Northpark Culvert Installation Resumes

Northpark culvert installation resumed in a major way last week.

For several months, utility conflicts stalled installation of the 6’x8′ box culverts down the center of Northpark Drive. During preparation of the center ditch, contractors found gas lines buried at insufficient depth.

With those conflicts now resolved, according to Project Manager Ralph De Leon, installation of the box culverts can now resume. When contractors complete the culverts, dirt will be placed on top of them, and then two lanes of pavement on top of the dirt. The result will be a Northpark Drive that expands inward instead of outward. It will create three lanes in each direction…that should not flood like the thoroughfare currently does.

The expansion project has two primary goals:

  • Get more people in and out of Kingwood faster…
  • …in all weather conditions, even when other thoroughfares are cut off by flooding.

During Hurricane Harvey, West Lake Houston Parkway, Hamblen, Kingwood Drive, and parts of Mills Branch Road were all blocked by rising floodwaters.

Pictures of Installation Progress as of 4/15/24

Since my last post on 4/8/24, contractors completed installation of the culvert at Parkwood Baptist Church and are working their way west past Russell Palmer Road. Today, they were working in front of Shipley’s Donuts.

Looking E. Northpark culvert installation west of Russell Palmer Road near top of frame.
Looking E at Northpark culvert installation. Heavy equipment lifting massive section of culvert to place in hole.
Once men finish prepping the hole in the background…
…step and repeat for almost another mile to 494.

In Other Northpark News

Entergy managed to install five more power poles in the last week. That brings their total to nine in four years.

The new power poles sit back farther from the street. That will create room for four more lanes of traffic adjacent to the bridge that will go over the railroad tracks at 494. The four include two inbound turn lanes and two outbound turn lanes to/from 494.

Project managers first notified Entergy of the need to move the poles in 2020. Construction experts tell me the project could have easily been completed by now.

Not much new has happened at the entry ponds at 59. Heavy rains a week ago have the bottoms covered with water.

Looking west at area that will become the North Pond. Parts of new turn lanes are already being used, reducing traffic congestion somewhat.
Looking SW at South Pond
More culvert awaiting installation which will carry excess stormwater between ponds and Ditch One.

See the route below. It will go behind the businesses on the north side of Northpark until reaching the Kingwood Diversion Ditch and Bens Branch.

Northpark Drive drainage improvements

That pretty much does it for visible progress during the last week.

For More Information

For more information about Northpark expansion, visit the project pages of the LHRA/Tirz 10 website. Or see these posts on ReduceFlooding:

Posted by Bob Rehak on 4/15/24

2421 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Why Flood Risk Increases During Construction

Pictures taken of a new Huffman development after a 3.75-inch, 2-year rain last week illustrate why flood risk increases during construction compared to other phases of a project.

Aerial images taken over Sila, west of the Huffman-Cleveland Road, show:

  • Cleared land that accelerates runoff and decreases infiltration
  • Partially constructed stormwater detention basins
  • Trenches not yet consistently sloped
  • Rampant erosion
  • Workers pumping water out of one flooded area under construction only to flood another

Friendswood took more precautions with the 553-acre Sila than most developers take with their projects.

Regardless, despite their best intentions, a 2-year rain still overwhelmed them in places. Let’s look at examples of each point above.

Accelerating Runoff, Decreasing Infiltration

Natural ground cover slows the rate of runoff. Removing the ground cover lets stormwater flow faster.

Contractors also grade the land to create consistent slopes for roads and storms drains. That can eliminate little ponds, pockets of wetlands, and other natural catchments that slow water down.

Construction clearing for Sila in Huffman
First phase of Friendswood’s Sila Development in Huffman. Looking east toward St. Tropez at top of frame across Huffman-Cleveland Road.

I took these pictures just hours after the rain stopped. Notice how fast the runoff accumulated, even without storm drains.

Reverse angle looking west. Note water rapidly collecting and running off cleared area compared to forested area.

Partially Constructed Mitigation Facilities

Stormwater detention basins collect accumulated runoff and later release it at slower pre-development rates. Thus post-development runoff rates equal pre-development rates. At least if everything is done correctly.

But what happens when a large rain slams you before you complete the detention basins?

