the channel.

Same tributary from a vantage point a little farther upstream. Looking NW.
At the split, you can see that repairs extend farther upstream. Spring Gully goes toward the right; Theiss Gully to the left.

Even though maintenance on Spring Gully may be complete for the time being, additional projects are in the works to provide even more flood relief to the area.

TC Jester Stormwater Detention Basin

Among them is the capital improvement project below. Note the two red ovals in the photo. They loosely represent the locations of what will become two large detention basins on either side of TC Jester.

Looking SE across Cypresswood Drive. TC Jester cuts across Cypresswood in the upper left and continues S between the circles.

Looking SE toward TC Jester in upper left. HCFCD has a head start on a detention basin thanks to an E&R Contract.

E&R Contract

E&R stands for Excavation and Removal. HCFCD has owned this property and the property across TC Jester for years. Knowing that someday a detention pond would be built here, HCFCD entered into an E&R contract with a dirt company. Such contracts give dirt companies the right to excavate the dirt and haul it away for pennies a truckload. The company then makes its money by selling the dirt at market rates.

Such contracts also create a quadruple-win situation.

  • Taxpayers get dirt removed virtually for free.
  • HCFCD gets a head start on excavation.
  • The hauling company reduces its costs.
  • Home- and road-builders reduce their costs.

The main restriction: excavated dirt must be taken outside of the floodplain.

The main drawback: If the market slows, so does excavation.

This contract is very similar, if not identical to the one with Sprint Sand & Clay on the Woodridge Village property in Montgomery County. There, HCFCD hopes to more than double the stormwater detention capacity on the site.

Crenshaw Earmark Will Accelerate Construction

U.S. Congressman Dan Crenshaw obtained a $9.9 million earmark earlier this year to help build a stormwater detention basin near TC Jester.

Crenshaw is also seeking another $15 million next year to expand stormwater detention basin capacity in the area.

Area shown in photo above with E&R contract is approximately 40 acres. HCAD has owned this since 2003.
Area east of TC Jester is almost 100 acres. HCAD has owned this since 2015. First phase of expansion will include light blue area.

Together, the projects will mitigate the risk of future riverine flooding by providing a safe place to temporarily store stormwater runoff. That will reduce both the size of the floodplain and the water level within it.

Every cubic yard of dirt removed creates room for a cubic yard of stormwater runoff.

Crenshaw and HCFCD say that approximately 2689 structures are located nearby in the existing 100-year floodplain. The proposed detention basin east of TC Jester could reduce stormwater elevations in a 100-year storm by half a foot. The first phase will remove 87 structures from the 100-year floodplain. When complete, the full detention basin will remove 271 structures from the existing floodplain. 

Spending this money now should save money in the long run – money that would otherwise go to more costly post-disaster recovery programs. 

Looking east over TC Jester toward area where HCFCD will build first phase of first detention basin. Photo taken 7/24/21.

More Major Maintenance and Capital Items

In addition to that, HCFCD just started its third batch of major maintenance projects in the Cypress Creek Watershed. HCFCD also expects a fourth and fifth batch. Altogether, HCFCD built $60 million into the 2018 flood bond for Cypress Creek maintenance projects. (See Project CI-012).

Separately, Crenshaw has also requested another $8.25 million to begin building the planned Westador Stormwater Detention Basin farther east along Cypress Creek at Ella Blvd.

None of these projects will provide an instant fix for the entire Cypress Creek watershed. But together they will reduce risk in areas along it.

Posted by Bob Rehak on 9/15/22

1843 Days since Hurricane Harvey

Dems Deprive Republican Precincts of Services

Late in the afternoon on 9/13/22, my phone started blowing up. Frantic callers asked, “Are you watching Commissioners Court?” I wasn’t unfortunately. I was working on a post about the completion of a flood-mitigation project. But my priorities quickly changed when I learned that the three Democrats (Garcia, Ellis and Hidalgo) voted – as a block – to take take “no action” on 32 separate projects. Each will deprive residents of Precincts 3 and 4 of services.

Adrian Garcia, Rodney Ellis and Lina Hidalgo removed 32 items from the 8/13/22 Harris County Commissioners Court Agenda that would have helped residents of Precincts 3 and 4.

The brazen no-action votes, led by Precinct 2 Commissioner Adrian Garcia, were in retaliation for Republican commissioners walking out of a vote that would have allowed Democrats to increase taxes at a time when rising inflation makes larger tax bills doubly difficult.

A quarter of the no-action votes directly targeted residents. The other three-quarters target companies that provide services that benefit residents, such as engineering companies that improve drainage.

Targeted items included residents’ community center wellness classes, maintenance, flood-rescue equipment, roadway improvements and drainage projects.

