7/7/25 – Most current Northpark expansion work has shifted west of Loop 494 out to US59.
Work had been underway to bore underneath the UnionPacific Railroad tracks in order to connect the drainage east and west of the tracks.
Looking west. 5′ diameter steel pipes are being forced under the tracks to convey stormwater from one side to the other.
However, workers in the “receiving pit” encountered more unplanned utility conflicts and work stalled.
Utility conflicts in the receiving pit west of the tracksare prohibiting installation of junction box for drainage.
The boring work on hold pending approval of a plan to remove the conflicts.
Removing Old Junction Box by Sonic
Meanwhile, the focus of work has shifted west. One storm-drain crew is working to remove an old drainage structure by the Sonic driveway. See pit in front of yellow excavator below.
Looking west. Storm sewer work near Sonic extends up and down the block.
Getting Ready for Fast-Track Paving
This week another crew will complete the sub grade in this same area from Whataburger to LP 494 in preparation for Fast Track paving.
Looking east at area in front of Sonic that will receive fast track paving.
Drainage Work in Center Will Soon Begin
Looking W from over US59. Old west bound lanes have now been removed. Before repaving, crews must install lateral drainage.
According to the Lake Houston Redevelopment Authority’s latest update, median work between I-69 and Whataburger will also include a detention pond equalizer pipe.
Looking east from over 59 at entry ponds.
Eastbound Inlets and Lateral Drainage
A storm-sewer crew will soon finish placing the inlets and laterals on eastbound Northpark from Anderson to Kings Mill.
Looking ESE over Anderson at bottom of frame. Northpark on left where inlet and lateral work is ongoing. This also shows construction work to date on the Enclave (center).
Loop 494 Paving and More
Work on new northbound lanes of LP 494 will continue in preparation for concrete pours on Wednesday and Friday during the week of 7/11.
Installation of new driveways on westbound Northpark from Sherwin-Williams to Extra Space storage will soon finish. That’s good news for those merchants. See below.
Looking E. Note new paving and driveways on left.
But getting into and out of the Exxon Station will require some exploration for a while.
To make room for extra lanes, the Exxon Station at Northpark and 59 will lose part of its driveway.
Here’s a three-week look-ahead schedule that tells you, weather permitting, what should happen when. Please note, however. The last item (illumination poles on south side of Northpark from Italiano’s to east end of project) has been delayed and will not happen as scheduled.
Posted by Bob Rehak on 7/7/25
2869 Days since Hurricane Harvey
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2025/07/20250707-DJI_20250707095849_0452_D.jpg?fit=1100%2C619&ssl=16191100adminadmin2025-07-07 15:31:022025-07-07 15:47:08Most Northpark Expansion Work Shifts West of Loop 494
7/6/25 – The closer you look at the two most recent 2018 Flood Bond Updates from Harris County Flood Control District – 2024 Year End and 2025 First Quarter – the more eyebrow-raising inconsistencies you see in accounting.
Last week, I reported how “funds remaining” in the 2018 Harris County Flood Bond mysteriously decreased by a billion dollars.
Today, let’s focus on inconsistencies from the other side of the ledger – “spending.” Spending has two main components: Spent + Remaining Work in Progress. That’s because contractually HCFCD must pay to finish work under contract.
Breaking down those two components reveals another published inconsistency totaling $461 million.
Together, the “spending” and “funds remaining” inconsistencies may exaggerate a crisis being used to justify defunding projects in all but Rodney Ellis’ preferred neighborhoods. They make it appear as though we are both spending money and depleting reserves faster than we really may be. It’s hard to tell because I no longer trust the published numbers.
The graphics below come from the two reports. They summarize both money already spent and the value of remaining work in progress. At the end of 2024, Spent + In Progress work totaled $3.245 billion.
So, HCFCD actually spent – out of pocket – only an additional $43 million in the first quarter. Not nearly enough to account for a $504 million increase in three months. Subtracting $43 million from $504 million means…
HCFCD is claiming “Work in Progress” increased $461 million during the first quarter. But where is it?
No Proof Shown for Spending Commitments
HCFCD’s previous management used to update “active projects on the District’s website monthly. That enabled reporters like me to verify where the money was going.
In sharp contrast, HCFCD’s new management no longer lists “active projects” on the District’s website.
The 2025 Q1 update contains no backup information that shows where $461 million is being spent.
Neither does the county’s purchasing website.
Nor did a review of all Commissioners Court agendas for the quarter.
Too much just doesn’t add up. I’m not saying there’s fraud. This could just be sloth, incompetence, disorganization, the world’s worst financial reporting or the work of someone’s clueless cousin. But these numbers are being used to make policy decisions.
Long story short: We need a state audit before Rodney Ellis dismantles the 2018 bond program beyond all recognition.