Partially completed Sila detention basin.

Trenches Not Yet Consistently Sloped

During work in progress, like this, trenches may not be consistently sloped. In the picture below, water flowed downhill from left to right. A swale caught most of the runoff. And a silt fence backstopped it. Regardless…

Because the swale was not consistently sloped toward the top of the frame, stormwater overflowed onto a neighbor’s property.

Rampant Erosion

Backslope interceptor systems that reduce erosion on the sides of ditches and basins have not yet been built here. Neither has grass been planted on the side slopes of those ditches and basins. The result: rampant erosion that can clog ditches and streams, and reduce the capacity of basins.

Note silt in stormwater detention basin.

Workers Saving One Area Only to Endanger Another

The first three shots below show the partially completed detention basin and workers scrambling to expel the rapidly accumulating runoff.

Workers pump water out of the pond into a ditch.
Note the pumps washing dirt into the ditch.

From there, water raced downslope toward the East Fork of the San Jacinto.

But the high flow from the pumped water found a way around one set of rock gabions and destroyed another.

That turned the outfall for a neighboring ditch (right of greenish pond above) into a mass of muck. From there, the muck flowed toward the river.

Muck moves toward East Fork San Jacinto beyond top of frame.

Could Have Been Worse

I didn’t see any homes that flooded on this day. Muck did flow into a few yards and across roads. And the outfall to a neighborhood drainage ditch, which was just cleaned out, will have to be cleaned out again.

But no doubt, it could have been much worse. See below.

Contractors created a slight depression to keep water from rushing downhill into neighboring homes (top of frame).

It’s also worth noting that runoff from Sila must go through more than a half mile of forested wetlands before reaching the East Fork. That will slow the water down, capture some of the erosion before it reaches the river, and keep the sediment from reducing the conveyance of the river channel.

Construction always entails flood risk, especially large scale construction that can take years. But with the right precautions, large rains don’t have to spell disaster.

Posted by Bob Rehak on 4/14/2024

2420 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.

Trammell Crow Contractors Still Pumping Silty Stormwater into Street

The persistent after-hours pumping of silty stormwater from the Trammell Crow construction site into the street drains has been reported to Harris County Engineering for several months now. Despite warnings, the practice continues. The danger: accumulated silt in drain pipes and the river can reduce their conveyance, back water up in heavy rains, and lead to flooding.

One small development won’t be catastrophic. But the cumulative impact of hundreds could be.

For all those reasons, construction permits come with instructions to use things that retain and filter silty water such as berms, sediment basins and semi-permeable fencing.

Repeat Offender

In January 2024, contractors began clearing Phase II of an apartment complex on West Lake Houston Parkway without any of these safeguards. Because the complex lies just outside the City limits, Harris County Engineering is responsible for inspections.

They have visited the site numerous times and cautioned contractors about discharges of silty stormwater. At different times, the contractors installed silt fences and erected berms. They also built sediment basins and channeled excess stormwater to them.

On April 10th, the area received approximately 2 inches of rain. And yesterday, April 11, the contractors were pumping water back into the street THROUGH A PILE OF MUD. After quitting time. When inspectors wouldn’t be around. Again!!!

Caught on Camera

Michelle Chavez, a nearby resident, caught the action on camera.

39 second video by Michelle Chavez showing extent and source of pumping

Chavez also took several still photos.

Silty stormwater being pumped through open gate washing out driveway
Note mud on right being washed into street.
Pumping took place near sunset, around 8PM when County inspectors were unlikely to be present.
They appeared to be pumping water from unfinished, underground storm drains, but pumped it through mud. Photo by BR taken around 7PM on 4/11/24.

At least one local resident concerned about flooding reported the pumping to Harris County Engineering. He was told that Engineering would send an inspector out.

Sending Wrong Message: Will Sixth Time be the Charm?

This is the sixth story I have posted about stormwater-control issues at this construction site. See the previous five.

One wonders when the county will level a stiff fine or shut down this site. At this point the Harris County Engineering Department also has its reputation on the line. Tolerating such behavior sends a message to other developers that may be unsafe in the long run.

Posted by Bob Rehak on 4/12/24

2418 Days since Hurricane Harvey

The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.