Violating Historical Norms

By agreement and tradition, historically, Harris County Commissioners do not interfere with each others’ business. So this sets a dangerous precedent in which one party weaponizes its majority to punish the opposition’s constituents. Here’s what happened.

Ramsey and Precinct 4 Commissioner Jack Cagle boycotted the meeting so that the Court would not have sufficient votes to raise taxes. In retaliation, Commissioner Adrian Garcia, aided by Commissioner Rodney Ellis and County Judge Lina Hidalgo, pulled dozens of Precinct 3 and 4 items from the agenda.

Commissioner Ramsey said in a press release that, “This is retaliation against Harris County residents at its lowest level. It punishes residents because they disagree about having a responsible fiscal budget. It’s childish and embarrassing for the Court and Harris County.”

Ramsey and Cagle have tried for several months to engage their Democratic counterparts in substantive budget discussions with little luck. The Democrats even rammed through a $1.2 billion bond proposal with no details except for a lopsided allocation plan that gave about 40% more to Democratic precincts.

Previously, Commissioners have agreed to respect the boundaries of one another’s precincts. “Today’s action is the latest example of Precinct 3 residents being stripped of services by the current Court,” said Ramsey.

Ramsey’s allusion to “latest” referred to a redistricting plan that left Ramsey with 47% of the county’s unincorporated area to maintain with only 25% of the budget.

During redistricting, Garcia also tried to shift $191 million from Precinct 3’s Cedar Bayou flood-bond budget to areas within his newly redrawn precinct.

Ramsey’s Rebuttal to Dire Dem Predictions

At one point Lina Hidalgo threatened a government shutdown. “If we don’t adopt a budget today, there would be government shutdown in essence,” she said at 35:40 into the 5-hour video.

Said Ramsey, “Judge Hidalgo and others would have you believe that since there was not a quorum at today’s Commissioners Court, the budget will fail. In reality, the lack of a quorum simply means that the maximum tax rate allowed by law – without voter consent – cannot be implemented. Instead, a smaller budget will be adopted.”

The difference between the two budgets is $100 million. Out of a $2.2 billion budget, that’s 4.5%.

Hidalgo counters that the extra money is needed for more “officers.” According to Ramsey, she referenced investigators and detention officers, “yet didn’t mention adding one patrol officer” who could combat street crime.

Hidalgo also threatened that if the maximum budget and tax rate aren’t passed, 180 flood projects that “…affect the lives of every single resident in Harris County” will be jeopardized. But the bond pays for those projects, and the difference between the two budgets for flood control is only $14 million. That’s .6% of the HCFCD’s budget. And Commissioners Ramsey and Cagle volunteered $7 million each from their precinct budgets to make up the difference.

Finally, Judge Hidalgo asserted that not passing the Voter-Approved-Rate budget instead of the No-New-Revenue budget would dramatically affect the Harris Health System. The difference between the two budgets is less than 2%. And Ramsey points out that many of the Health System’s requests are for capital investments which are not even a part of these budgets at all.

On-Call Engineering Contracts Delayed by Dems

So which projects did Dems pull from the agenda? Let’s start with retainer fees for on-call engineering in Precincts 3 and 4. The numbers below refer to agenda items. See full descriptions here.

  • #43 Pape-Dawson Consulting Engineers, Inc. for Precinct 3
  • #44 Volkert, Inc. for Precinct 3
  • #45 Cascade Civil Services, LLC for Precinct 3
  • #49 HVJ Associates, Inc. for Precinct 4
  • #52 Eneval, LLC for Precinct 4
  • #53 Volkert, Inc. for Precinct 4

Engineering Contracts for Specific Projects Also Delayed

In addition, the Dems agreed to delay approval of engineering contracts or contract amendments for specific projects in Precincts 3 and 4..

  • #51 Request to amend a contract Isani Consultants, L.P. for Professional Engineering Services relating to Stuebner Airline Road Segment C in Precinct 3.
  • #55 Approval of a contract with Edminster, Hinshaw, Russ and Associates, Inc. d/b/a EHRA to develop a Master Plan for improvements to Burnett Bayland Park in Precinct 4.
  • #67 Approval of an amendment to a contract with Huitt-Zollars, Inc. for improvements to Atascocita Area Trails Phase 2 in Precinct 3.
  • #76 Approval of Interlocal Agreement with City of Tomball to construct improvements to Nabors Parkway between Highway 249 and Holderrieth Road in Precinct 4.
  • #114 Approval of a contract with HNTB Corporation for engineering and landscape architecture services for a Road and Drainage Master Plan, Precinct 4.