Write your state representative, state senator, the Governor and the Attorney General today. It’s your tax money. Make sure you get some value for it.
Posted by Bob Rehak on 7/6/2025
2868 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2025/07/Funds-Spent-Increase.png?fit=1100%2C733&ssl=17331100adminadmin2025-07-06 19:24:022025-07-07 08:01:27More Inconsistencies in HCFCD Bond Updates Demand State Audit
Examination of bond language that voters approved shows Ellis and his colleagues likely violated six provisions: 14 A, B, C, D, F, and G. Let’s examine each, starting with G.
Basis for Prioritization Distorted
Paragraph 14(G) specifies an “equitable” distribution of funds. Ellis “reminds” people constantly that bond language gives commissioners the right to prioritize projects. But he never mentions how he redefined the basis specified for prioritization.
Ellis uses a self-serving definition of “equity” instead of “equitable.” His race-based formula prioritizes social vulnerability instead of flood-risk and flood-damage reduction.
Open any dictionary and you will see that equitable means fair and impartial. That’s not Ellis. His self-serving formula penalizes areas that have higher flood risk than his and that have received no or little help from HCFCD.
Funds Not Used for Purposes Described
Paragraph 14(A) says that funds must be used only for purposes described.
Yet the bond came packaged with a heavily promoted list of projects, many of which are being defunded to pay for items that were not on the list.
Due to a lack of transparency and questionable accounting, it is unclear what the bond proceeds are being spent on. That may also violate 14(A).
Not Providing Benefits Throughout the County
Paragraph 14(B) says that projects will provide benefits throughout the county. Defunding all but the highest ranked “equity” projects will effectively create “funding deserts.” Remaining projects will not benefit taxpayers throughout the county.
Commissioner Tom Ramsey said, “This decision puts voter-approved funding of over $220 million in Precinct 3 at risk. It also threatens partnerships and matching funds from local, state, and federal agencies worth another $206 million. But the court voted to do just that, thus violating 14(B).
Bait-and-Switch
Paragraph 14(C) says that projects will include those described in the bond. But Ellis’ defunding will effectively kill many. Meanwhile, Ellis plans to fund others not in the bond. Promising one thing and delivering another is called bait-and-switch advertising.
The language in 14(C) was intended to focus HCFCD on delivering promised projects, not commissioners’ pet projects. But now, we are getting Ellis’ pet projects.
Rights of Way Endangered
Paragraph 14(D) says bond money will be used to purchase rights of way for the construction of future detention basins and channel improvements. The original bond list contained money to acquire land in the Little Cypress and Cedar Bayou watersheds.
But those projects fall below the cutoff in Ellis’ gerrymandering Equity formula. In the future, it may be impossible to purchase those rights of way. And without them, growth in those watersheds may doom another generation to flooding.
Slow-Motion Project Delivery
Paragraph 14(F) specifies that projects will be undertaken in an expeditious manner. But execution of the bond program has slowed dramatically under HCFCD’s current leadership.
Under the previous management team, HCFCD projects were launched quickly. Not so much anymore!
HCFCD bid only three projects in 2024.
Slow execution has resulted in inflation undermining the bond’s purchasing power. It is unconscionable given the project output under previous HCFCD management. But Ellis doesn’t seem concerned about the slowdown or impact of inflation, either.
In fact, faced with tight Federal deadlines on HUD projects, he gave HCFCD Director Dr. Tina Petersen another 2.5 months to figure out how his equity cuts would affect projects.
Fine Print vs. Voter “Takeaway”
There may be fine print in the bond language that gives Ellis a technical “out” on some of these points. But generally, fine print does not legally excuse advertisers from creating a false or misleading impression. And this bond was heavily advertised.
In advertising law, especially under Federal and Texas consumer-protection laws:
Overall Impressions Matter: Courts look at the net impression an advertisement conveys to a reasonable consumer. If the overall impression is misleading, disclaimers buried in fine print generally won’t cure it.
FTC Standards: The Federal Trade Commission explicitly states that disclosures must be clear and conspicuous. Disclaimers that consumers are unlikely to notice or understand do not meet FTC standards.
Texas Deceptive Trade Practices If overall impressions mislead consumers, disclaimers hidden in fine print typically won’t absolve liability. The Texas Attorney General’s office has a clear standard: fine print does not cure deception.
Courts Generally Do Not Accept Fine Print as a Shield: Judges typically base rulings on the takeaway of an average consumer at first glance, not careful study of fine print.
Fine print can clarify net impressions, but it does not excuse deception.
The Ballot Box Cure
On balance, I feel misled. But rather than sue, I plan to use my voice and vote in the upcoming election. That will likely produce results faster than the courts.