Bizarre Delay

For unknown reasons, the Dems also voted to pull the following from the agenda:

  • #119 Request for approval to change the names of several projects in Precinct 3.

Delaying Release or Retention of Financial Surety

The following motions relating to approval of the release or retention of financial surety from developers were also taken off the agenda.

  • #123 Grand Oaks Section 9 in Precinct 4.
  • #124 Breckenridge West Section 7 in Precinct 3.
  • #125 Breckenridge West Section 10 in Precinct 3.
  • #126 Bridge Creek Section 2 in Precinct 3.
  • #127 Bridgeland Creek Parkway in Precinct 4.
  • #128 Bridgeland Sec 44 in Precinct 3.
  • #129 Bridgeland streets in Precinct 4.
  • #131 Groves Section 35 in Precinct 3.
  • #132 Groves Section 36 in Precinct 3.
  • #133 Newport Section 7 Partial Replat #3 in Precinct 3.
  • #134 Newport Section 7 Partial Replat #4 in Precinct 3.
  • #135 Windrow Section 3 in Precinct 4.

Delaying/Denying Services Directly Affecting Public

The items that most directly and immediately affect residents include the following. Garcia, Hidalgo and Ellis took each off the agenda.

  • #155 Approval to negotiate an agreement for surveying as needed in Precinct 3.
  • #160 Approval to convert Sam Houston Tollway Segment #3 in Precincts 3 and 4 to an all-electronic roadway.
  • #278 Approval to construct pedestrian trails along a drainage ditch of Brays Bayou under Addicks Clodine Road Bridge in Precinct 3.
  • #291 Renewal of 1-year contract for exercise classes in Precinct 3.
  • #342 Approval to bid reinforced concrete pipe, saddle inlets and related items for Precinct 4.
  • #343 Approval to bid asphalt roadway rehabilitation for the Western Trails Subdivision in Precinct 3.
  • #351 Approval to bid airboat and trailer purchases for Precinct 3.
  • #352 Approval to bid passenger buses for Precinct 3.

Most Troubling Item Cancelled, Not Just Delayed

#351 is especially concerning because the airboats would presumably be used for rescue operations during flooding…something the Lake Houston Area remembers all too well. The Dems outright cancelled that; they didn’t just delay it.

Watch the meeting and form your own opinions. Apocalyptic predictions take up the first three hours and fifty minutes. Garcia then starts listing the agenda items he wants to kill or take off the agenda.

Posted by Bob Rehak on 9/14/22

1842 Days since Hurricane Harvey


Batch 3 of Cypress Creek Major Maintenance Projects Ramping Up

Harris County Flood Control District has essentially completed the first two batches of major maintenance projects along Cypress Creek tributaries and is ramping up for the third, according to District spokesperson Karen Hastings.

Current Batch to Cost about $10.8 Million

Construction costs for Batch 3 should total about $10.8 million. Batch 3 includes 11 channels. The projects within them will span 5.8 miles.

Batches 1-3 include channels within the Cypress Creek watershed for which the Flood Control District already has property rights. They were previously developed and altered. They do not generally include natural channels.

Overview of three batches completed or started to date. From HCFCD presentation on Project CI-012.

Below is a general list of the types of maintenance needed on these channels. However, not every channel will need all the types of maintenance listed.

Desilting is the removal of sediment deposited in channels after multiple rain events. The sediment can restrict the conveyance of channels leading to flooding. See below.


Location of Batch 3 Projects

Location of first project in Batch 3 circled in red. See photos below.

Photos Taken September 12, 2022

Looking west across K-124 at southern end of project. Street is Bridgeview Lane.
Looking NW (upstream) across Bridgeview Lane.
Father up the channel, still looking NW, at the current limit of construction. Because of the proximity of homes, it would be difficult to widen this channel if that became necessary in the future.
Looking back toward SE from NW limit of construction several blocks up.

Altogether, projects such as this one will total almost 20 miles in Batches 1-3 alone. That should help reduce flood risk throughout the Cypress Creek watershed. Estimated completion for Batch 3 construction is Summer 2024.

12 Major Maintenance of Cypress Creek and Tr
From HCFCD’s Active Construction Project page associated with Project CI-012, Major Maintenance of Cypress Creek and Tributaries.
Two More Batches to Follow

But the major maintenance won’t stop there. HCFCD expects at least two more batches. The District will separately design each and put each out for construction bidding. Batch 5 will include major maintenance at multiple sites along Cypress Creek itself. 

According to the March 2021 Flood Bond Update, HCFCD had allocated $60 million for all batches of Project CI-012.

Posted by Bob Rehak on 9/12/2022

1840 Days since Hurricane Harvey