Posted by Bob Rehak on 7/5/2025
2867 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
https://i0.wp.com/reduceflooding.com/wp-content/uploads/2020/08/Ellis.jpg?fit=1200%2C809&ssl=18091200adminadmin2025-07-05 18:50:272025-07-05 22:50:22Ellis Equity Cuts Likely Violate Bond Language Approved by Voters
Most Northpark Expansion Work Shifts West of Loop 494
7/7/25 – Most current Northpark expansion work has shifted west of Loop 494 out to US59.
Work had been underway to bore underneath the UnionPacific Railroad tracks in order to connect the drainage east and west of the tracks.
However, workers in the “receiving pit” encountered more unplanned utility conflicts and work stalled.
The boring work on hold pending approval of a plan to remove the conflicts.
Removing Old Junction Box by Sonic
Meanwhile, the focus of work has shifted west. One storm-drain crew is working to remove an old drainage structure by the Sonic driveway. See pit in front of yellow excavator below.
Getting Ready for Fast-Track Paving
This week another crew will complete the sub grade in this same area from Whataburger to LP 494 in preparation for Fast Track paving.
Drainage Work in Center Will Soon Begin
According to the Lake Houston Redevelopment Authority’s latest update, median work between I-69 and Whataburger will also include a detention pond equalizer pipe.
Eastbound Inlets and Lateral Drainage
A storm-sewer crew will soon finish placing the inlets and laterals on eastbound Northpark from Anderson to Kings Mill.
Loop 494 Paving and More
Installation of new driveways on westbound Northpark from Sherwin-Williams to Extra Space storage will soon finish. That’s good news for those merchants. See below.
But getting into and out of the Exxon Station will require some exploration for a while.
Here’s a three-week look-ahead schedule that tells you, weather permitting, what should happen when. Please note, however. The last item (illumination poles on south side of Northpark from Italiano’s to east end of project) has been delayed and will not happen as scheduled.
Posted by Bob Rehak on 7/7/25
2869 Days since Hurricane Harvey
More Inconsistencies in HCFCD Bond Updates Demand State Audit
7/6/25 – The closer you look at the two most recent 2018 Flood Bond Updates from Harris County Flood Control District – 2024 Year End and 2025 First Quarter – the more eyebrow-raising inconsistencies you see in accounting.
Last week, I reported how “funds remaining” in the 2018 Harris County Flood Bond mysteriously decreased by a billion dollars.
Today, let’s focus on inconsistencies from the other side of the ledger – “spending.” Spending has two main components: Spent + Remaining Work in Progress. That’s because contractually HCFCD must pay to finish work under contract.
Breaking down those two components reveals another published inconsistency totaling $461 million.
Together, the “spending” and “funds remaining” inconsistencies may exaggerate a crisis being used to justify defunding projects in all but Rodney Ellis’ preferred neighborhoods. They make it appear as though we are both spending money and depleting reserves faster than we really may be. It’s hard to tell because I no longer trust the published numbers.
We need a state audit BEFORE defunding any projects.
Compare Reported Spending + Work in Progress
The graphics below come from the two reports. They summarize both money already spent and the value of remaining work in progress. At the end of 2024, Spent + In Progress work totaled $3.245 billion.
But during 2025 Q1, the comparable total rose to $3.749 billion.
Pretty impressive! Especially when you consider that it’s taken HCFCD seven years to spend $1.5 billion.
Now let’s subtract money already out the door so that we can focus on the “work in progress” component only. That’s where the mystery deepens.
HCFCD Spent Only $43 Million in Q1
HCFCD says it “spent” (past tense) $1.526 billion through the end of 2024.
But by the end of the first quarter, money spent had climbed to $1.569 billion.
So, HCFCD actually spent – out of pocket – only an additional $43 million in the first quarter. Not nearly enough to account for a $504 million increase in three months. Subtracting $43 million from $504 million means…
No Proof Shown for Spending Commitments
HCFCD’s previous management used to update “active projects on the District’s website monthly. That enabled reporters like me to verify where the money was going.
In sharp contrast, HCFCD’s new management no longer lists “active projects” on the District’s website.
The 2025 Q1 update contains no backup information that shows where $461 million is being spent.
Neither does the county’s purchasing website.
Nor did a review of all Commissioners Court agendas for the quarter.
Too much just doesn’t add up. I’m not saying there’s fraud. This could just be sloth, incompetence, disorganization, the world’s worst financial reporting or the work of someone’s clueless cousin. But these numbers are being used to make policy decisions.
Long story short: We need a state audit before Rodney Ellis dismantles the 2018 bond program beyond all recognition.
Write your state representative, state senator, the Governor and the Attorney General today. It’s your tax money. Make sure you get some value for it.
Posted by Bob Rehak on 7/6/2025
2868 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.
Ellis Equity Cuts Likely Violate Bond Language Approved by Voters
In Harris County Commissioners Court on June 26, 2025, Democrats voted 4:1 along party lines to reallocate all remaining money in the 2018 Flood Bond to projects that scored in the top quartile of Commissioner Rodney Ellis’ Equity Prioritization Framework.
That will defund all but a handful of projects that voters approved. Is that legal?
Examination of bond language that voters approved shows Ellis and his colleagues likely violated six provisions: 14 A, B, C, D, F, and G. Let’s examine each, starting with G.
Basis for Prioritization Distorted
Paragraph 14(G) specifies an “equitable” distribution of funds. Ellis “reminds” people constantly that bond language gives commissioners the right to prioritize projects. But he never mentions how he redefined the basis specified for prioritization.
Ellis uses a self-serving definition of “equity” instead of “equitable.” His race-based formula prioritizes social vulnerability instead of flood-risk and flood-damage reduction.
Open any dictionary and you will see that equitable means fair and impartial. That’s not Ellis. His self-serving formula penalizes areas that have higher flood risk than his and that have received no or little help from HCFCD.
Funds Not Used for Purposes Described
Paragraph 14(A) says that funds must be used only for purposes described.
Yet the bond came packaged with a heavily promoted list of projects, many of which are being defunded to pay for items that were not on the list.
Due to a lack of transparency and questionable accounting, it is unclear what the bond proceeds are being spent on. That may also violate 14(A).
Not Providing Benefits Throughout the County
Paragraph 14(B) says that projects will provide benefits throughout the county. Defunding all but the highest ranked “equity” projects will effectively create “funding deserts.” Remaining projects will not benefit taxpayers throughout the county.
Commissioner Tom Ramsey said, “This decision puts voter-approved funding of over $220 million in Precinct 3 at risk. It also threatens partnerships and matching funds from local, state, and federal agencies worth another $206 million. But the court voted to do just that, thus violating 14(B).
Bait-and-Switch
Paragraph 14(C) says that projects will include those described in the bond. But Ellis’ defunding will effectively kill many. Meanwhile, Ellis plans to fund others not in the bond. Promising one thing and delivering another is called bait-and-switch advertising.
The language in 14(C) was intended to focus HCFCD on delivering promised projects, not commissioners’ pet projects. But now, we are getting Ellis’ pet projects.
Rights of Way Endangered
Paragraph 14(D) says bond money will be used to purchase rights of way for the construction of future detention basins and channel improvements. The original bond list contained money to acquire land in the Little Cypress and Cedar Bayou watersheds.
But those projects fall below the cutoff in Ellis’ gerrymandering Equity formula. In the future, it may be impossible to purchase those rights of way. And without them, growth in those watersheds may doom another generation to flooding.
Slow-Motion Project Delivery
Paragraph 14(F) specifies that projects will be undertaken in an expeditious manner. But execution of the bond program has slowed dramatically under HCFCD’s current leadership.
Slow execution has resulted in inflation undermining the bond’s purchasing power. It is unconscionable given the project output under previous HCFCD management. But Ellis doesn’t seem concerned about the slowdown or impact of inflation, either.
In fact, faced with tight Federal deadlines on HUD projects, he gave HCFCD Director Dr. Tina Petersen another 2.5 months to figure out how his equity cuts would affect projects.
Fine Print vs. Voter “Takeaway”
There may be fine print in the bond language that gives Ellis a technical “out” on some of these points. But generally, fine print does not legally excuse advertisers from creating a false or misleading impression. And this bond was heavily advertised.
In advertising law, especially under Federal and Texas consumer-protection laws:
Courts look at the net impression an advertisement conveys to a reasonable consumer. If the overall impression is misleading, disclaimers buried in fine print generally won’t cure it.
The Federal Trade Commission explicitly states that disclosures must be clear and conspicuous. Disclaimers that consumers are unlikely to notice or understand do not meet FTC standards.
If overall impressions mislead consumers, disclaimers hidden in fine print typically won’t absolve liability. The Texas Attorney General’s office has a clear standard: fine print does not cure deception.
Judges typically base rulings on the takeaway of an average consumer at first glance, not careful study of fine print.
Fine print can clarify net impressions, but it does not excuse deception.
The Ballot Box Cure
On balance, I feel misled. But rather than sue, I plan to use my voice and vote in the upcoming election. That will likely produce results faster than the courts.
Posted by Bob Rehak on 7/5/2025
2867 Days since Hurricane Harvey
The thoughts expressed in this post represent opinions on matters of public concern and safety. They are protected by the First Amendment of the US Constitution and the Anti-SLAPP Statute of the Great State of Texas.